Data centers are emerging as large electricity consumers whose demand can be reshaped through workload scheduling. However, computing flexibility in behind-the-meter facilities does not automatically translate into electrically realizable power flexibility. Ignoring converter and network operating limits may cause converter overloads, protection trips, and interruptions to power supply and computing services. This paper proposes a converter-aware intraday scheduling methodology. First, a task-level mixed-integer linear formulation preserves synchronous training configurations and completion requirements, while Minkowski-sum aggregation and Shapley--Folkman convexification yield a linear inference-pool representation without unit-level binary variables. The latter admits a conditional relative relaxation-gap bound that decreases inversely with pool size. Second, a four-node electrical model links computing demand, on-site injections, and grid exchange to converter and network limits through lifted voltage variables and second-order cone relaxation. Finally, a mixed-integer model coordinates workloads, photovoltaic generation, energy storage, and grid purchases. Case studies show that electrical limits reshape scheduling and renewable utilization, while on-site resources reduce grid dependence. Under the studied conditions, fixed training cannot support full inference service within voltage limits, whereas coordinated scheduling achieves negligible inference shortage and passes verification against the original alternating-current model. These findings demonstrate the role of computing--electrical coordination in realizing the operational value of workload flexibility.

Closest papers

Nearest neighbours by meaning across the whole index.

Unlocking AI Data Center Interconnection Capacity Through Coordinated Grid and Data Center Flexibility

eess.SY ·2026-10-04 ·Rida Fatima, Xingpeng Li
similarity 0.66
Abstract

The rapid growth of AI data centers is creating concentrated electricity demands that can exceed available distribution network headroom and delay interconnection. This paper investigates whether capacity can be used effectively by coordinating flexibility on both sides of the interconnection. A day-ahead mixed integer second order cone programming framework maximizes feasible AI data center IT capacity using utility side conservation voltage reduction and network topology reconfiguration, together with data center workload shifting and reserve constrained uninterruptible power supply storage. Background feeder demand uses voltage dependent ZIP models, while the data center is modeled as constant power demand using Training, Inference, and Mixed workload profiles. A two-stage solution first maximizes interconnection capacity and then minimizes feeder losses for the retained capacity, with numerical relaxation screening. Studies on a 116-bus model derived from the IEEE 123-node feeder show that, at the constrained bus-60 connection point, grid side flexibility, driven almost entirely by network reconfiguration, increases feasible IT capacity by approximately 42.5-45.0%, while data center flexibility alone provides approximately 2.1-5.4% gains. Coordinated operation increases feasible IT capacity from approximately 10.5-10.6 MW under BASE operation to 15.3-16.0 MW, corresponding to gains of approximately 45.9-50.8%; the 16.0 MW Inference result is limited by the adopted UPS reserve requirement. Benefits are strongly location dependent and influenced by workload flexibility, deferral duration, PUE, UPS energy and reserve requirements, and feeder loading. Under a combined adverse operating condition, FULL capacity decreases by only 3.4% relative to the nominal Mixed case while retaining substantial additional capacity over BASE.

0.08

Minimizing Grid Interconnection Capacity Requirements for AI Data Centers: A Developer-Side Planning Framework with Onsite Resources and Workload Flexibility

eess.SY ·2026-08-29 ·Hassan Zahid Butt, Rida Fatima, Xingpeng Li
similarity 0.66
Abstract

Securing grid interconnection capacity has become a bottleneck for AI data center projects and can take longer than constructing the facilities themselves. This mismatch can delay deployment for years, making early interconnection planning essential. This paper develops ICP-AI, an interconnection capacity planning framework from a data center developer's perspective. The framework minimizes grid import capacity under a prescribed onsite investment budget while jointly sizing photovoltaic (PV) and battery energy storage system (BESS) resources and scheduling deadline constrained workload flexibility. A secondary refinement fixes the minimum grid capacity and selects the minimum-investment PV-BESS portfolio among solutions that achieve that capacity. The framework is evaluated using monthly composite stress profiles across varying temporal assumptions, load shapes, flexible load fractions, and deferral windows. Results show that interconnection capacity reduction depends strongly on the planning environment: at a $100M budget, it is about 6% for the high load factor baseline, exceeds 10% under monthly average solar availability, and reaches 13.3% for a more diurnal load. At a $10M budget, 5% flexible load with a 1 h workload deferral window reduces BESS capacity from 15.30 to 4.87 MWh while increasing capacity reduction from 4.43% to 4.84%. To test sensitivity to temporal compression, the model is also solved over the full 8,760 h chronology, which preserves the main capacity and flexibility trends. Overall, ICP-AI quantifies the interconnection capacity and infrastructure substitution value of workload flexibility, providing an investment-interconnection frontier to support capital allocation and early project planning in constrained grid environments.

0.12

Spatial LLM Workload Shifting Needs Foresight: Model Commitment for AI Data Center Operation under Power Grid Constraints

eess.SY ·2026-09-09 ·Bojun Du, Hongyang Jia, Tonghui Li, Qingchun Hou, Ze Wang +2 more
similarity 0.66
Abstract · 3 pages, 2 figures

AI data centers may face power supply shortages during certain periods, requiring operators to shift large language model (LLM) inference workloads spatially to maintain service rates. However, existing workload-shifting methods typically assume that any data center with sufficient computing resources can immediately serve shifted requests, which may lead to infeasible transfers and unserved demand. This letter proposes model commitment (MC), a mixed-integer linear programming framework that jointly schedules model deployment and cross-site request routing under power constraints and electricity-price signals. First, MC formulates the intertemporal coupling introduced by model replica loading. Second, it translates prefill and decode latency requirements into the amount of demand that each replica can serve. Case studies based on real-world data show that MC enables AI data center operators to achieve a 100% service rate under time-varying grid conditions and reduce total operating cost by 29.0%.

0.24

Steady-State Equivalent Circuit Model for Data Center Loads

eess.SY ·2026-08-18 ·Muhammad Hamza Ali, Peng Sang, Hyeon Woo, Hyein Kang, Sungyun Choi +1 more
similarity 0.65
Abstract

Planners currently represent data centers as aggregate constant-PQ or ZIP loads in steady-state interconnection and contingency studies. These aggregate models are computationally convenient. However, they obscure the electrical relationship between computational workloads, server utilization, and grid-side demand. They ignore the internal power-electronic conversion stages of IT loads and assume homogeneous workload distributions across the compute clusters. This hides operating-point-dependent converter losses and efficiency variations. We propose a steady-state equivalent-circuit model (ECM) for data centers, which explicitly builds circuit models for IT loads, power supply units, cooling, and auxiliary systems. For power supply units, the equivalent circuit model explicitly represents internal power-electronic conversion stages. For IT loads, we develop a utilization-dependent server power model, and we combine it with loss-aware ECMs of power supply units. This approach captures the grid-side impact of heterogeneous workload distributions while preserving compatibility with conventional power-flow analysis. We evaluate this data center ECM in large-scale transmission power flows, using Monte Carlo simulations under heterogeneous and homogeneous cluster utilization. In comparison with the fixed-efficiency constant-PQ model, the ECM predicts that the most stressed line exceeds its thermal limit in about 30% of Monte Carlo samples. The results further show that homogeneous server utilization overstates line-loading variability by 17%-46% relative to heterogeneous server utilization, depending on the intra-cluster workload correlation.

0.47

Grid Demand Flexibility Assessment of AI Data Centers via Batch Workload Temporal Shifting

eess.SY ·2026-09-29 ·Suntao Su, Liang Du, Shengyi Wang
similarity 0.65
Abstract · 5 pages, 5 figures, conference

The rapid growth of artificial intelligence (AI) data centers has introduced new challenges to power system operation. As their power demand becomes larger and more variable, quantitatively characterizing their demand flexibility is increasingly important for effective power system coordination. However, heterogeneous workload characteristics and resource requirements make this flexibility difficult to characterize directly. This paper proposes a framework for assessing the grid-compatible demand flexibility of AI data centers via batch workload temporal shifting. An averaging-based resource usage processing method is developed to map fine-resolution CPU, GPU and memory usage into unified time intervals compatible with power system operation. A workload temporal scheduling model is then formulated to shift batch workloads while preserving execution continuity, delay constraints, and server resource capacities, and is coupled with a utilization-dependent server power model to translate workload scheduling decisions into server power demand. Two complementary flexibility metrics are evaluated: short-term peak demand shaving and the maximum duration of sustained power reduction. Numerical results based on real GPU cluster traces demonstrate that workload temporal shifting can provide quantifiable and grid-compatible demand flexibility for AI data centers with limited disruption to computing workloads.

0.13

Robust Joint Planning of EV and eBus Charging Infrastructure with PV Self-Consumption under Demand Uncertainty

eess.SY ·2026-08-19 ·Biswarup Mukherjee
benchmark similarity 0.65
Abstract · This manuscript has been submitted for peer review

This paper presents a mixed-integer linear programming (MILP) framework for joint electric vehicle (EV) and electric bus (eBus) charging-infrastructure planning with photovoltaic (PV) self-consumption. The model co-optimizes charger siting, sizing, technology selection, eBus-to-depot assignment, and hourly charging schedules. A deterministic MILP is first formulated as a nominal benchmark and then extended to a scenario-based robust min--max formulation under vehicle energy-demand uncertainty. The robust model uses shared first-stage infrastructure decisions and scenario-specific operating decisions, and minimizes infrastructure cost plus the worst-case scenario operating cost through an epigraph reformulation. Soft-feasibility penalties quantify unmet charging energy, terminal state-of-charge (SOC) shortfall, and capacity violations under stressed scenarios. A 50-node case study shows that route-segment eBus demand and PV weighting alter charger deployment, technology mix, and grid import, while V2G enables hard-feasible robust operation at sufficiently large penalty weights. These results highlight that effective long-term infrastructure planning must simultaneously account for diverse vehicle fleets, operational strategies that adapt to different scenarios, and node-level constraints on charging capacity.

0.19

AI Data Centers Meet Electrical Grids: A Review of Power Challenges and Coordinated Solutions

eess.SY ·2026-10-06 ·Mariam Mughees, Yuzhuo Li, Yize Chen, Yunwei Ryan Li
survey similarity 0.65
Abstract

Artificial intelligence (AI) workloads are creating large, power-electronic loads whose effects on power systems depend on location, temporal variability, controllability, and interactions with other loads and resources. Annual electricity consumption alone cannot capture these effects. This review examines how AI data centers affect power systems stability, renewable-energy integration, and low-carbon planning by tracing the power-delivery chain from accelerators and workloads through rack converters, uninterruptible power supplies (UPS), storage, and microgrids to the transmission point of interconnection. Reported oscillatory events and multi-gigawatt load transfers highlight how facility responses can amplify disturbances, while programmable workloads and controllable power converters offer opportunities for demand flexibility. Challenges and mitigation strategies are organized across device, rack, facility, and power systems levels, spanning millisecond-to-year timescales. A bandwidth-matching framework relates disturbances to the response capabilities of mitigation resources. The review distinguishes computational energy efficiency from power systems and sustainability outcomes: lower energy consumption per token does not necessarily reduce peak demand, electrical disturbances, or carbon emissions. It examines how coordinated workload scheduling, grid-interactive UPS systems, storage, high-voltage DC distribution, and flexible interconnection can support reliability, efficiency, and decarbonization. Key research needs include dynamic load models, high-bandwidth telemetry, carbon-and grid-aware scheduling, and mechanisms for valuing flexible computational demand.

0.08

AI Inference-Aware Optimal Power Flow: Converting Token Requirements into Grid Flexibility

eess.SY ·2026-11-14 ·Qianyi Ma, Dawei Qiu, Xiao Liu
similarity 0.64
Abstract

The rapid growth, temporal variability, and geographic concentration of electricity demand from artificial intelligence (AI) inference can aggravate transmission congestion near data centers (DCs). The spatial and temporal flexibility of inference workloads offers an opportunity to alleviate this congestion: requests can be routed across DCs or deferred within users' quality-of-service (QoS) requirements. However, inference routing primarily considers graphics processing unit (GPU) availability, leaving this flexibility underused in grid operation. Using GPU measurements, this paper models inference latency and DC power consumption to quantify the flexibility available under users' time-to-first-token (TTFT) and inter-token latency (ITL) requirements. These models are then incorporated into an AI inference-aware optimal power flow (OPF) that coordinates inference routing and power system operation among DC operators, the transmission system operator, and inference users. By linking user requests, token generation at DCs, and electricity delivery through the transmission network, the formulation schedules inference workloads subject to both users' QoS requirements and transmission constraints. Simulations on the PJM system show that, compared with computing-based routing and with electricity price-based routing, coordinating inference routing with network operation enables growing DC electricity demand deliverable to be met at lower cost.

0.26