Time-reliability optimization of multi-pass underfill dispensing sequences on printed circuit boards: a schedule-dependent reliability model solved by a multiset-permutation binary-addition-tree algorithm

Wei-Chang Yeh

eess.SY math.OC ·submitted 2026-10-03 00:53 UTC · v1
unusual

Abstract

Multi-pass underfill dispensing couples cycle time with process reliability because the sequence determines the inter-pass flow times. This paper formulates a tri-objective multiset-permutation routing model that minimises nominal cycle time and additive duration variance while maximising reliability under hard- and soft-dwell policies; reliability combines pass, schedule-dependent flow and travel terms. Under independent durations and deterministic dwell thresholds, the variance measure equals the cycle-time variance under soft dwell and bounds it from above under hard dwell. A multiset-permutation binary-addition-tree algorithm enumerates the feasible routes without duplication and prunes prefixes by dominance. Six instances, including three BeagleBone Black benchmarks, yield reference Pareto fronts, the largest search space of $1.47 \times 10^{12}$ routes in 38 minutes on 20 CPU cores. Among simulated candidates, the nominally cost-selected routes incur maximum estimated excess costs of USD 0.0014 per board at the modelled duration variability and USD 0.0035 with it doubled. Round-robin dispatch is within 3.7 % of the reference optimum at the tested costs; NSGA-II and simplified swarm optimisation show at most 0.53 % observed cost regret while recovering about 30 % of the largest hard-dwell front. The framework quantifies sequencing trade-offs and heuristic decision regret; physical reliability prediction requires inspection-based calibration.

Comment
30 pages, 4 figures, 18 tables. Submitted to Reliability Engineering & System Safety. Supplementary code and data (solvers, instances, reference fronts, heuristic archives, validation outputs, one-command test suite) accompany the journal submission and are available from the author

Closest papers

Nearest neighbours by meaning across the whole index.

An Efficient Algorithm for the Quickest Path Reliability Problem

cs.DM ·2026-10-06 ·Majid Forghani-elahabad
similarity 0.53
Abstract

The quickest path reliability problem is to compute the probability that a given flow is transmitted along a single source-destination path within a given time limit. When a budget is imposed, path feasibility is jointly dependent on lead time, transmission cost, and capacity. Existing exact methods may require enumeration of all minimal paths a priori or examination of many partial paths that cannot be completed feasibly. In this paper, we propose an exact algorithm that generates the corresponding lower boundary state vectors without first enumerating minimal paths. Shortest-lead-time, least-cost, and widest-capacity information yield admissible destination-based bounds. Stronger capacity-aware bounds are derived from capacity-filtered subnetworks. These bounds allow early pruning of infeasible branches while keeping all solutions. The algorithm generates the exact complete set of lower bounds without any duplicates, and its correctness and computational complexity are proven.

0.26

ASCEND: Automated Shockproof Cost-Efficient Network Design

cs.NI ·2026-11-16 ·Taha ValizadehAslani, Vaibhav Phatarpekar, Cameron Brackmann, Bala Ramachandran
similarity 0.51
Abstract · Submitted to IEEE Transactions on Network and Service Management

Designing resilient and cost-effective IP network topologies over an existing physical infrastructure is a challenging combinatorial optimization problem, particularly at large scale and under extensive failure modeling assumptions. Traditional deterministic approaches struggle to jointly address resiliency against shock (large customer-impact outages) and implementation cost objectives when the number of candidate circuits grows quadratically with the number of sites to be interconnected. In this paper, we propose Automated Shockproof Cost-Efficient Network Design (ASCEND), a systematic design pipeline for IP core network optimization based on a two-level optimization framework. At the outer level, ASCEND uses Multi-Objective Particle Swarm Optimization (MOPSO) to select core sites and core circuits. Given a core design, the inner-level integral Multi-Commodity Flow (MCF) formulation selects edge circuits and maps both core and edge circuits onto optical (fiber/transport) paths while prioritizing resource disjointness and latency. Network designs are evaluated using two competing objectives: a performance cost capturing resiliency under probabilistic failure scenarios and an implementation cost. The performance cost incorporates an exponentially weighted vulnerability metric that explicitly penalizes infeasible configurations. Experimental results on multiple real-world networks demonstrate that ASCEND consistently identifies designs that outperform a manually engineered baseline in both resiliency and implementation cost.

0.28

Exact Multistate Reliability and Upgrade Design for Heterogeneous HBM Systems via Threshold-Pruned BAT

cs.AR cs.PFmath.OC ·2026-08-19 ·Wei-Chang Yeh
benchmark similarity 0.51
Abstract

High Bandwidth Memory (HBM) systems can exhibit partial service rather than only full service or complete isolation: a controller-visible service unit may deliver full, reduced, or zero bandwidth because of sub-channel isolation, lane remapping, or protection overhead. This paper develops an exact multistate reliability framework in which each service unit carries an arbitrary finite set of bandwidth states and reliability is the probability that aggregate delivered bandwidth meets a demand. The binary k-out-of-n model is recovered as a special case, while closed-form binary-mapping error relations quantify mean-bandwidth distortion and provide a screening test for the simpler abstraction. For exact single-threshold evaluation a threshold-pruned multistate Binary-Addition-Tree (TP-mBAT) algorithm is proposed. It is deliberately regime-specific: fixed-grid dynamic programming is preferable on a compact common grid, where a 16-unit commensurate control required 273 pruned-DP updates versus 362,506 TP-mBAT node visits. On a reproducible 14-unit incommensurate benchmark, TP-mBAT is compared against a dynamic program carrying the same threshold rules, so that no baseline is weakened. Both expand the same state space, 6,862 nodes against 6,861 updates, and the separation lies entirely in retained state: 17 traversal entries against 412,121 probability states at central demand, reducing measured peak storage from 25.02 MB to 1,152 B. An exact probability-transfer sensitivity identifies when moving mass from a degraded state to a higher-bandwidth state changes system success, and a reserved-unit floor model admits a third exact pruning rule that is vacuous without such floors. A latent package-state mixture captures shared stress, where ignoring dependence overstates reliability by 8.73 percentage points.

0.28

Optimal Seat Movement Strategies Among Modular Bus Units

cs.CE math.OC ·2026-11-12 ·Shiyue Wang, Yuhao Liu, Zhibin Chen, Mingyang Pei, Changhong Lu
similarity 0.50
Abstract

Movable seats enable passengers to transfer between coupled modular bus units while remaining seated, but require physical reconfiguration that existing modular transit models largely abstract away. We model seat reconfiguration as a colored generalized sliding-tile puzzle on the physical track graph, capturing simultaneous movements, seat indistinguishability within destination groups, and vertex, edge, and corner-following conflicts. A lexicographic objective minimizes makespan first and then the sum of costs (SoC), which penalizes movements and waiting at non-target positions. We develop an exact time-expanded mixed-integer linear programming formulation and a Boundary-Sequence Dynamic Programming (BSDP) algorithm. BSDP decomposes the problem at single-edge module interfaces and coordinates local schedules through compressed boundary-crossing sequences, provably preserving feasibility and optimal costs. On two- and three-module benchmarks, BSDP achieves mean per-instance speedups of 3.24x and 6.30x over Gurobi, respectively. In fixed-horizon tests with four to seven modules, both methods start from identical greedy schedules and receive a 300 s budget. BSDP obtains lower final SoC than Gurobi on 197 of 200 instances and ties on three, reducing mean final SoC by 17.93%-69.07% across the four size classes. Geometry sensitivity and ablation studies further clarify the contribution of boundary compression to computational performance. The framework links seat reconfiguration to the timing and operational cost of modular bus decoupling.

0.43

PPAPlace: Differentiable Cross-Stage Objectives for Chip Placement Optimization

cs.LG cs.AIcs.AR ·2026-08-13 ·Ruogu Chen, Jie Han
publishedcode/data similarity 0.50
Abstract · 9 pages, 4 figures, 6 tables, accepted at ICCAD 2026

Macro placement significantly affects a chip's post-route performance, power, and area (PPA). Most placement methods optimize half-perimeter wirelength (HPWL) as the primary objective. However, recent benchmarking shows a near-zero correlation between HPWL and post-route timing metrics such as the worst negative slack (WNS) and total negative slack (TNS). As a result, all six evaluated artificial intelligence (AI) placers degraded PPA relative to the hierarchical baseline. Recent efforts have tried to train cross-stage predictors to close this gap. However, existing methods focus on macro-only representations and use pre-route metrics as training labels. A label fidelity study of ten circuits at four design flow stages reveals that HPWL and pre-route timing poorly reflect final post-route timing rankings. In contrast, post-global-routing achieves the best balance between final timing fidelity and label generation cost-effectiveness. Based on this finding, PPAPlace is a timing-driven differentiable surrogate predicting post-route PPA from macro and standard-cell placements. The surrogate is a dual-stream predictor that combines graph attention over the chip netlist with spatial convolution over the placement grid. It is trained on post-global-routing labels. The predicted WNS and TNS gradients flow end-to-end back to cell coordinates. PPAPlace exploits these gradients in two ways: as a co-objective injected into an analytical placer's optimization loop (PPAPlace-CoOpt), and as a post-placement refinement step that adjusts macro positions via projected gradient descent (PPAPlace-Refine). On five ChiPBench test circuits excluded from training, PPAPlace improves average WNS and TNS by 22\% and 51\% over the hierarchical baseline while preserving power and routability, using the same predictor without test-circuit retraining. Code is available at https://github.com/ValleyC/PPAPlace.

0.53

Minimizing Bottleneck Overload Risk in Online Edge Task Placement under Workload Uncertainty

cs.DC ·2026-11-03 ·Lei Wang, Winston K. G. Seah, Gang Xu, Xiaodong Xu, Baoqi Huang
similarity 0.50
Abstract · 15 pages, 2 figures, 7 tables

In edge computing, tasks must be placed on servers of finite capacity before workloads are realized, often with only workload means and variances known. An assignment balanced on expected load can still leave a server with more fluctuations than its residual capacity can absorb. Per-server risk constraints can enforce a prescribed overload tolerance but do not distinguish the assignments that meet it by how close the riskiest server comes to the limit. We show that, for independent tasks, placement preserves a period's total variance and total residual capacity, and decides only how fluctuation, measured by standard deviation, is paired with residual capacity across servers. The risk ratio, the ratio of fluctuation to residual capacity, parameterizes a server's worst-case overload probability over all aggregate workload distributions with given mean and variance. We minimize the largest risk ratio, attained at the risk bottleneck. Risk-Bottleneck Placement (RBP) places tasks in descending order of standard deviation, each on the server with the smallest post-assignment risk ratio, and refines the assignment with relocations and swaps within a finite per-period online budget. On small instances solved exactly by enumerating every assignment, minimizing the maximum expected utilization leaves the largest risk ratio 25.66-29.19% above its exact minimum on average, even with risk-minimizing tie-breaking, and the corresponding gap for RBP is 1.77-2.64%. In trace-derived multi-period simulations at two workload pressures, RBP reduces the worst-server overload probability by 26.0% and 18.0% relative to the best baseline and remains the lowest at every tested pressure and scale.

0.32

Whole-Route Planning of a Memory Bus Between Two BGAs: An Exact Model of Crossings and Layer Changes, Negotiated to DRC-Clean Copper

cs.AR ·2026-10-26 ·Andrew Haas
similarity 0.50
Abstract · 11 pages, 7 figures, 1 table

Routing the bus between a processor and its DRAM remains largely manual in printed circuit board (PCB) design, and published algorithms optimize proxies such as crossing or layer counts. We present a router that plans every lane of a two-layer BGA-to-BGA bus before any copper is laid, and carries the plan to design-rule-clean copper. Its core is an exact constraint-programming model that chooses, for all lanes at once, where each necessary crossing occurs, in what order -- by a rule over every triple of lanes -- and where each lane changes layer, with via room; for the ends it is given, it proves its plan optimal within the model. The model reads naturally as physics: worldlines, frustrated Ising spins and contact forces. A linear program places the lanes in millimeters; the constraints it must violate return to the model as cuts, and audit findings as negotiated congestion prices, until the plan passes an audit against the production router's rules or lays clean. The escapes are chosen by an estimate of the same objective, and differential pairs carry their polarity, with an automatic via crossover where the ends disagree. On an Allwinner H3 and a Zynq-7020, each to a DDR3 device, the router completes every rung of two ladders, of up to 51 nets on the H3 (its whole bus) and 43 on the Zynq, connected and DRC-clean, never with more vias than the human designer (80 against 88 and 62 against 100 at the top rungs) and always with less copper, where the toolkit's production router leaves nets open on four of the ten rungs and Freerouting completes none. On the Zynq board itself it completes 45 of the bus's nets with 70 vias to the designer's 105. On generated buses of three, four and six routing layers every run completes, and every one with a known optimum attains it.

0.36

DART: Aiming for Tail-Delay Control in Reconfigurable Networks

cs.PF ·2026-09-01 ·Hossein Mohammadalizadeh, Holger Karl
similarity 0.50
Abstract

Many systems serve different job classes by switching among configurations. Often, reconfiguration takes a stochastic amount of time that depends on direction and can differ in distribution between configurations. Reaching a target configuration may require crossing intermediate ones. Under a high-percentile delay objective, rarely served or pass-through configurations accumulate the long-waiting jobs that dominate the sojourn-time tail. Controlling that tail couples three decisions: which target to choose, which path to take, and whether and how many jobs to serve at the configurations crossed on the way. We introduce DART, an opportunistic commitment policy that commits to a target configuration to avoid myopic detours while serving a traversed configuration only when its weighted delay or backlog justifies the pause. We show how these decisions shape the weighted sojourn-time tail. Across six stress topologies, each isolating a different tail-control challenge, DART achieves the lowest P99 sojourn time in every case, up to 23% below the strongest baseline. The advantage holds under heterogeneous, heavy-tailed, and asymmetric reconfiguration times.

0.27