BOLT: Multi-Bottleneck Bound-Guided Learning for Flexible Job-Shop Scheduling with Time Lags and Resource-Coupled Transport

Ziheng Zhang, Wei Zhang, Yunyi Zhao, Zuming Liu, Wei Zhou, Boon Ping Gan

cs.LG math.OC ·submitted 2026-10-15 08:54 UTC · v1
theorycode/data

Abstract

Flexible job-shop scheduling becomes resource-coupled when a scarce vehicle fleet moves jobs between stations, because the schedule sets the transport waits. BOLT (bound-oriented learning for transport-coupled scheduling) builds a lower bound from chain, machine-capacity, and fleet-capacity relaxations. The bound equals the makespan at termination, so its per-step changes form a reward that sums to a constant minus the makespan. Because it never exceeds the attainable makespan, each candidate's bound increase is a proven rise of the makespan floor, which the policy reads as a price. The root bound certifies a completed schedule's suboptimality gap without a solver. On industry-motivated 10-module prefabricated-construction instances, explicit transport coupling outperforms a transport-penalty policy in every tested cell where loaded moves occupy at least 66% of fleet time and in none at or below 56%. Across five zero-shot 50- and 80-module production batches, BOLT outperforms the best dispatching-rule pair on four and the penalty policy on the three with long moves. In the three-vehicle 80-module batch, its mean makespan is 13.0% below the best pair and 4.2% below an hour-budget constraint-programming solver whose proven gap averages 34%. BOLT decides in 2.3-5.9 ms per event on one processor core and re-plans a disruption in seconds.

Comment
12 pages main text plus 18 pages of supplementary material appended after the references (30 pages total). Code, data, and trained models: https://github.com/NTUZZH/FJSP-TLT-MARL. Submitted to IEEE Transactions on Automation Science and Engineering

Closest papers

Nearest neighbours by meaning across the whole index.

Reshaping Rollout Workloads for Asynchronous RL Post-Training on Heterogeneous Accelerators

cs.DC ·2026-09-29 ·Jiahui Li, Hao Nie, Yibo Zhu, Pengjin Xie, Yu Zhou +3 more
similarity 0.61
Abstract

Reinforcement learning (RL) post-training increasingly relies on long-horizon, multi-turn rollouts. As post-training jobs outgrow a single cluster, rollout pools assembled across clusters introduce hardware heterogeneity. Rollout scheduling must serve two stakeholders: the hardware needs high aggregate decode throughput, while each trajectory needs to finish quickly. The tension arises from the memory-bandwidth-bound nature of autoregressive decoding. A large active batch amortizes weight reads for high throughput but leaves each trajectory a smaller bandwidth share and a longer completion time. The scheduling objective is therefore specialization, letting different workers serve different roles. Heterogeneous hardware further enables this specialization. High-bandwidth accelerators favor long-context work, while cost-efficient accelerators sustain large batches. Workload evolution makes this specialization difficult to sustain, and dynamic reassignment faces a circular dependency because a move's benefit depends on subsequent placement decisions. We present CadenceRL, which bypasses this dependency through structural workload reshaping rather than per-move benefit estimation. Pacing replaces long-context trajectories with shorter ones, providing a structurally positive transformation that sustains large active batches for high throughput. When accumulated staleness demands faster completion, concentration directs the residual long-context tail onto high-affinity workers. Late-bound KV preparation stages accumulated prefixes before a destination is selected. On heterogeneous rollout pools, CadenceRL improves decode throughput by up to 48% and reduces P95 trajectory latency by up to 64%. Adding high-bandwidth accelerators reduces tail latency, while adding cost-efficient accelerators increases throughput, without manual routing configuration.

0.22

Speed-Robust Scheduling for Total Completion Time

cs.DS cs.DM ·2026-11-16 ·Moritz Buchem, Nicole Megow, Morten Weber
similarity 0.60
Abstract

We study two-stage speed-robust scheduling for minimizing total completion time. Jobs must be partitioned into $M$ bags before an adversary reveals the speeds of at most $M$ machines. Each bag is then assigned to one available machine, and the jobs on each machine may be processed in any order independent of the bags. We compare with an optimal schedule that knows the speeds in advance and assigns jobs individually. This model has been studied for makespan minimization. We initiate its study for total completion time, as suggested by Stein and Zhong (TALG 2020). For an unknown number of identical machines, we show that the optimal deterministic robustness factor is exactly~$13/12$, both for unit-size jobs and for arbitrary processing times. For infinitesimally small jobs, the factor lies between $31/30\approx1.0333$ and $28/27\approx1.0370$, well below the optimal makespan factor of about $1.2071$. General speeds make the problem strictly harder: no deterministic algorithm is better than $1.2669$-robust, already for infinitesimally small jobs. We give a $25/16$-robust algorithm for arbitrary processing times and improve the guarantee to $1681/1152\approx1.4592$ for infinitesimally small jobs. Our main tools are a layer decomposition that extends guarantees from unit-size jobs to arbitrary processing times when one assignment satisfies them for every prefix in non-increasing processing-time order, and a threshold analysis of the bag counts produced by greedy assignment rules.

0.31

Imperfect Is Perfect: Learned Column Prefilling for Branch-Price-and-Cut

cs.LG ·2026-10-14 ·Haoran Liu, Yu Yang
benchmark similarity 0.58
Abstract · 27 pages, 3 figures

Column generation folklore warns that initial columns hurt: a warm start may bias the dual and slow the root of branch-price-and-cut. We show the opposite once the columns are imperfect in the right way. Preloading the support of the optimal root LP, the best columns one could know in advance, fails to finish on half of our hardest instances; a pool of ordinary routes that need not belong to any optimal solution, held outside the master and priced at the current smoothed dual, speeds the root up. Because the columns need not be optimal, producing them becomes a learning task: a neural edge scorer guides a constructive generator that builds the pool in seconds. A second network predicts the initial center of Wentges smoothing from the instance file, and with it the direction of the smoothed pricing queries; the solver's own updates run unchanged. With prefill and center in place, exact pricing dominates root pricing time, so we rebuild bucket-graph labeling around its dominance test for the GPU and certify on the CPU. Inside RouteOpt, the state-of-the-art exact solver for capacitated vehicle routing, the pipeline reaches the same certified root bound in 13.2% of vanilla RouteOpt's root pricing time over 95 instances with 300 to 1000 customers, prefill alone in 26.1%, and 17.5 times faster in the best case. In an exact branch-price-and-cut solver for unrelated parallel machine scheduling, prefill with smoothing and the learned center certifies all 25 benchmark instances, 12 times faster than the solver's own column generation, which certifies 20 of them.

0.50

Below Three: A 2.8027-Approximation for Moldable Precedence Scheduling

cs.DS ·2026-11-19 ·Klaus Jansen, Felix Ohnesorge
similarity 0.57
Abstract

We study makespan minimisation for nonpreemptive moldable jobs with arbitrary precedence constraints on identical processors. Each job runs on a chosen number of processors that remains fixed throughout its execution. Allocating more processors to a job can shorten its execution, but may increase total work and delay other jobs. We assume nonincreasing processing times, nondecreasing work, and a convex duration--work relation after dominated allocations are removed. This model includes jobs with concave speedup, for which Jansen and Zhang obtained a $3.291919\ldots$-approximation. Independently and concurrently with our work, Chen obtained a $3.016208\ldots$-approximation for the full convex model and a $2.973912\ldots$-approximation for concave speedup. We give a deterministic polynomial-time $2.8027$-approximation for the full convex model and every number of processors. Our result breaks the factor-three barrier for this model and also improves the approximation guarantee for concave speedup.

0.34

Single-Machine Guarantees on Unrelated Machines and Beyond: Proportional Fairness for Nonclairvoyant Polytope Scheduling

cs.DS ·2026-10-23 ·Sven Jäger, Alexander Lindermayr, Bart Zondervan
theory similarity 0.57
Abstract · Shortened abstract

The Polytope Scheduling Problem (PSP) is a general framework for preemptive scheduling in which feasible instantaneous job allocations form a packing polytope. In the nonclairvoyant online setting, Proportional Fairness (PF), a practical allocation rule rooted in market theory, is the leading general-purpose algorithm. On a single machine, PF coincides with weighted Round-Robin, which is $2$-competitive for weighted completion time with uniform release dates (optimal for nonclairvoyant algorithms) and $(2+\varepsilon)$-speed $O(1/\varepsilon)$-competitive for weighted flow time. Known guarantees beyond a single machine are weaker. This raises a central question: Are these heterogeneous environments intrinsically harder than a single machine under nonclairvoyance? We show that they are not: PF retains both single-machine guarantees on the novel class of support-submodular polytopes, which includes unrelated machines and polymatroids. On unrelated machines, this refutes a belief (JACM'18, SODA'25) that PF is not $O(1)$-speed $O(1)$-competitive for weighted flow time. Our main technical contribution is an equivalent characterization: a polytope is support submodular if and only if, for all job weights, the optimal weighted completion time is concave in the processing requirements. This structural insight underlies both guarantees. For general PSP, the picture changes: we give the first lower bound above $2$, showing that every randomized nonclairvoyant algorithm has a competitive ratio of at least $2+10^{-5}$ for weighted completion time, even with uniform release dates. On the positive side, we substantially improve the best known guarantee for weighted completion time from $27$ (SICOMP'26) to $4$ via a new dual-fitting analysis of PF. For weighted flow time, we show that PF achieves the first $O(1)$-speed $O(1)$-competitive nonclairvoyant guarantee for graph scheduling.

0.27

Exact SAT and Constraint Programming for Job Shop Scheduling with Time-Varying Peak Power Constraints

cs.LO ·2026-08-26 ·Huy Tuan Nguyen, Duc Trung Kim Nguyen, Khanh To Van
benchmark similarity 0.56
Abstract

The Job Shop Scheduling Problem with Power Requirements (JSPPR) extends the classical job shop scheduling problem by imposing time-varying limits on instantaneous power consumption. Previous studies have used a mixed-integer linear programming formulation and the GRASP x ELS metaheuristic, but no SAT-based exact approach or constraint programming model has been reported. This paper develops the first exact SAT and constraint programming (CP) formulations for the JSPPR. On the 35 published benchmark instances, both SAT and CP prove global optimality for all instances and obtain identical optimal makespans, substantially improving upon the best previously reported results. They also establish four improved makespan values over the GRASP x ELS results reported in the original study. CP proves optimality faster than SAT, while both exact approaches substantially improve the optimality coverage of the MILP formulations, which prove optimality on only 6 and 10 instances using CPLEX and Gurobi, respectively. The certified optimal solutions also reveal inconsistencies in several previously reported benchmark results, including makespans below the proven optimum. We provide corrected optimal makespans and a complete set of certified optimal results for the JSPPR benchmark, establishing a reliable reference for future studies.

0.26

Flattening Every Memory Peak in Long-Context Mixture-of-Experts Training

cs.DC ·2026-09-13 ·Shrey Pandit, Xuan-Phi Nguyen, Yiran Zhao, Shafiq Joty
similarity 0.56
Abstract · Preprint

Training a Mixture-of-Experts (MoE) model at long context or large batch size fails as soon as any one component's peak allocation exceeds device memory, so the target is every peak at once, not the average footprint. Four are left unbounded by the parallelism plans in common use, and each grows differently: expert dispatch with the routing matrix, the vocabulary projection with tokens times vocabulary, gradient checkpoint boundaries with depth times sequence length, and optimizer state with parameter count. Which one runs out first changes with the model, the context length, and the device count, so lowering the largest only exposes the next. We bound all four with schedules whose GPU working set is fixed at launch: PipelinedLLEP extends least-loaded expert parallelism with a cap on the tokens each source contributes to a dispatch chunk, Ring-DTP circulates activations or weight shards around a ring at the vocabulary projection and folds each block of logits into an online log-sum-exp, Selective checkpoint offload (SCO) keeps the one long-lived tensor of each checkpoint boundary in CPU memory, and OffloadStreamAdamW turns the serial CPU Adam update of optimizer offload into a bucket pipeline. All four change only the order and granularity of computation and data movement, so the loss and gradients stay exact. In matched component tests, they cut the MoE dispatch peak by up to $59.3\%$ without losing throughput, the vocabulary projection peak by $86.6\%$, and the offloaded optimizer step by $2.05\times$ faster. Composed on MoE models from 120B to 667B parameters, they train at 1M context length, $8$--$32\times$ the reach of a tuned FSDP2 baseline, and up to $10.4\times$ its throughput.

0.40

TAILROLL: Tail-Aware Rollout Acceleration for RL-Based LLM Post-Training

cs.DC ·2026-11-17 ·Niloofar Gholipour, Marcos Assuncao, Timothy Yu, Gursimran Singh, Rajkumar Buyya +3 more
code/data similarity 0.56
Abstract

RL post-training of large language models (LLMs) is bottlenecked by rollout: heavy-tailed responses leave engines idle as each step waits for the longest response. Asynchronous training masks, but does not eliminate, idle time. We distinguish imbalance waste (uneven placement and decode contention) from straggler waste (waiting for the longest response). Tail length, not average load, often sets the step bound. We propose TAILROLL, an online scheduler integrated into an open-source RL framework. It combines stateless in-flight migration and sufficiency-gated termination. Migration moves decoding requests between engines at chunk boundaries and resumes them with one re-prefill under a freeness-based, cost-aware tail-balancing policy. Termination stops a response when its GRPO group has enough completed samples for advantage estimation, masking its partial output from the training loss. Across ten configurations, TAILROLL reduces rollout bubble ratio by 21% to 74% and cross-engine KV-cache imbalance by 44% to 79%. In end-to-end RL training, it cuts rollout time by 24% to 34%, full step time by 21% to 22% on long-CoT RL, and p95 request latency by 28% to 37%, while raising generation throughput by up to 33% with comparable or higher final reward.

0.22