Abstract

Flexible interconnections allow data centers to connect to the grid sooner without upgrading the grid infrastructure, if they accept limits on their grid power during periods of grid stress. When a limit is reached, the data center must slow some of its computing jobs. This choice sets the cost of flexibility, because the work done by a job is worth far more than the energy it uses. This paper models how jobs respond when their power is reduced, and proposes a real-time method that shares the available power among jobs according to their value. It also gives grid planners a simple measure of how much power a data center can reduce, and for how long. A one-year case study of a 100-MW data center shows that the proposed method lowers the cost of meeting grid limits, and that on-site generation and storage lower it further.

Comment
Submitted to IEEE PES General Meeting 2027

Closest papers

Nearest neighbours by meaning across the whole index.

Quantifying the hosting capacity value of workload flexibility for AI data centers: A two-stage electricity-computation co-optimization framework

eess.SY ·2026-11-18 ·Jiakai Wu, Wei Sun, Pengyu Ren, Yifan Wang
hot direction similarity 0.76
Abstract

Grid connection constraints increasingly limit the expansion of AI data centers, yet the additional hosting capacity enabled by computational workload flexibility remains insufficiently quantified. This paper develops a two-stage electricity--computation co-optimization framework to quantify the individual and coordinated hosting capacity values of spatial and temporal workload flexibility. Data center capacities are determined endogenously, with computational task arrivals scaling with admitted capacity. Spatial routing of eligible interactive requests and temporal deferral of batch workloads are linked to server operation and facility power demand, subject to workload completion requirements and transmission constraints. The first stage maximizes aggregate hosting capacity; the second fixes the resulting site capacities and optimizes annual workload scheduling and generation dispatch to minimize generation and carbon costs. An 8760-hour case study with three data centers on a modified IEEE 118-bus system shows that temporal and spatial flexibility individually increase hosting capacity by 21.26\% and 5.37\%, respectively. Their coordinated use raises hosting capacity from 4635.1~MW to 6231.5~MW, a 34.44\% increase without network reinforcement. The coordinated gain exceeds the sum of the individual gains by 361.9~MW, demonstrating complementarity between spatial migration and temporal deferral. By redistributing computational demand across locations and operating hours, these mechanisms enable fuller utilization of existing transmission capacity. The findings establish workload flexibility as a quantifiable planning resource for accommodating additional data center capacity within existing transmission networks.

0.28

Modeling and Stability of Power Systems With Coupled Data Center and Grid Dynamics

eess.SY ·2026-11-17 ·Guido Cavraro
similarity 0.74
Abstract

The growing deployment of data centers poses challenges for power-system operation. However, data centers possess flexible resources that can be leveraged to mitigate their impact on the grid and provide grid services. This paper develops a linear-affine dynamic model of a transmission network with multiple data centers, explicitly coupling electromechanical grid dynamics with data center power demand and computational backlog. Grid-aware computing policies are incorporated to represent how data centers adjust their computational power in response to grid frequency deviations and workload backlog. The proposed framework provides a tractable means of investigating the interactions between multiple data centers and the transmission grid and assessing the potential of flexible computing to support power-system stability.

0.27

Slasher: Power Flexibility for Cloud Datacenters

cs.DC cs.OSeess.SY ·2026-08-26 ·Liuzixuan Lin, Fiodar Kazhamiaka, Alok Gautam Kumbhare, Chaojie Zhang, Jaylen Wang +8 more
similarity 0.72
Abstract · 18 pages, 15 figures

Datacenters consume many megawatts of power, and regularly encounter scenarios that require modulating their power draw. These scenarios include datacenter infrastructure failures, power grid failures, grid services, and more, spanning a diverse range of requirements in terms of the power magnitude, the scope of the reduction, the notice time, and other dimensions. To address these scenarios, we have built Slasher, a general system for modulating the power of \azure datacenters to handle scenarios ranging from individual racks to regional multi-datacenter grid events. Slasher coordinates datacenter resources with the goal of meeting power targets while minimizing negative impact on hosted workloads. In this paper, we review the main power modulation scenarios, characterize the power reduction levers using data from production cloud datacenters, describe Slasher's system architecture, and formulate the cloud datacenter power modulation control problem. We also develop a high-fidelity datacenter simulator and propose a workload impact model, using them to design and evaluate power control algorithms.

0.31

Grid Demand Flexibility Assessment of AI Data Centers via Batch Workload Temporal Shifting

eess.SY ·2026-09-29 ·Suntao Su, Liang Du, Shengyi Wang
similarity 0.72
Abstract · 5 pages, 5 figures, conference

The rapid growth of artificial intelligence (AI) data centers has introduced new challenges to power system operation. As their power demand becomes larger and more variable, quantitatively characterizing their demand flexibility is increasingly important for effective power system coordination. However, heterogeneous workload characteristics and resource requirements make this flexibility difficult to characterize directly. This paper proposes a framework for assessing the grid-compatible demand flexibility of AI data centers via batch workload temporal shifting. An averaging-based resource usage processing method is developed to map fine-resolution CPU, GPU and memory usage into unified time intervals compatible with power system operation. A workload temporal scheduling model is then formulated to shift batch workloads while preserving execution continuity, delay constraints, and server resource capacities, and is coupled with a utilization-dependent server power model to translate workload scheduling decisions into server power demand. Two complementary flexibility metrics are evaluated: short-term peak demand shaving and the maximum duration of sustained power reduction. Numerical results based on real GPU cluster traces demonstrate that workload temporal shifting can provide quantifiable and grid-compatible demand flexibility for AI data centers with limited disruption to computing workloads.

0.13

Unlocking AI Data Center Interconnection Capacity Through Coordinated Grid and Data Center Flexibility

eess.SY ·2026-10-04 ·Rida Fatima, Xingpeng Li
similarity 0.71
Abstract

The rapid growth of AI data centers is creating concentrated electricity demands that can exceed available distribution network headroom and delay interconnection. This paper investigates whether capacity can be used effectively by coordinating flexibility on both sides of the interconnection. A day-ahead mixed integer second order cone programming framework maximizes feasible AI data center IT capacity using utility side conservation voltage reduction and network topology reconfiguration, together with data center workload shifting and reserve constrained uninterruptible power supply storage. Background feeder demand uses voltage dependent ZIP models, while the data center is modeled as constant power demand using Training, Inference, and Mixed workload profiles. A two-stage solution first maximizes interconnection capacity and then minimizes feeder losses for the retained capacity, with numerical relaxation screening. Studies on a 116-bus model derived from the IEEE 123-node feeder show that, at the constrained bus-60 connection point, grid side flexibility, driven almost entirely by network reconfiguration, increases feasible IT capacity by approximately 42.5-45.0%, while data center flexibility alone provides approximately 2.1-5.4% gains. Coordinated operation increases feasible IT capacity from approximately 10.5-10.6 MW under BASE operation to 15.3-16.0 MW, corresponding to gains of approximately 45.9-50.8%; the 16.0 MW Inference result is limited by the adopted UPS reserve requirement. Benefits are strongly location dependent and influenced by workload flexibility, deferral duration, PUE, UPS energy and reserve requirements, and feeder loading. Under a combined adverse operating condition, FULL capacity decreases by only 3.4% relative to the nominal Mixed case while retaining substantial additional capacity over BASE.

0.29

Spatial LLM Workload Shifting Needs Foresight: Model Commitment for AI Data Center Operation under Power Grid Constraints

eess.SY ·2026-09-09 ·Bojun Du, Hongyang Jia, Tonghui Li, Qingchun Hou, Ze Wang +2 more
similarity 0.70
Abstract · 3 pages, 2 figures

AI data centers may face power supply shortages during certain periods, requiring operators to shift large language model (LLM) inference workloads spatially to maintain service rates. However, existing workload-shifting methods typically assume that any data center with sufficient computing resources can immediately serve shifted requests, which may lead to infeasible transfers and unserved demand. This letter proposes model commitment (MC), a mixed-integer linear programming framework that jointly schedules model deployment and cross-site request routing under power constraints and electricity-price signals. First, MC formulates the intertemporal coupling introduced by model replica loading. Second, it translates prefill and decode latency requirements into the amount of demand that each replica can serve. Case studies based on real-world data show that MC enables AI data center operators to achieve a 100% service rate under time-varying grid conditions and reduce total operating cost by 29.0%.

0.24

Locational Marginal Pricing of Compute: Co-optimizing Compute and Energy for Transparent Data Center Flexibility

eess.SY cs.AI ·2026-11-15 ·Vladimir Pyltsov, Teng Zeng
similarity 0.70
Abstract

Demand from data centers and AI compute is growing rapidly and is increasing stress on the power grid. This load could be flexible through user adjustments and provide relief during energy scarcity events, yet today its flexibility is provided through utility call-ups or system-operator load shedding, and is invisible to the users whose workloads are being curtailed. In this work, we propose to quantify and couple the prices of compute and energy in a single optimization problem. The resulting compute price reflects the marginal cost of the binding constraints and decomposes into components indicating which grid, power, hardware, or service requirement causes a price surge. The economic interpretation updates the price with real-time conditions and gives users a signal for potential flexibility provision. The co-optimization ultimately connects compute and energy markets while providing a signal for relief of stress on both the grid and the compute resources.

0.25

N-1 Security constrained Hosting Capacity Assessment for Ultra Large-scale Data Center with Workload Flexibility

eess.SY ·2026-11-18 ·Jiakai Wu, Pengyu Ren, Yifan Wang, Wei Sun
hot direction similarity 0.69
Abstract · conference

Transmission network security can substantially alter where large-scale data centers can connect and how much workload flexibility can unlock. This paper develops a hosting-capacity framework that couples computing demand, batch workload scheduling, and N-1 security constraints. A modified IEEE 118-bus case study reveals that two data center sites with identical hosting capacities under normal operation differ by 874.5 MW under the contingencies operation when workload flexibility is enabled. Six-hour batch deferral increases N-1 hosting capacity by up to 24.5\% relative to immediate execution. These gains arise from reducing demand at critical hours while accommodating deferred tasks within subsequent transmission limits and deadlines. At bus 92, a four-hour window captures 90.9\% of the six-hour capacity gain. The findings establish workload flexibility as a location-dependent connection resource whose capacity value requires joint assessment of contingency exposure and deadline constrainted workload recovery, beyond the power reduction available at a single critical hour.

0.30