Priority-Aware Firm and Flexible Capacity Quantification for Large-Load Interconnection

Shaoze Li, Bohang Fang, Junjie Qin, Cong Chen

eess.SY ·submitted 2026-11-10 07:20 UTC · v1

Abstract

We study how to unlock existing transmission capacity to accelerate large-load interconnection under differentiated quality-of-service (QoS) requirements. We establish an efficient framework to quantify firm and flexible hosting capacities and assess marginal values of grid upgrades. Specifically, we define multiple flexible capacity tiers with differentiated QoS limits and design a two-layer priority rule to allocate curtailment among tiers. We then formulate a mixed-integer chance-constrained model to jointly quantify firm and flexible capacities under QoS and priority constraints. To improve computational efficiency, we derive an equivalent aggregate formulation that eliminates individual curtailment variables and priority binaries without changing the feasible capacity set. Numerical results show the computational advantage of aggregation. Multi-tier flexible capacity increases total admitted capacity by 45.0\% over the firm-only hosting capacity.

Closest papers

Nearest neighbours by meaning across the whole index.

Minimizing Grid Interconnection Capacity Requirements for AI Data Centers: A Developer-Side Planning Framework with Onsite Resources and Workload Flexibility

eess.SY ·2026-08-29 ·Hassan Zahid Butt, Rida Fatima, Xingpeng Li
similarity 0.59
Abstract

Securing grid interconnection capacity has become a bottleneck for AI data center projects and can take longer than constructing the facilities themselves. This mismatch can delay deployment for years, making early interconnection planning essential. This paper develops ICP-AI, an interconnection capacity planning framework from a data center developer's perspective. The framework minimizes grid import capacity under a prescribed onsite investment budget while jointly sizing photovoltaic (PV) and battery energy storage system (BESS) resources and scheduling deadline constrained workload flexibility. A secondary refinement fixes the minimum grid capacity and selects the minimum-investment PV-BESS portfolio among solutions that achieve that capacity. The framework is evaluated using monthly composite stress profiles across varying temporal assumptions, load shapes, flexible load fractions, and deferral windows. Results show that interconnection capacity reduction depends strongly on the planning environment: at a $100M budget, it is about 6% for the high load factor baseline, exceeds 10% under monthly average solar availability, and reaches 13.3% for a more diurnal load. At a $10M budget, 5% flexible load with a 1 h workload deferral window reduces BESS capacity from 15.30 to 4.87 MWh while increasing capacity reduction from 4.43% to 4.84%. To test sensitivity to temporal compression, the model is also solved over the full 8,760 h chronology, which preserves the main capacity and flexibility trends. Overall, ICP-AI quantifies the interconnection capacity and infrastructure substitution value of workload flexibility, providing an investment-interconnection frontier to support capital allocation and early project planning in constrained grid environments.

0.30

Integrating Fast-response Capability into Virtual Power Plant Operation for Ancillary Services

eess.SY ·2026-08-26 ·Qixing Liu, Ruike Lyu, Zhe Zhai, Yan Shen, Xue Liu +1 more
published similarity 0.58
Abstract · Published in: 2025 IEEE Kiel PowerTech

Virtual power plants (VPPs) can aggregate distributed energy resources (DERs) to provide ancillary services for power systems, creating new profit opportunities. Ancillary services such as secondary frequency regulation require providers to have sufficient response capability to follow rapidly changing control commands. If overlooking the response requirement, the VPP will not be able to accurately measure its regulation capability, reducing its earnings in performance-based markets or risking disqualification. This paper integrates the requirement for fast-response capability into the operational framework of VPPs providing ancillary services. We leverage historical control commands to formulate chance constraints in the bidding model, mandating that the VPP's fast-response capability meets the requirement of ancillary services with a specified probability. Case studies verify that considering fast-response capabilities can enhance VPP operation.

0.63

Feeder-Aware Service-Conditioned Flexibility of Grid-Interactive Buildings

eess.SY ·2026-10-22 ·Dafang Zhao, Ittetsu Taniguchi, Takao Onoye
similarity 0.56
Abstract

Grid-interactive buildings can adjust demand, but building-feasible power budgets may differ from accepted feeder-head offers. This study addresses a practical question: to what extent can the adjustable electricity consumption of buildings be translated into deliverable flexibility services while satisfying feeder-head operating requirements? To enable a fair comparison, we adopt the same baseline operating schedule, equipment conditions, and post-service recovery requirements for indoor temperature and battery state of charge (SOC). Flexibility is then evaluated under two settings: one considering only building-level constraints, and the other additionally accounting for feeder-head constraints. We first use a simplified network model with explicit security margins to determine a preliminary amount of flexibility that can be committed. The resulting schedule is then validated using a more detailed network simulation via Modelica. If network losses cause the actual response to deviate from the committed response, the electricity consumption of individual buildings is rescheduled. If the required response still cannot be achieved, the committed flexibility level is reduced. The experiments cover multiple service activation times, regulation directions, and service durations. For comparative purposes, we retain the initial optimization result as the reference estimate of the maximum potentially available flexibility, rather than interpreting the failure of a particular subsequent realization attempt as evidence that a larger flexibility level is inherently infeasible. The results demonstrated that 24.51\% of nonzero flexibility contracts were rejected due to feeder-head constraints, 67.04\% of contracts were accepted with some rescheduling and building redispatch, and only 8.09\% of contracts were accepted without any changes.

0.16

N-1 Security constrained Hosting Capacity Assessment for Ultra Large-scale Data Center with Workload Flexibility

eess.SY ·2026-11-18 ·Jiakai Wu, Pengyu Ren, Yifan Wang, Wei Sun
similarity 0.56
Abstract · conference

Transmission network security can substantially alter where large-scale data centers can connect and how much workload flexibility can unlock. This paper develops a hosting-capacity framework that couples computing demand, batch workload scheduling, and N-1 security constraints. A modified IEEE 118-bus case study reveals that two data center sites with identical hosting capacities under normal operation differ by 874.5 MW under the contingencies operation when workload flexibility is enabled. Six-hour batch deferral increases N-1 hosting capacity by up to 24.5\% relative to immediate execution. These gains arise from reducing demand at critical hours while accommodating deferred tasks within subsequent transmission limits and deadlines. At bus 92, a four-hour window captures 90.9\% of the six-hour capacity gain. The findings establish workload flexibility as a location-dependent connection resource whose capacity value requires joint assessment of contingency exposure and deadline constrainted workload recovery, beyond the power reduction available at a single critical hour.

0.27

Dynamic Coalition Formation Under Capacity Constraints: A Regime-Switching Value-Investing Game

cs.GT cs.DC ·2026-11-02 ·Rosario Patanè
publishedbenchmark similarity 0.56
Abstract

Edge computing service deployment requires the Network Operator (NO) and Service Providers (SPs) to coordinate investment and resource allocation under uncertain demand. This paper develops an audit-based service management framework for daily coalition formation with fixed capacity and service-level agreement (SLA) reservations. A two-stage coalitional game separates infrastructure investment from operational participation. Demand follows a Geometric Random Walk (GRW), and SPs apply an ordered admission and suspension rule using reported marginal contributions. With the NO held fixed, the operational coalition value is submodular; mandatory reservations can produce negative Shapley payoffs. We derive a separable benchmark, compute operational Shapley allocations, and give a sufficient condition for convergence to an individual equilibrium. A probabilistic audit mechanism provides a conditional daily truthfulness guarantee under verified settlement and enforceable penalties. For five service classes over three years, the reference run gains 12.4% over static grand-coalition membership and recovers 94.6% of the full-information optimum. Across 30 runs, the median gain is 13.3%. Sensitivity tests examine policy parameters, capacity and alternative demand models. The gain depends on capacity and update order; abundant capacity can make the admission rule underperform static membership.

0.34

Quantifying the hosting capacity value of workload flexibility for AI data centers: A two-stage electricity-computation co-optimization framework

eess.SY ·2026-11-18 ·Jiakai Wu, Wei Sun, Pengyu Ren, Yifan Wang
similarity 0.55
Abstract

Grid connection constraints increasingly limit the expansion of AI data centers, yet the additional hosting capacity enabled by computational workload flexibility remains insufficiently quantified. This paper develops a two-stage electricity--computation co-optimization framework to quantify the individual and coordinated hosting capacity values of spatial and temporal workload flexibility. Data center capacities are determined endogenously, with computational task arrivals scaling with admitted capacity. Spatial routing of eligible interactive requests and temporal deferral of batch workloads are linked to server operation and facility power demand, subject to workload completion requirements and transmission constraints. The first stage maximizes aggregate hosting capacity; the second fixes the resulting site capacities and optimizes annual workload scheduling and generation dispatch to minimize generation and carbon costs. An 8760-hour case study with three data centers on a modified IEEE 118-bus system shows that temporal and spatial flexibility individually increase hosting capacity by 21.26\% and 5.37\%, respectively. Their coordinated use raises hosting capacity from 4635.1~MW to 6231.5~MW, a 34.44\% increase without network reinforcement. The coordinated gain exceeds the sum of the individual gains by 361.9~MW, demonstrating complementarity between spatial migration and temporal deferral. By redistributing computational demand across locations and operating hours, these mechanisms enable fuller utilization of existing transmission capacity. The findings establish workload flexibility as a quantifiable planning resource for accommodating additional data center capacity within existing transmission networks.

0.27

Unlocking AI Data Center Interconnection Capacity Through Coordinated Grid and Data Center Flexibility

eess.SY ·2026-10-04 ·Rida Fatima, Xingpeng Li
similarity 0.55
Abstract

The rapid growth of AI data centers is creating concentrated electricity demands that can exceed available distribution network headroom and delay interconnection. This paper investigates whether capacity can be used effectively by coordinating flexibility on both sides of the interconnection. A day-ahead mixed integer second order cone programming framework maximizes feasible AI data center IT capacity using utility side conservation voltage reduction and network topology reconfiguration, together with data center workload shifting and reserve constrained uninterruptible power supply storage. Background feeder demand uses voltage dependent ZIP models, while the data center is modeled as constant power demand using Training, Inference, and Mixed workload profiles. A two-stage solution first maximizes interconnection capacity and then minimizes feeder losses for the retained capacity, with numerical relaxation screening. Studies on a 116-bus model derived from the IEEE 123-node feeder show that, at the constrained bus-60 connection point, grid side flexibility, driven almost entirely by network reconfiguration, increases feasible IT capacity by approximately 42.5-45.0%, while data center flexibility alone provides approximately 2.1-5.4% gains. Coordinated operation increases feasible IT capacity from approximately 10.5-10.6 MW under BASE operation to 15.3-16.0 MW, corresponding to gains of approximately 45.9-50.8%; the 16.0 MW Inference result is limited by the adopted UPS reserve requirement. Benefits are strongly location dependent and influenced by workload flexibility, deferral duration, PUE, UPS energy and reserve requirements, and feeder loading. Under a combined adverse operating condition, FULL capacity decreases by only 3.4% relative to the nominal Mixed case while retaining substantial additional capacity over BASE.

0.28

Real-Time Operation Strategy of Virtual Power Plants With Optimal Power Disaggregation Among Heterogeneous Resources

eess.SY ·2026-08-27 ·Qixin Chen, Ruike Lyu, Hongye Guo, Xiangbo Su
publishedhot directionhighly cited similarity 0.55
Abstract · Accepted by Applied Energy

The virtual power plant (VPP) can aggregate flexible resources on the demand side to provide frequency regulation for the grid, helping address the supply-demand balance challenges. When deploying regulation, the VPP disaggregates the requested power adjustment in real time among its internal heterogeneous resources. Achieving optimal power disaggregation in this process is challenging due to the temporal coupling characteristics of the resources, the uncertain regulation signals, and the requirement for fast response. Therefore, existing research relies on heuristic methods, such as proportional disaggregation, and fails to leverage the heterogeneity of multiple resources. Here, we propose an optimal operation strategy for VPPs to provide regulation, exploiting the complementary characteristics of heterogeneous resources by prioritizing the use of low-cost resources while considering temporal coupling. To reduce the computational overhead of online deployment, we further propose a fast disaggregation algorithm to eliminate the reliance on optimisation solvers. We conducted case studies on the operation of a VPP composed of resources including thermostatically controlled loads and industrial production processes. The results verified the reduced operation cost and increased profit of the VPP under the proposed strategy, with only milliseconds of online computation time. We believe that our work can help better exploit demand-side flexibility.

0.62