Data-center growth impacts household electricity costs more through wholesale prices than through grid reinforcement

Lingdong Zhou, Wenjia Xia, Jiyu Wang, Fei Ding, Xiangqi Zhu

eess.SY econ.GN ·submitted 2026-11-11 23:08 UTC · v1
hot direction

Abstract

Rapid data-center expansion is raising concerns about electricity affordability, yet how the costs of serving these large new loads reach residential customers remains poorly understood. Here, we quantify the potential impact of 371 announced Texas data-center projects, totaling 38.9 GW by 2030, on residential electricity costs by linking power system expansion, wholesale electricity markets, transmission reinforcement, and retail cost allocation. We find that accommodating this demand increases modeled residential electricity costs in one representative case by 1.64 cents/kWh, with 68% arising from higher wholesale electricity prices and 32% from regulated transmission charges. Allowing new gas generation near data centers reduces the 2023 residential cost increase to 0.92 cents/kWh, whereas excluding data centers from the transmission cost-sharing base raises it to 1.87 cents/kWh. These findings reveal that the residential cost burden of data-center growth is driven primarily by wholesale electricity price increases, rather than direct transmission investment costs, and depends critically on generation siting, infrastructure planning, and cost allocation.

Comment
22 pages, 8 figures, 1 table. Lingdong Zhou and Wenjia Xia contributed equally to this work

Closest papers

Nearest neighbours by meaning across the whole index.

Impact of Data Center Load on Co-Optimized Generation and Transmission Expansion Planning with Embedded Unit Commitment

eess.SY ·2026-10-13 ·Haoxiang Wan, Xingpeng Li, Jonghwan Kwon
published similarity 0.70
Abstract · 6 pages, 2 figures, 3 tables. Accepted to the 2027 IEEE Texas Power and Energy Conference (TPEC)

The rapid growth of hyperscale data centers challenges grid expansion planning, yet existing studies focus largely on operational flexibility rather than long-term investment decisions. This paper examines how large data center loads sited at multiple buses affect co-optimized Transmission Expansion Planning (TEP) and Generation Expansion Planning (GEP). The problem is formulated as a multi-year, Unit Commitment (UC)-embedded mixed-integer linear program on the modified IEEE 24-bus Reliability Test System (RTS-24) with Electric Reliability Council of Texas (ERCOT)-calibrated renewable energy profiles. A 500 MW data center load, about 17.5% of the base-year peak, is allocated across four buses by voltage level, generation headroom, renewable co-location, and network connectivity. Integrating this load raises the 15-year net present value of total system cost by 1,794 million USD (+61.6%) and the system-average locational marginal price (LMP) by 45.2%, with operating cost dominating capital investment (84.2% versus 15.8%). Renewable curtailment remains negligible: existing renewables are already near full utilization, so the added demand is served almost entirely by incremental thermal generation. Most notably, the load shifts the optimal plan from transmission-only to generation-only, replacing the base-case 230 kV reinforcement with a new 400 MW combined-cycle gas turbine and showing that strategically sited generation can substitute for network reinforcement.

0.47

U.S. Data Center Growth Through 2030: A Critical Review of Grid Adequacy and Transmission Expansion Planning

eess.SY ·2026-11-10 ·Babak Porkar, Mona Ghassemi
hot direction similarity 0.66
Abstract

The growth of large data centers raises questions about both supply adequacy and the suitability of load representations used in connection studies. This paper critically reviews the U.S. demand, generation, and transmission outlook through 2030 and examines the implications for transmission expansion planning (TEP). Comparison of public forecasts highlights distinctions among annual average demand, peak demand, and grid connection capacity. National generating-capacity totals cannot establish a dependable surplus because resource availability, regional adequacy, transmission constraints, and project timing determine supply capability. Recent grid events and published dynamic studies demonstrate that faults can trigger substantial data-center transfers to backup supply, followed by delayed or coordinated demand recovery. These behaviors require appropriate representation within the conventional planning framework, alongside assessment of the requested maximum grid import. The selected literature reveals limited integration of validated data-center dynamic models into the technical screening and economic comparison of expansion alternatives. The review identifies the need to establish whether fault response and recovery change feasible connection capacity, required reinforcement, or the preferred transmission investment.

0.28

Locational Marginal Pricing of Compute: Co-optimizing Compute and Energy for Transparent Data Center Flexibility

eess.SY cs.AI ·2026-11-15 ·Vladimir Pyltsov, Teng Zeng
similarity 0.64
Abstract

Demand from data centers and AI compute is growing rapidly and is increasing stress on the power grid. This load could be flexible through user adjustments and provide relief during energy scarcity events, yet today its flexibility is provided through utility call-ups or system-operator load shedding, and is invisible to the users whose workloads are being curtailed. In this work, we propose to quantify and couple the prices of compute and energy in a single optimization problem. The resulting compute price reflects the marginal cost of the binding constraints and decomposes into components indicating which grid, power, hardware, or service requirement causes a price surge. The economic interpretation updates the price with real-time conditions and gives users a signal for potential flexibility provision. The co-optimization ultimately connects compute and energy markets while providing a signal for relief of stress on both the grid and the compute resources.

0.25

Job-Level Workload Allocation for Data Centers Under Flexible Interconnections

eess.SY ·2026-11-14 ·Tanmay Mishra, Arash Omidi, Mads R. Almassalkhi
hot direction similarity 0.64
Abstract · Submitted to IEEE PES General Meeting 2027

Flexible interconnections allow data centers to connect to the grid sooner without upgrading the grid infrastructure, if they accept limits on their grid power during periods of grid stress. When a limit is reached, the data center must slow some of its computing jobs. This choice sets the cost of flexibility, because the work done by a job is worth far more than the energy it uses. This paper models how jobs respond when their power is reduced, and proposes a real-time method that shares the available power among jobs according to their value. It also gives grid planners a simple measure of how much power a data center can reduce, and for how long. A one-year case study of a 100-MW data center shows that the proposed method lowers the cost of meeting grid limits, and that on-site generation and storage lower it further.

0.24

Comparative Analysis of Large Load Interconnection Requirements Across U.S. Transmission Entities

cs.AR ·2026-10-27 ·Rafi Zahedi, Rahul Anilkumar, Amin Zamani
publishedbenchmark similarity 0.63
Abstract

The rapid growth of large loads, especially data centers driven by artificial intelligence, is creating unprecedented demands on the North American electric grid. Data centers now account for nearly 80% of large load interconnection requests in the Western Interconnection, and U.S. electricity consumption from data centers is projected to reach 325-580 TWh by 2028. Despite this urgency, technical interconnection requirements for large loads have not yet matured and still contain several gaps. This paper presents a comparative analysis of large load interconnection requirements across eleven U.S. entities, including AEP, Ameren, CAISO, Dominion, Duke Energy, ERCOT, LIPA, MISO, PJM, Southern Company, and SPP, under seven technical categories: large load definition, load data and modeling, fault ride-through, load curtailment and shedding, dispatchability, power quality, and reactive power control. The analysis reveals significant variation in both the scope and specificity of requirements. LIPA addresses all seven technical categories at least partially, while Dominion and Duke Energy provide detailed coverage across nearly all categories. The analysis also finds that data center applicants can be viewed as potential grid resources, rather than only as consumers. The findings provide a structured baseline from which utilities, regulators, ISOs/RTOs, and developers can identify gaps, benchmark against peers, and accelerate the development of interconnection standards.

0.33

AI for AI: Optimizing Additional Infrastructure Build-out to Power Artificial Intelligence Data Centers

cs.AI q-fin.GNecon.GN ·2026-09-08 ·Alexander Crosier, Kyle Onghai, Ronnie Sircar
similarity 0.63
Abstract

The twenty-first century's transformative technology, artificial intelligence, is increasingly constrained by the twentieth century's transformative technology, the electricity grid. Rapid growth in electricity demand from data centers is leading to higher electricity prices, without a compensating supply-side response. We develop a framework linking data-center load growth, available generation capacity, and market-clearing prices to understand this phenomenon. We first analyze a deterministic model to show how differing estimates of demand and supply growth rates affect prices. We then model the expansion of new data centers and their associated electricity demand, together with build-outs of new electricity supply, as stochastic processes,resulting in probabilistic distributions of supply, demand, and prices rather than a single forecast. Finally, we formulate generation expansion as a stochastic control problem in which a revenue-maximizing investor dynamically chooses the intensity of supply-side investments. The analysis highlights a central challenge of the data-center build-out: even when rapid demand growth increases the need for new generation, the uncertainties related to load forecasts, development execution risks, and value cannibalization from overbuilding capacity may weaken incentives to invest at the pace required to keep electricity prices stable.

0.22

Speed-to-Power Dominates Energy Costs for AI Data Centers: Technoeconomic Analysis of Powering AI in the Continental United States

cs.AI eess.SY ·2026-11-12 ·Alex C. Newkirk, Daniel L. Gerber, Erica R. H. Fuchs, Alex Hubbard, M. Granger Morgan +3 more
code/datahot direction similarity 0.62
Abstract · 80 pages incl. SI

The rapid growth of artificial intelligence is driving demand for new data centers at large scale and on short deployment timelines. To power them, firms connect to the commercial grid or contract generation directly, but interconnection and gas-turbine delays now incentivize on-site generation. We compare grid-connected and off-grid data center energy infrastructure (AC- and DC-coupled solar-plus-storage, islanded natural gas, and grid interconnection) across the continental U.S. Using an open-source technoeconomic framework built on empirically calibrated AI training loads, climate-driven cooling, stage-by-stage power conversion, and physics-based battery degradation, we model designs providing equivalent energy services. Our central contribution is a speed-adjusted cost of energy that values the compute unlocked by faster construction, making options with different deployment timelines directly comparable on one physically consistent basis. We find DC coupling reduces lifetime energy costs by 18% ($0.09/ kWh) on average versus AC counterparts by eliminating inverters and improving efficiency. Though rarely cheapest on unadjusted energy cost, DC-coupled microgrids' faster deployment makes them the lowest-cost modeled option in 85% of U.S. locations once foregone compute is valued, or 55% under accelerated natural gas timelines. For AI infrastructure, deployment speed rather than unit energy cost determines the economically preferred path to power.

0.31

Exploiting the Benefits of V2B Application on Peak Shaving of Data Center Loads

eess.SY ·2026-08-31 ·Arya Joshi, Hamed Haggi, Chinmay Morankar
similarity 0.62
Abstract · Digest submission version for IEEE IAS Annual Meeting 2026

The accelerated growth in data center projects has introduced a demand-driven bottleneck throughout power grids and contributed to a substantial increase in carbon emissions. These concerns are fueling discussions on methods to use existing energy assets to drive operational efficiency. To this end, this paper explores the benefits of Vehicle-to-Building (V2B) applications to support peak shaving of data center cooling loads. Initially, a literature review was conducted considering V2B constraints and optimization methods including SoC limitations, EV participation, tariffs, and building loads. This analysis was then used to develop a conceptual case study of a 10 MW data center in Loudoun County, VA by simulating a temperature-dependent load profile and adjusting the V2B participation of 40 commercial and passenger EVs. Simulation results indicate that, depending on seasonal variations in cooling load demands, strategic deployment of V2B assets between 12-5pm can offset gross cooling loads by 13-36%.