U.S. Data Center Growth Through 2030: A Critical Review of Grid Adequacy and Transmission Expansion Planning

Babak Porkar, Mona Ghassemi

eess.SY ·submitted 2026-11-10 21:35 UTC · v1
hot direction

Abstract

The growth of large data centers raises questions about both supply adequacy and the suitability of load representations used in connection studies. This paper critically reviews the U.S. demand, generation, and transmission outlook through 2030 and examines the implications for transmission expansion planning (TEP). Comparison of public forecasts highlights distinctions among annual average demand, peak demand, and grid connection capacity. National generating-capacity totals cannot establish a dependable surplus because resource availability, regional adequacy, transmission constraints, and project timing determine supply capability. Recent grid events and published dynamic studies demonstrate that faults can trigger substantial data-center transfers to backup supply, followed by delayed or coordinated demand recovery. These behaviors require appropriate representation within the conventional planning framework, alongside assessment of the requested maximum grid import. The selected literature reveals limited integration of validated data-center dynamic models into the technical screening and economic comparison of expansion alternatives. The review identifies the need to establish whether fault response and recovery change feasible connection capacity, required reinforcement, or the preferred transmission investment.

Closest papers

Nearest neighbours by meaning across the whole index.

A Critical Review of Grid Integration Challenges and Flexibility Opportunities for Large-Scale Data Centers

eess.SY ·2026-10-14 ·Bibek Dhakal, Manohar Chamana, Biswambhar Gayen, Jatendar Kumar, S M Shams Rahman +5 more
similarity 0.67
Abstract

The rapid proliferation of cloud computing and artificial intelligence workloads is fundamentally reshaping the magnitude, spatial concentration, and electrical characteristics of data center power demand. Data centers differ from conventional commercial loads because they combine high rack densities, converter-dominated interfaces, thermally coupled cooling, uninterruptible power supplies, programmable workloads, and increasingly complex behind-the-meter generation and storage within a single facility. This review examines their grid integration from utility and sustainable-energy perspectives across resource planning, large-load interconnection, distribution feeders, market operation, real-time dynamics, power quality, and asset management. Particular attention is given to distribution-level issues that receive limited treatment in broader energy reviews: bidirectional operation on renewable-rich feeders, harmonic propagation and resonance, ride-through and reconnection, transformer derating, cable ampacity, neutral-conductor heating, protection, and measurement. Static, composite, physics-based dynamic, calibrated, impedance, electromagnetic transient, and hybrid load models are compared according to study purpose and data requirements, and utility coordination platforms, uninterruptible power supply and battery control, workload flexibility, renewable co-location, cogeneration, fuel cells, thermal storage, and clean firm supply are assessed. The central finding is that requested peak demand and annual energy matching alone cannot establish reliable or sustainable integration. Credible assessment must consider hourly and locational supply, network deliverability, marginal emissions, lifecycle and water impacts, backup obligations, rebound, asset health, and verified operating capability.

0.12

Data-center growth impacts household electricity costs more through wholesale prices than through grid reinforcement

eess.SY econ.GN ·2026-11-11 ·Lingdong Zhou, Wenjia Xia, Jiyu Wang, Fei Ding, Xiangqi Zhu
hot direction similarity 0.66
Abstract · 22 pages, 8 figures, 1 table. Lingdong Zhou and Wenjia Xia contributed equally to this work

Rapid data-center expansion is raising concerns about electricity affordability, yet how the costs of serving these large new loads reach residential customers remains poorly understood. Here, we quantify the potential impact of 371 announced Texas data-center projects, totaling 38.9 GW by 2030, on residential electricity costs by linking power system expansion, wholesale electricity markets, transmission reinforcement, and retail cost allocation. We find that accommodating this demand increases modeled residential electricity costs in one representative case by 1.64 cents/kWh, with 68% arising from higher wholesale electricity prices and 32% from regulated transmission charges. Allowing new gas generation near data centers reduces the 2023 residential cost increase to 0.92 cents/kWh, whereas excluding data centers from the transmission cost-sharing base raises it to 1.87 cents/kWh. These findings reveal that the residential cost burden of data-center growth is driven primarily by wholesale electricity price increases, rather than direct transmission investment costs, and depends critically on generation siting, infrastructure planning, and cost allocation.

0.29

Comparative Analysis of Large Load Interconnection Requirements Across U.S. Transmission Entities

cs.AR ·2026-10-27 ·Rafi Zahedi, Rahul Anilkumar, Amin Zamani
publishedbenchmark similarity 0.65
Abstract

The rapid growth of large loads, especially data centers driven by artificial intelligence, is creating unprecedented demands on the North American electric grid. Data centers now account for nearly 80% of large load interconnection requests in the Western Interconnection, and U.S. electricity consumption from data centers is projected to reach 325-580 TWh by 2028. Despite this urgency, technical interconnection requirements for large loads have not yet matured and still contain several gaps. This paper presents a comparative analysis of large load interconnection requirements across eleven U.S. entities, including AEP, Ameren, CAISO, Dominion, Duke Energy, ERCOT, LIPA, MISO, PJM, Southern Company, and SPP, under seven technical categories: large load definition, load data and modeling, fault ride-through, load curtailment and shedding, dispatchability, power quality, and reactive power control. The analysis reveals significant variation in both the scope and specificity of requirements. LIPA addresses all seven technical categories at least partially, while Dominion and Duke Energy provide detailed coverage across nearly all categories. The analysis also finds that data center applicants can be viewed as potential grid resources, rather than only as consumers. The findings provide a structured baseline from which utilities, regulators, ISOs/RTOs, and developers can identify gaps, benchmark against peers, and accelerate the development of interconnection standards.

0.33

Impact of Data Center Load on Co-Optimized Generation and Transmission Expansion Planning with Embedded Unit Commitment

eess.SY ·2026-10-13 ·Haoxiang Wan, Xingpeng Li, Jonghwan Kwon
published similarity 0.65
Abstract · 6 pages, 2 figures, 3 tables. Accepted to the 2027 IEEE Texas Power and Energy Conference (TPEC)

The rapid growth of hyperscale data centers challenges grid expansion planning, yet existing studies focus largely on operational flexibility rather than long-term investment decisions. This paper examines how large data center loads sited at multiple buses affect co-optimized Transmission Expansion Planning (TEP) and Generation Expansion Planning (GEP). The problem is formulated as a multi-year, Unit Commitment (UC)-embedded mixed-integer linear program on the modified IEEE 24-bus Reliability Test System (RTS-24) with Electric Reliability Council of Texas (ERCOT)-calibrated renewable energy profiles. A 500 MW data center load, about 17.5% of the base-year peak, is allocated across four buses by voltage level, generation headroom, renewable co-location, and network connectivity. Integrating this load raises the 15-year net present value of total system cost by 1,794 million USD (+61.6%) and the system-average locational marginal price (LMP) by 45.2%, with operating cost dominating capital investment (84.2% versus 15.8%). Renewable curtailment remains negligible: existing renewables are already near full utilization, so the added demand is served almost entirely by incremental thermal generation. Most notably, the load shifts the optimal plan from transmission-only to generation-only, replacing the base-case 230 kV reinforcement with a new 400 MW combined-cycle gas turbine and showing that strategically sited generation can substitute for network reinforcement.

0.47

Virtual Transmission Lines from Data Center Workload Migration: Coordinated Multi-Year Transmission Expansion Planning

eess.SY ·2026-10-09 ·Mengxin Zhu, Qian Kai, Yadong Liu, Yingjie Yan, Haoyu Zhao
similarity 0.64
Abstract

The rapid growth of electricity demand from AI data centers is creating a dual mismatch in power systems: a temporal mismatch between fast-rising demand and slow transmission expansion, and a spatial mismatch between concentrated data-center loads and geographically dispersed renewable resources. These mismatches can exacerbate transmission congestion, resulting in unserved data-center load and renewable-energy curtailment. This study models geographic workload migration as a virtual transmission line (VTL) that changes nodal data-center demand without transferring physical electricity. A mixed-integer linear programming model is then developed to co-optimize multi-year candidate-line construction and workload migration, subject to construction delays, renewable-energy curtailment, unserved data-center load, workload-balance requirements, communication-bandwidth constraints, and link-latency limits. The model is evaluated over an eight-year planning horizon on a modified IEEE 14-bus system. The results show that coordinating VTL with physical transmission expansion reduces total system cost, unserved data-center load, and renewable-energy curtailment while alleviating transmission congestion. VTL-aware planning also requires one fewer candidate line than build-only planning. However, VTL alone cannot meet system demand and does not eliminate the need for physical transmission reinforcement. Sensitivity analysis indicates that VTL provides the greatest value when transfer capacity is tight, construction costs are high, load growth is rapid, and data-center flexibility is greater. Additional validation on the IEEE 118-bus system over a five-year planning horizon shows that coordinated planning retains its cost and reliability benefits while reducing physical expansion requirements.

0.06

Long-Term Operational Planning Using Scenario-Based System Load Forecasting

cs.CR ·2026-09-28 ·Akash Debnath, Shiuli Subhra Ghosh, Jaime De La Ree, Alex Freeman, Kavin D Jones
similarity 0.63
Abstract

The rapid expansion of hyperscale data centers is significantly increasing electricity demand in Northern Virginia. Dominion Energy, the region's primary electric utility, must reinforce its transmission network to support this growth. These projects require planned outages that must be evaluated months in advance to support construction planning and outage coordination while meeting NERC and PJM N-1 reliability requirements. Long-term outage studies are commonly performed day by day using monthly or seasonal peak-load assumptions. Although this approach simplifies analysis, it can be overly conservative because it does not capture granular load variability. Consequently, short-duration outages that may be feasible under realistic loading conditions are often postponed or denied, delaying critical transmission expansion and grid modernization projects. This paper evaluates the operational value of incorporating realistic multigranular load forecasts into long-term, contingency-based outage assessments and compares the results with conventional peak-based methods. Daily, weekly, and monthly forecasts are developed using statistical and machine-learning models, including SARIMA, Prophet, Gradient Boosting, and Random Forest, followed by bottom-up temporal reconciliation to maintain consistency across forecast horizons. Results show that granular load forecasts reduce unnecessary conservatism and improve outage accommodation, particularly for short-duration requests, without changing existing reliability criteria. The proposed approach can strengthen long-term outage coordination and support timely transmission reinforcement and grid modernization.

0.20

Shift or curtail? How much data-center flexibility is worth depends on the host power grid

eess.SY physics.soc-ph ·2026-08-20 ·Saroj Khanal, Geon Roh, Boyu Yao, Abraham Silverman, Dennice Gayme +3 more
similarity 0.63
Abstract · Submitted to Nature Energy

Data-center growth risks overbuilding power grid infrastructure and stranding capital. Flexible data-center operation can defer infrastructure investments, but its value depends on the flexibility mechanism and the host power grid characteristics. We classify data-center load as firm, flexible or interruptible, and embed them in capacity expansion applied to market-organized, fossil-heavy PJM and carbon-capped, centrally coordinated Korea. In PJM, the flexibility value is spatial: shifting workloads between zones reduces system cost by 6% in 2028 and 19% in 2038, avoiding 4.4 GW and 8.9 GW of gas and nuclear generation. In Korea, it is temporal: shifting load into midday solar hours makes 0.5 GW of additional solar worth building in 2028 and avoids 1.2 GW of gas and 0.3 GW of batteries in 2038. In both, realistic event-shape limits diminish the value of curtailment. The results show that flexibility procurement and its value are driven by grid characteristics and policy objectives.

0.46

Hosting Capacity Assessment of Data Centers with Voltage Ride-Through Capability in Power Systems

eess.SY ·2026-09-02 ·Pengyu Ren, Wei Sun, Fei Teng
similarity 0.63
Abstract

Large data centers are emerging as concentrated, power-electronic grid loads whose abrupt disconnection or transfer to on-site backup supply during voltage disturbances can remove large demand from the power system, and may create a system-level stability problem. Their interconnection feasibility therefore depends not only on steady-state thermal and voltage limits, but also on whether internal power-conditioning systems can maintain IT service while limiting customer-initiated load reduction. This paper presents a voltage ride-through (VRT)-aware data center and grid co-planning framework that couples transmission-level fault simulation with an internal data center ride-through model. Python-based dynamic simulations generate point-of-interconnection (POI) voltage trajectories under selected network faults, and the resulting waveforms drive an internal model incorporating IT and cooling-load dynamics, DC-link, Uninterruptible Power Supply (UPS) response, and converter apparent power limits. The IEEE 118-bus case study shows that internal VRT capability can become a binding interconnection constraint: steady-state planning alone can overestimate feasible data center capacity, whereas increased UPS converter headroom progressively restores hosting capacity. Under the reduced-order response models studied, the grid-forming mode provides greater ride-through margin than the current-limited grid-following mode under the same network fault conditions. The results further show that VRT constraints can materially change both the total hosting capacity of data centers and its spatial allocation across candidate interconnection buses.

0.16