Shift or curtail? How much data-center flexibility is worth depends on the host power grid

Saroj Khanal, Geon Roh, Boyu Yao, Abraham Silverman, Dennice Gayme, Charalambos Konstantinou, Jip Kim, Yury Dvorkin

eess.SY physics.soc-ph ·submitted 2026-08-20 04:15 UTC · v1

Abstract

Data-center growth risks overbuilding power grid infrastructure and stranding capital. Flexible data-center operation can defer infrastructure investments, but its value depends on the flexibility mechanism and the host power grid characteristics. We classify data-center load as firm, flexible or interruptible, and embed them in capacity expansion applied to market-organized, fossil-heavy PJM and carbon-capped, centrally coordinated Korea. In PJM, the flexibility value is spatial: shifting workloads between zones reduces system cost by 6% in 2028 and 19% in 2038, avoiding 4.4 GW and 8.9 GW of gas and nuclear generation. In Korea, it is temporal: shifting load into midday solar hours makes 0.5 GW of additional solar worth building in 2028 and avoids 1.2 GW of gas and 0.3 GW of batteries in 2038. In both, realistic event-shape limits diminish the value of curtailment. The results show that flexibility procurement and its value are driven by grid characteristics and policy objectives.

Comment
Submitted to Nature Energy

Closest papers

Nearest neighbours by meaning across the whole index.

On the Optimal Co-location of Data Centers with Renewable Energy Sources in SIDS

eess.SY math.OC ·2026-09-16 ·Shankar Ramharack, Patrick Hosein, Rajiv Sahadeo
top venue similarity 0.67
Abstract · 6 pages, 4 figures, accepted to 2026 IEEE Caribbean Conference (CaribCon) - Track 3 - Smart Systems, Robotics, and Automation

The rapid expansion of data centers presents both economic opportunities and systemic risks for Caribbean Small Island Developing States~(SIDS). This paper develops a PyPSA-based capacity expansion framework for optimal co-location of data centers with renewable energy infrastructure, incorporating behind-the-meter battery storage, workload flexibility (70\%/30\% inflexible/flexible split), and multi-bus transmission topology. Two case studies are examined: Trinidad~\&~Tobago (single-bus, 92\,MW Brechin Castle solar, 5\,MW data center) and Jamaica (4-bus 138\,kV JPS network, 15\,MW data center at Kingston). Jamaica's optimum deploys 405\,MW solar, 278\,MW wind, 800\,MWh grid-scale BESS, and 84\,MWh behind-the-meter BESS, achieving 42.5\% renewable penetration; Trinidad's gas-anchored optimum builds no new RE, and a sensitivity analysis shows solar entering at gas costs above \$65--70/MWh, a carbon price of \$25--50/tCO$_2$, or solar CAPEX of \$800/kW. A post-hoc distributionally robust stress test evaluates hurricane resilience, and a novel 10-factor siting framework addresses the regulatory gap in SIDS that lack data-center-specific zoning. Results show that energy-optimal locations may score poorly on societal criteria---noise, freshwater stress, zoning readiness. This demonstrates the need for integrated planning tools in small island contexts.

0.33

Minimizing Grid Interconnection Capacity Requirements for AI Data Centers: A Developer-Side Planning Framework with Onsite Resources and Workload Flexibility

eess.SY ·2026-08-29 ·Hassan Zahid Butt, Rida Fatima, Xingpeng Li
similarity 0.65
Abstract

Securing grid interconnection capacity has become a bottleneck for AI data center projects and can take longer than constructing the facilities themselves. This mismatch can delay deployment for years, making early interconnection planning essential. This paper develops ICP-AI, an interconnection capacity planning framework from a data center developer's perspective. The framework minimizes grid import capacity under a prescribed onsite investment budget while jointly sizing photovoltaic (PV) and battery energy storage system (BESS) resources and scheduling deadline constrained workload flexibility. A secondary refinement fixes the minimum grid capacity and selects the minimum-investment PV-BESS portfolio among solutions that achieve that capacity. The framework is evaluated using monthly composite stress profiles across varying temporal assumptions, load shapes, flexible load fractions, and deferral windows. Results show that interconnection capacity reduction depends strongly on the planning environment: at a $100M budget, it is about 6% for the high load factor baseline, exceeds 10% under monthly average solar availability, and reaches 13.3% for a more diurnal load. At a $10M budget, 5% flexible load with a 1 h workload deferral window reduces BESS capacity from 15.30 to 4.87 MWh while increasing capacity reduction from 4.43% to 4.84%. To test sensitivity to temporal compression, the model is also solved over the full 8,760 h chronology, which preserves the main capacity and flexibility trends. Overall, ICP-AI quantifies the interconnection capacity and infrastructure substitution value of workload flexibility, providing an investment-interconnection frontier to support capital allocation and early project planning in constrained grid environments.

0.12

Market Efficiency and Capacity Investment under Flexible Price-Making Loads: A Computational Study

eess.SY ·2026-10-30 ·Aron Brenner, Deepjyoti Deka, Saurabh Amin
similarity 0.64
Abstract

Large flexible loads such as data centers can shift consumption across locations and hours to lower their bills. We model a price-making consumer leading the system operator in a Stackelberg game and compare its shifts with a cost-minimizing planner's over a simulated RTS-GMLC year. Strategic temporal and spatial shifting capture 75% and 93% of the planner's savings, forgoing the rest mostly by withholding flexibility to protect favorable prices. Scarce capacity and abundant renewables raise this share for temporal shifting; scarce transmission lowers it for spatial shifting. Temporal and spatial flexibility substitute for thermal and transmission capacity, respectively, and complement renewables.

0.24

Impact of Data Center Load on Co-Optimized Generation and Transmission Expansion Planning with Embedded Unit Commitment

eess.SY ·2026-10-13 ·Haoxiang Wan, Xingpeng Li, Jonghwan Kwon
published similarity 0.64
Abstract · 6 pages, 2 figures, 3 tables. Accepted to the 2027 IEEE Texas Power and Energy Conference (TPEC)

The rapid growth of hyperscale data centers challenges grid expansion planning, yet existing studies focus largely on operational flexibility rather than long-term investment decisions. This paper examines how large data center loads sited at multiple buses affect co-optimized Transmission Expansion Planning (TEP) and Generation Expansion Planning (GEP). The problem is formulated as a multi-year, Unit Commitment (UC)-embedded mixed-integer linear program on the modified IEEE 24-bus Reliability Test System (RTS-24) with Electric Reliability Council of Texas (ERCOT)-calibrated renewable energy profiles. A 500 MW data center load, about 17.5% of the base-year peak, is allocated across four buses by voltage level, generation headroom, renewable co-location, and network connectivity. Integrating this load raises the 15-year net present value of total system cost by 1,794 million USD (+61.6%) and the system-average locational marginal price (LMP) by 45.2%, with operating cost dominating capital investment (84.2% versus 15.8%). Renewable curtailment remains negligible: existing renewables are already near full utilization, so the added demand is served almost entirely by incremental thermal generation. Most notably, the load shifts the optimal plan from transmission-only to generation-only, replacing the base-case 230 kV reinforcement with a new 400 MW combined-cycle gas turbine and showing that strategically sited generation can substitute for network reinforcement.

0.47

U.S. Data Center Growth Through 2030: A Critical Review of Grid Adequacy and Transmission Expansion Planning

eess.SY ·2026-11-10 ·Babak Porkar, Mona Ghassemi
hot direction similarity 0.63
Abstract

The growth of large data centers raises questions about both supply adequacy and the suitability of load representations used in connection studies. This paper critically reviews the U.S. demand, generation, and transmission outlook through 2030 and examines the implications for transmission expansion planning (TEP). Comparison of public forecasts highlights distinctions among annual average demand, peak demand, and grid connection capacity. National generating-capacity totals cannot establish a dependable surplus because resource availability, regional adequacy, transmission constraints, and project timing determine supply capability. Recent grid events and published dynamic studies demonstrate that faults can trigger substantial data-center transfers to backup supply, followed by delayed or coordinated demand recovery. These behaviors require appropriate representation within the conventional planning framework, alongside assessment of the requested maximum grid import. The selected literature reveals limited integration of validated data-center dynamic models into the technical screening and economic comparison of expansion alternatives. The review identifies the need to establish whether fault response and recovery change feasible connection capacity, required reinforcement, or the preferred transmission investment.

0.28

Quantifying the hosting capacity value of workload flexibility for AI data centers: A two-stage electricity-computation co-optimization framework

eess.SY ·2026-11-18 ·Jiakai Wu, Wei Sun, Pengyu Ren, Yifan Wang
hot direction similarity 0.63
Abstract

Grid connection constraints increasingly limit the expansion of AI data centers, yet the additional hosting capacity enabled by computational workload flexibility remains insufficiently quantified. This paper develops a two-stage electricity--computation co-optimization framework to quantify the individual and coordinated hosting capacity values of spatial and temporal workload flexibility. Data center capacities are determined endogenously, with computational task arrivals scaling with admitted capacity. Spatial routing of eligible interactive requests and temporal deferral of batch workloads are linked to server operation and facility power demand, subject to workload completion requirements and transmission constraints. The first stage maximizes aggregate hosting capacity; the second fixes the resulting site capacities and optimizes annual workload scheduling and generation dispatch to minimize generation and carbon costs. An 8760-hour case study with three data centers on a modified IEEE 118-bus system shows that temporal and spatial flexibility individually increase hosting capacity by 21.26\% and 5.37\%, respectively. Their coordinated use raises hosting capacity from 4635.1~MW to 6231.5~MW, a 34.44\% increase without network reinforcement. The coordinated gain exceeds the sum of the individual gains by 361.9~MW, demonstrating complementarity between spatial migration and temporal deferral. By redistributing computational demand across locations and operating hours, these mechanisms enable fuller utilization of existing transmission capacity. The findings establish workload flexibility as a quantifiable planning resource for accommodating additional data center capacity within existing transmission networks.

0.28

Job-Level Workload Allocation for Data Centers Under Flexible Interconnections

eess.SY ·2026-11-14 ·Tanmay Mishra, Arash Omidi, Mads R. Almassalkhi
hot direction similarity 0.62
Abstract · Submitted to IEEE PES General Meeting 2027

Flexible interconnections allow data centers to connect to the grid sooner without upgrading the grid infrastructure, if they accept limits on their grid power during periods of grid stress. When a limit is reached, the data center must slow some of its computing jobs. This choice sets the cost of flexibility, because the work done by a job is worth far more than the energy it uses. This paper models how jobs respond when their power is reduced, and proposes a real-time method that shares the available power among jobs according to their value. It also gives grid planners a simple measure of how much power a data center can reduce, and for how long. A one-year case study of a 100-MW data center shows that the proposed method lowers the cost of meeting grid limits, and that on-site generation and storage lower it further.

0.24

Data-center growth impacts household electricity costs more through wholesale prices than through grid reinforcement

eess.SY econ.GN ·2026-11-11 ·Lingdong Zhou, Wenjia Xia, Jiyu Wang, Fei Ding, Xiangqi Zhu
hot direction similarity 0.61
Abstract · 22 pages, 8 figures, 1 table. Lingdong Zhou and Wenjia Xia contributed equally to this work

Rapid data-center expansion is raising concerns about electricity affordability, yet how the costs of serving these large new loads reach residential customers remains poorly understood. Here, we quantify the potential impact of 371 announced Texas data-center projects, totaling 38.9 GW by 2030, on residential electricity costs by linking power system expansion, wholesale electricity markets, transmission reinforcement, and retail cost allocation. We find that accommodating this demand increases modeled residential electricity costs in one representative case by 1.64 cents/kWh, with 68% arising from higher wholesale electricity prices and 32% from regulated transmission charges. Allowing new gas generation near data centers reduces the 2023 residential cost increase to 0.92 cents/kWh, whereas excluding data centers from the transmission cost-sharing base raises it to 1.87 cents/kWh. These findings reveal that the residential cost burden of data-center growth is driven primarily by wholesale electricity price increases, rather than direct transmission investment costs, and depends critically on generation siting, infrastructure planning, and cost allocation.

0.29