Impact of Data Center Load on Co-Optimized Generation and Transmission Expansion Planning with Embedded Unit Commitment

Haoxiang Wan, Xingpeng Li, Jonghwan Kwon

eess.SY ·submitted 2026-10-13 13:36 UTC · v1
published

Abstract

The rapid growth of hyperscale data centers challenges grid expansion planning, yet existing studies focus largely on operational flexibility rather than long-term investment decisions. This paper examines how large data center loads sited at multiple buses affect co-optimized Transmission Expansion Planning (TEP) and Generation Expansion Planning (GEP). The problem is formulated as a multi-year, Unit Commitment (UC)-embedded mixed-integer linear program on the modified IEEE 24-bus Reliability Test System (RTS-24) with Electric Reliability Council of Texas (ERCOT)-calibrated renewable energy profiles. A 500 MW data center load, about 17.5% of the base-year peak, is allocated across four buses by voltage level, generation headroom, renewable co-location, and network connectivity. Integrating this load raises the 15-year net present value of total system cost by 1,794 million USD (+61.6%) and the system-average locational marginal price (LMP) by 45.2%, with operating cost dominating capital investment (84.2% versus 15.8%). Renewable curtailment remains negligible: existing renewables are already near full utilization, so the added demand is served almost entirely by incremental thermal generation. Most notably, the load shifts the optimal plan from transmission-only to generation-only, replacing the base-case 230 kV reinforcement with a new 400 MW combined-cycle gas turbine and showing that strategically sited generation can substitute for network reinforcement.

Comment
6 pages, 2 figures, 3 tables. Accepted to the 2027 IEEE Texas Power and Energy Conference (TPEC)

Closest papers

Nearest neighbours by meaning across the whole index.

Virtual Transmission Lines from Data Center Workload Migration: Coordinated Multi-Year Transmission Expansion Planning

eess.SY ·2026-10-09 ·Mengxin Zhu, Qian Kai, Yadong Liu, Yingjie Yan, Haoyu Zhao
similarity 0.75
Abstract

The rapid growth of electricity demand from AI data centers is creating a dual mismatch in power systems: a temporal mismatch between fast-rising demand and slow transmission expansion, and a spatial mismatch between concentrated data-center loads and geographically dispersed renewable resources. These mismatches can exacerbate transmission congestion, resulting in unserved data-center load and renewable-energy curtailment. This study models geographic workload migration as a virtual transmission line (VTL) that changes nodal data-center demand without transferring physical electricity. A mixed-integer linear programming model is then developed to co-optimize multi-year candidate-line construction and workload migration, subject to construction delays, renewable-energy curtailment, unserved data-center load, workload-balance requirements, communication-bandwidth constraints, and link-latency limits. The model is evaluated over an eight-year planning horizon on a modified IEEE 14-bus system. The results show that coordinating VTL with physical transmission expansion reduces total system cost, unserved data-center load, and renewable-energy curtailment while alleviating transmission congestion. VTL-aware planning also requires one fewer candidate line than build-only planning. However, VTL alone cannot meet system demand and does not eliminate the need for physical transmission reinforcement. Sensitivity analysis indicates that VTL provides the greatest value when transfer capacity is tight, construction costs are high, load growth is rapid, and data-center flexibility is greater. Additional validation on the IEEE 118-bus system over a five-year planning horizon shows that coordinated planning retains its cost and reliability benefits while reducing physical expansion requirements.

0.06

On the Optimal Co-location of Data Centers with Renewable Energy Sources in SIDS

eess.SY math.OC ·2026-09-16 ·Shankar Ramharack, Patrick Hosein, Rajiv Sahadeo
top venue similarity 0.71
Abstract · 6 pages, 4 figures, accepted to 2026 IEEE Caribbean Conference (CaribCon) - Track 3 - Smart Systems, Robotics, and Automation

The rapid expansion of data centers presents both economic opportunities and systemic risks for Caribbean Small Island Developing States~(SIDS). This paper develops a PyPSA-based capacity expansion framework for optimal co-location of data centers with renewable energy infrastructure, incorporating behind-the-meter battery storage, workload flexibility (70\%/30\% inflexible/flexible split), and multi-bus transmission topology. Two case studies are examined: Trinidad~\&~Tobago (single-bus, 92\,MW Brechin Castle solar, 5\,MW data center) and Jamaica (4-bus 138\,kV JPS network, 15\,MW data center at Kingston). Jamaica's optimum deploys 405\,MW solar, 278\,MW wind, 800\,MWh grid-scale BESS, and 84\,MWh behind-the-meter BESS, achieving 42.5\% renewable penetration; Trinidad's gas-anchored optimum builds no new RE, and a sensitivity analysis shows solar entering at gas costs above \$65--70/MWh, a carbon price of \$25--50/tCO$_2$, or solar CAPEX of \$800/kW. A post-hoc distributionally robust stress test evaluates hurricane resilience, and a novel 10-factor siting framework addresses the regulatory gap in SIDS that lack data-center-specific zoning. Results show that energy-optimal locations may score poorly on societal criteria---noise, freshwater stress, zoning readiness. This demonstrates the need for integrated planning tools in small island contexts.

0.33

Generation and Transmission Expansion Planning with BESS-Based Virtual Transmission Lines

eess.SY ·2026-10-02 ·Qiushi Wang, Xingpeng Li
similarity 0.70
Abstract · Submitted to Energy Conversion and Economics

This paper proposes a mathematical model for long-term Generation and Transmission Expansion Planning (GTEP) that integrates a relaxed Virtual Transmission Line (VTL) as a Storage in Place of Transmission Asset (SIPTA) strategy to address challenges posed by transmission capacity shortages and system congestion in deregulated power markets, particularly under the rapid growth of renewable energy resources and integrated data centers. The proposed VTL formulation coordinates the operation of the two battery energy storage systems (BESSs) forming a VTL pair by preventing them from charging or discharging simultaneously, thereby providing additional congestion relief without introducing an explicit congestion cost into the objective function. Base case studies on a revised IEEE 24-bus system demonstrate that VTL reduces system congestion compared with the standalone BESS case, achieving a 12.3% reduction in weighted total congestion and up to approximately 67% reduction in congestion on individual transmission branches, with only a 0.3% increase in total planning cost. Furthermore, improvements across multiple congestion metrics indicate that the benefits of VTL extend beyond reducing congested line-hours to reducing congestion rent and N-1 transmission violations in the base case. These results demonstrate the potential of VTL to provide congestion mitigation that complements standalone BESS applications.

0.17

Data-center growth impacts household electricity costs more through wholesale prices than through grid reinforcement

eess.SY econ.GN ·2026-11-11 ·Lingdong Zhou, Wenjia Xia, Jiyu Wang, Fei Ding, Xiangqi Zhu
hot direction similarity 0.70
Abstract · 22 pages, 8 figures, 1 table. Lingdong Zhou and Wenjia Xia contributed equally to this work

Rapid data-center expansion is raising concerns about electricity affordability, yet how the costs of serving these large new loads reach residential customers remains poorly understood. Here, we quantify the potential impact of 371 announced Texas data-center projects, totaling 38.9 GW by 2030, on residential electricity costs by linking power system expansion, wholesale electricity markets, transmission reinforcement, and retail cost allocation. We find that accommodating this demand increases modeled residential electricity costs in one representative case by 1.64 cents/kWh, with 68% arising from higher wholesale electricity prices and 32% from regulated transmission charges. Allowing new gas generation near data centers reduces the 2023 residential cost increase to 0.92 cents/kWh, whereas excluding data centers from the transmission cost-sharing base raises it to 1.87 cents/kWh. These findings reveal that the residential cost burden of data-center growth is driven primarily by wholesale electricity price increases, rather than direct transmission investment costs, and depends critically on generation siting, infrastructure planning, and cost allocation.

0.37

Assessing Data Center Hosting Capacity Considering Electromagnetic Transient Dynamics

eess.SY ·2026-11-11 ·Fan Jiang, Xingpeng Li
hot direction similarity 0.68
Abstract

Hosting capacity is commonly assessed with steady-state optimization, which leaves the dynamic response of the data center and the grid at the resulting operating point untested. This paper assesses candidate data center capacities by coupling a unit commitment (UC) model with electromagnetic transient (EMT) simulation. During the capacity search, the UC model determines the economic dispatch for each tested data center capacity, and the resulting operating points are tested for settling with the generators committed online by the UC model and after a selected synchronous generator outage. Three nested capacities are obtained: the optimization-based steady-state capacity, the dynamic pre-outage capacity, and the post-outage dynamic capacity, each bounded by the previous one. On a test system with a detailed data center model, both dynamic capacities fall well below the optimization capacity, and the ranking of connection locations changes with the assessment stage and with the outage. In the most severe outage case at each candidate bus, the capacity is about 30% below the steady-state capacity. Thus, the dynamic response of the data center and the grid should be part of the hosting capacity assessment, and the comparison of connection locations should be made on the post-outage dynamic capacity.

0.34

Unlocking AI Data Center Interconnection Capacity Through Coordinated Grid and Data Center Flexibility

eess.SY ·2026-10-04 ·Rida Fatima, Xingpeng Li
similarity 0.67
Abstract

The rapid growth of AI data centers is creating concentrated electricity demands that can exceed available distribution network headroom and delay interconnection. This paper investigates whether capacity can be used effectively by coordinating flexibility on both sides of the interconnection. A day-ahead mixed integer second order cone programming framework maximizes feasible AI data center IT capacity using utility side conservation voltage reduction and network topology reconfiguration, together with data center workload shifting and reserve constrained uninterruptible power supply storage. Background feeder demand uses voltage dependent ZIP models, while the data center is modeled as constant power demand using Training, Inference, and Mixed workload profiles. A two-stage solution first maximizes interconnection capacity and then minimizes feeder losses for the retained capacity, with numerical relaxation screening. Studies on a 116-bus model derived from the IEEE 123-node feeder show that, at the constrained bus-60 connection point, grid side flexibility, driven almost entirely by network reconfiguration, increases feasible IT capacity by approximately 42.5-45.0%, while data center flexibility alone provides approximately 2.1-5.4% gains. Coordinated operation increases feasible IT capacity from approximately 10.5-10.6 MW under BASE operation to 15.3-16.0 MW, corresponding to gains of approximately 45.9-50.8%; the 16.0 MW Inference result is limited by the adopted UPS reserve requirement. Benefits are strongly location dependent and influenced by workload flexibility, deferral duration, PUE, UPS energy and reserve requirements, and feeder loading. Under a combined adverse operating condition, FULL capacity decreases by only 3.4% relative to the nominal Mixed case while retaining substantial additional capacity over BASE.

0.08

Trust-Region Benders for Scalable Multiperiod Expansion Planning for Transmission and Storage

eess.SY ·2026-10-23 ·Kevin Wu, Rabab Haider, Pascal Van Hentenryck
published similarity 0.66
Abstract · Presented at PowerUp 2026, September 9-11, 2026, Boulder, Colorado

Transmission expansion planning (TEP) seeks to identify cost-effective investment strategies that enable power systems to reliably meet future demand, while accounting for the location, timing, and operational impacts of infrastructure upgrades. As demand grows and renewable penetration increases, there is growing interest in jointly modeling energy storage investments to enhance operational flexibility. This work presents a multiperiod formulation that co-optimizes transmission reconductoring and energy storage installation across multiple planning periods. To solve the resulting large-scale problem efficiently, a Benders decomposition with per-period trust-region stabilization and a relaxation-based warm-start procedure is proposed. The approach is demonstrated on a 2,000-bus Texas system, producing an investment plan spanning 2030-2045 with optimality gap below 1.0%, and is compared against a rolling-horizon approach to highlight the benefits of multiperiod coordination.

0.29

U.S. Data Center Growth Through 2030: A Critical Review of Grid Adequacy and Transmission Expansion Planning

eess.SY ·2026-11-10 ·Babak Porkar, Mona Ghassemi
hot direction similarity 0.65
Abstract

The growth of large data centers raises questions about both supply adequacy and the suitability of load representations used in connection studies. This paper critically reviews the U.S. demand, generation, and transmission outlook through 2030 and examines the implications for transmission expansion planning (TEP). Comparison of public forecasts highlights distinctions among annual average demand, peak demand, and grid connection capacity. National generating-capacity totals cannot establish a dependable surplus because resource availability, regional adequacy, transmission constraints, and project timing determine supply capability. Recent grid events and published dynamic studies demonstrate that faults can trigger substantial data-center transfers to backup supply, followed by delayed or coordinated demand recovery. These behaviors require appropriate representation within the conventional planning framework, alongside assessment of the requested maximum grid import. The selected literature reveals limited integration of validated data-center dynamic models into the technical screening and economic comparison of expansion alternatives. The review identifies the need to establish whether fault response and recovery change feasible connection capacity, required reinforcement, or the preferred transmission investment.

0.36