Virtual Transmission Lines from Data Center Workload Migration: Coordinated Multi-Year Transmission Expansion Planning

Mengxin Zhu, Qian Kai, Yadong Liu, Yingjie Yan, Haoyu Zhao

eess.SY ·submitted 2026-10-09 05:44 UTC · v1

Abstract

The rapid growth of electricity demand from AI data centers is creating a dual mismatch in power systems: a temporal mismatch between fast-rising demand and slow transmission expansion, and a spatial mismatch between concentrated data-center loads and geographically dispersed renewable resources. These mismatches can exacerbate transmission congestion, resulting in unserved data-center load and renewable-energy curtailment. This study models geographic workload migration as a virtual transmission line (VTL) that changes nodal data-center demand without transferring physical electricity. A mixed-integer linear programming model is then developed to co-optimize multi-year candidate-line construction and workload migration, subject to construction delays, renewable-energy curtailment, unserved data-center load, workload-balance requirements, communication-bandwidth constraints, and link-latency limits. The model is evaluated over an eight-year planning horizon on a modified IEEE 14-bus system. The results show that coordinating VTL with physical transmission expansion reduces total system cost, unserved data-center load, and renewable-energy curtailment while alleviating transmission congestion. VTL-aware planning also requires one fewer candidate line than build-only planning. However, VTL alone cannot meet system demand and does not eliminate the need for physical transmission reinforcement. Sensitivity analysis indicates that VTL provides the greatest value when transfer capacity is tight, construction costs are high, load growth is rapid, and data-center flexibility is greater. Additional validation on the IEEE 118-bus system over a five-year planning horizon shows that coordinated planning retains its cost and reliability benefits while reducing physical expansion requirements.

Closest papers

Nearest neighbours by meaning across the whole index.

Generation and Transmission Expansion Planning with BESS-Based Virtual Transmission Lines

eess.SY ·2026-10-02 ·Qiushi Wang, Xingpeng Li
similarity 0.78
Abstract · Submitted to Energy Conversion and Economics

This paper proposes a mathematical model for long-term Generation and Transmission Expansion Planning (GTEP) that integrates a relaxed Virtual Transmission Line (VTL) as a Storage in Place of Transmission Asset (SIPTA) strategy to address challenges posed by transmission capacity shortages and system congestion in deregulated power markets, particularly under the rapid growth of renewable energy resources and integrated data centers. The proposed VTL formulation coordinates the operation of the two battery energy storage systems (BESSs) forming a VTL pair by preventing them from charging or discharging simultaneously, thereby providing additional congestion relief without introducing an explicit congestion cost into the objective function. Base case studies on a revised IEEE 24-bus system demonstrate that VTL reduces system congestion compared with the standalone BESS case, achieving a 12.3% reduction in weighted total congestion and up to approximately 67% reduction in congestion on individual transmission branches, with only a 0.3% increase in total planning cost. Furthermore, improvements across multiple congestion metrics indicate that the benefits of VTL extend beyond reducing congested line-hours to reducing congestion rent and N-1 transmission violations in the base case. These results demonstrate the potential of VTL to provide congestion mitigation that complements standalone BESS applications.

0.17

Impact of Data Center Load on Co-Optimized Generation and Transmission Expansion Planning with Embedded Unit Commitment

eess.SY ·2026-10-13 ·Haoxiang Wan, Xingpeng Li, Jonghwan Kwon
published similarity 0.75
Abstract · 6 pages, 2 figures, 3 tables. Accepted to the 2027 IEEE Texas Power and Energy Conference (TPEC)

The rapid growth of hyperscale data centers challenges grid expansion planning, yet existing studies focus largely on operational flexibility rather than long-term investment decisions. This paper examines how large data center loads sited at multiple buses affect co-optimized Transmission Expansion Planning (TEP) and Generation Expansion Planning (GEP). The problem is formulated as a multi-year, Unit Commitment (UC)-embedded mixed-integer linear program on the modified IEEE 24-bus Reliability Test System (RTS-24) with Electric Reliability Council of Texas (ERCOT)-calibrated renewable energy profiles. A 500 MW data center load, about 17.5% of the base-year peak, is allocated across four buses by voltage level, generation headroom, renewable co-location, and network connectivity. Integrating this load raises the 15-year net present value of total system cost by 1,794 million USD (+61.6%) and the system-average locational marginal price (LMP) by 45.2%, with operating cost dominating capital investment (84.2% versus 15.8%). Renewable curtailment remains negligible: existing renewables are already near full utilization, so the added demand is served almost entirely by incremental thermal generation. Most notably, the load shifts the optimal plan from transmission-only to generation-only, replacing the base-case 230 kV reinforcement with a new 400 MW combined-cycle gas turbine and showing that strategically sited generation can substitute for network reinforcement.

0.27

Unlocking AI Data Center Interconnection Capacity Through Coordinated Grid and Data Center Flexibility

eess.SY ·2026-10-04 ·Rida Fatima, Xingpeng Li
similarity 0.66
Abstract

The rapid growth of AI data centers is creating concentrated electricity demands that can exceed available distribution network headroom and delay interconnection. This paper investigates whether capacity can be used effectively by coordinating flexibility on both sides of the interconnection. A day-ahead mixed integer second order cone programming framework maximizes feasible AI data center IT capacity using utility side conservation voltage reduction and network topology reconfiguration, together with data center workload shifting and reserve constrained uninterruptible power supply storage. Background feeder demand uses voltage dependent ZIP models, while the data center is modeled as constant power demand using Training, Inference, and Mixed workload profiles. A two-stage solution first maximizes interconnection capacity and then minimizes feeder losses for the retained capacity, with numerical relaxation screening. Studies on a 116-bus model derived from the IEEE 123-node feeder show that, at the constrained bus-60 connection point, grid side flexibility, driven almost entirely by network reconfiguration, increases feasible IT capacity by approximately 42.5-45.0%, while data center flexibility alone provides approximately 2.1-5.4% gains. Coordinated operation increases feasible IT capacity from approximately 10.5-10.6 MW under BASE operation to 15.3-16.0 MW, corresponding to gains of approximately 45.9-50.8%; the 16.0 MW Inference result is limited by the adopted UPS reserve requirement. Benefits are strongly location dependent and influenced by workload flexibility, deferral duration, PUE, UPS energy and reserve requirements, and feeder loading. Under a combined adverse operating condition, FULL capacity decreases by only 3.4% relative to the nominal Mixed case while retaining substantial additional capacity over BASE.

0.08

Spatial LLM Workload Shifting Needs Foresight: Model Commitment for AI Data Center Operation under Power Grid Constraints

eess.SY ·2026-09-09 ·Bojun Du, Hongyang Jia, Tonghui Li, Qingchun Hou, Ze Wang +2 more
similarity 0.66
Abstract · 3 pages, 2 figures

AI data centers may face power supply shortages during certain periods, requiring operators to shift large language model (LLM) inference workloads spatially to maintain service rates. However, existing workload-shifting methods typically assume that any data center with sufficient computing resources can immediately serve shifted requests, which may lead to infeasible transfers and unserved demand. This letter proposes model commitment (MC), a mixed-integer linear programming framework that jointly schedules model deployment and cross-site request routing under power constraints and electricity-price signals. First, MC formulates the intertemporal coupling introduced by model replica loading. Second, it translates prefill and decode latency requirements into the amount of demand that each replica can serve. Case studies based on real-world data show that MC enables AI data center operators to achieve a 100% service rate under time-varying grid conditions and reduce total operating cost by 29.0%.

0.24

Minimizing Grid Interconnection Capacity Requirements for AI Data Centers: A Developer-Side Planning Framework with Onsite Resources and Workload Flexibility

eess.SY ·2026-08-29 ·Hassan Zahid Butt, Rida Fatima, Xingpeng Li
similarity 0.65
Abstract

Securing grid interconnection capacity has become a bottleneck for AI data center projects and can take longer than constructing the facilities themselves. This mismatch can delay deployment for years, making early interconnection planning essential. This paper develops ICP-AI, an interconnection capacity planning framework from a data center developer's perspective. The framework minimizes grid import capacity under a prescribed onsite investment budget while jointly sizing photovoltaic (PV) and battery energy storage system (BESS) resources and scheduling deadline constrained workload flexibility. A secondary refinement fixes the minimum grid capacity and selects the minimum-investment PV-BESS portfolio among solutions that achieve that capacity. The framework is evaluated using monthly composite stress profiles across varying temporal assumptions, load shapes, flexible load fractions, and deferral windows. Results show that interconnection capacity reduction depends strongly on the planning environment: at a $100M budget, it is about 6% for the high load factor baseline, exceeds 10% under monthly average solar availability, and reaches 13.3% for a more diurnal load. At a $10M budget, 5% flexible load with a 1 h workload deferral window reduces BESS capacity from 15.30 to 4.87 MWh while increasing capacity reduction from 4.43% to 4.84%. To test sensitivity to temporal compression, the model is also solved over the full 8,760 h chronology, which preserves the main capacity and flexibility trends. Overall, ICP-AI quantifies the interconnection capacity and infrastructure substitution value of workload flexibility, providing an investment-interconnection frontier to support capital allocation and early project planning in constrained grid environments.

0.12

U.S. Data Center Growth Through 2030: A Critical Review of Grid Adequacy and Transmission Expansion Planning

eess.SY ·2026-11-10 ·Babak Porkar, Mona Ghassemi
hot direction similarity 0.64
Abstract

The growth of large data centers raises questions about both supply adequacy and the suitability of load representations used in connection studies. This paper critically reviews the U.S. demand, generation, and transmission outlook through 2030 and examines the implications for transmission expansion planning (TEP). Comparison of public forecasts highlights distinctions among annual average demand, peak demand, and grid connection capacity. National generating-capacity totals cannot establish a dependable surplus because resource availability, regional adequacy, transmission constraints, and project timing determine supply capability. Recent grid events and published dynamic studies demonstrate that faults can trigger substantial data-center transfers to backup supply, followed by delayed or coordinated demand recovery. These behaviors require appropriate representation within the conventional planning framework, alongside assessment of the requested maximum grid import. The selected literature reveals limited integration of validated data-center dynamic models into the technical screening and economic comparison of expansion alternatives. The review identifies the need to establish whether fault response and recovery change feasible connection capacity, required reinforcement, or the preferred transmission investment.

0.36

Modeling of Network Constraints in Large-scale Capacity Expansion Optimization of Power Grids

eess.SY math.OC ·2026-08-28 ·Yu Weng, Lara Booth, Priya L. Donti, Ruaridh Macdonald
publishedtheoryhot direction similarity 0.62
Abstract

Capacity expansion modeling plays a critical role in optimizing the deployment of new generation, storage, and transmission, typically at national and regional levels. To support long-term planning, these models consider a large set of energy technologies and policies, along with decades of weather and demand data. Realistic capacity expansion models thus become high-dimensional optimization problems, with hundreds of millions of variables and constraints, which are challenging to solve. A common strategy to address this complexity is to omit non-linear, non-convex AC optimal power flow (ACOPF) constraints and instead use linearized power balance equations or transport formulations. While these simplifications improve tractability, they limit our understanding of how power flow and the physical properties of power networks impact investment decisions across generation, storage, and transmission infrastructure. This paper addresses this gap by extending the GenX capacity expansion model to incorporate fixed point theorem-based network constraints. These embed ACOPF-based considerations while maintaining the tractability of the planning model, nearly preserving the dimensionality of the transport formulation and incurring only modest runtime increases. This approach is much cheaper than embedding ACOPF directly, making it appropriate for large-scale capacity planning problems. We compare our approach to the original transport-based GenX model as well as a non-linear, non-convex version that incorporates the full ACOPF constraints, for a case study of the ISO New England grid.

0.47

Data-center growth impacts household electricity costs more through wholesale prices than through grid reinforcement

eess.SY econ.GN ·2026-11-11 ·Lingdong Zhou, Wenjia Xia, Jiyu Wang, Fei Ding, Xiangqi Zhu
hot direction similarity 0.62
Abstract · 22 pages, 8 figures, 1 table. Lingdong Zhou and Wenjia Xia contributed equally to this work

Rapid data-center expansion is raising concerns about electricity affordability, yet how the costs of serving these large new loads reach residential customers remains poorly understood. Here, we quantify the potential impact of 371 announced Texas data-center projects, totaling 38.9 GW by 2030, on residential electricity costs by linking power system expansion, wholesale electricity markets, transmission reinforcement, and retail cost allocation. We find that accommodating this demand increases modeled residential electricity costs in one representative case by 1.64 cents/kWh, with 68% arising from higher wholesale electricity prices and 32% from regulated transmission charges. Allowing new gas generation near data centers reduces the 2023 residential cost increase to 0.92 cents/kWh, whereas excluding data centers from the transmission cost-sharing base raises it to 1.87 cents/kWh. These findings reveal that the residential cost burden of data-center growth is driven primarily by wholesale electricity price increases, rather than direct transmission investment costs, and depends critically on generation siting, infrastructure planning, and cost allocation.

0.37