CS Paper Radar

Hosting Capacity Assessment of Data Centers with Voltage Ride-Through Capability in Power Systems

Pengyu Ren, Wei Sun, Fei Teng

eess.SY ·submitted 2026-09-02 18:04 UTC · v1

Abstract

Large data centers are emerging as concentrated, power-electronic grid loads whose abrupt disconnection or transfer to on-site backup supply during voltage disturbances can remove large demand from the power system, and may create a system-level stability problem. Their interconnection feasibility therefore depends not only on steady-state thermal and voltage limits, but also on whether internal power-conditioning systems can maintain IT service while limiting customer-initiated load reduction. This paper presents a voltage ride-through (VRT)-aware data center and grid co-planning framework that couples transmission-level fault simulation with an internal data center ride-through model. Python-based dynamic simulations generate point-of-interconnection (POI) voltage trajectories under selected network faults, and the resulting waveforms drive an internal model incorporating IT and cooling-load dynamics, DC-link, Uninterruptible Power Supply (UPS) response, and converter apparent power limits. The IEEE 118-bus case study shows that internal VRT capability can become a binding interconnection constraint: steady-state planning alone can overestimate feasible data center capacity, whereas increased UPS converter headroom progressively restores hosting capacity. Under the reduced-order response models studied, the grid-forming mode provides greater ride-through margin than the current-limited grid-following mode under the same network fault conditions. The results further show that VRT constraints can materially change both the total hosting capacity of data centers and its spatial allocation across candidate interconnection buses.

Closest papers

Nearest neighbours by meaning across the whole index.

EMT Modeling and Coordinated Mode-Transition Ride-Through Control of Modern Data Centers

eess.SY ·2026-11-05 ·Junyuan Zheng, Salish Maharjan, Min Lwin, Soummya Roy, Zhaoyu Wang +3 more
similarity 0.73
Abstract

Large data centers are emerging as power-electronic loads whose response to grid voltage disturbances can affect bulk-system stability. This paper presents the composition and control characteristics of a proprietary electromagnetic transient (EMT) model of a modern data center comprising an uninterruptible power supply (UPS) with battery energy storage, induction-motor cooling loads, a computer room air handler (CRAH) driven by a variable-frequency drive (VFD), and an aggregated server load. A voltage-based state machine coordinates three aspects of the facility response: the UPS operating mode (eco, double conversion, or battery), the supply path of the CRAH, and a ramped reconnection of the grid-side UPS converter after the disturbance clears. A 100 MW facility is implemented in PSCAD/EMTDC and benchmarked against the PSSE PERC1 aggregate data center model under a symmetrical three-phase fault and low- and high-voltage ride-through (LVRT/HVRT) events. The two models agree closely in their voltage and active-power trajectories, while the EMT model also resolves the converter and motor-reacceleration transients that the phasor-domain model cannot.

0.50

Low-Voltage Ride-Through in AI Data Centers via Coordinated Battery and Computing Load Control

eess.SY ·2026-11-14 ·Xiaoyang Wang, Xin Chen, Fang Chen Lin, Prasad Enjeti, Ali Yazdanpanah +2 more
hot direction similarity 0.73
Abstract · 5 pages, 7 figures

The ability of large AI data centers to ride through grid voltage sags is critical to power system stability and reliability. This paper frames data center low-voltage ride-through (LVRT) as a DC-link power balance problem. Once the rectifier reaches its current limit, the power drawn from the grid decreases in proportion to the grid voltage. The DC-link capacitor can supply the resulting power deficit only briefly before the DC-link voltage falls low enough to trigger undervoltage protection tripping. To address this issue, this paper proposes effective control strategies for coordinating uninterruptible power supply (UPS) battery and computing load curtailment to offset the power deficit and enable LVRT at minimum control cost. Three control scenarios are studied: UPS battery support alone, computing load curtailment alone, and the coordinated use of both resources. Electromagnetic transient (EMT) simulations using the TAMU-ERCOT AI data center model demonstrate that battery support and the coordinated strategy achieve LVRT for all tested sags, including a near-zero-voltage fault, while load curtailment alone rides through moderate voltage sags.

0.29

Reducing Data-Center Load Transfers with Ride-Through-Aware Voltage Control

eess.SY ·2026-11-05 ·Siyu Lu, Yang Weng
similarity 0.73
Abstract · 10 pages, 5 figures

Fault-induced transfers of large data centers to backup supply can cause abrupt reductions in grid-served demand. Coordinating reactive-power support to mitigate these transfers requires consideration of facility-specific voltage--duration ride-through characteristics, particularly when support capacity is limited. This paper develops a ride-through-aware extension of quadratic voltage control that assesses voltage deviations relative to the admissible margins specified by these characteristics. We establish four design requirements that jointly express envelope-based severity, duration dependence, and preventive voltage-restoration incentives. Within a multiplicatively gated quadratic class, we derive necessary and sufficient conditions for satisfying these requirements and construct an explicit family of envelope-normalized objectives. We apply the proposed objectives to reactive-power coordination and evaluate their performance on the IEEE 14-bus, New England 39-bus, and NPCC 140-bus systems. Comparisons with Volt/VAR control, conventional nominal-voltage tracking, and recent data-center voltage-control methods demonstrate improved data-center retention under matched reactive-power support constraints. In the IEEE 14-bus study, the proposed controller reduces the mean data-center disconnection rate by 44.8\% and grid-demand loss by 27.4\% compared with the best-performing baseline. These results highlight the benefit of incorporating data-center ride-through requirements into reactive-power allocation.

0.50

Steady-State Equivalent Circuit Model for Data Center Loads

eess.SY ·2026-08-18 ·Muhammad Hamza Ali, Peng Sang, Hyeon Woo, Hyein Kang, Sungyun Choi +1 more
similarity 0.70
Abstract

Planners currently represent data centers as aggregate constant-PQ or ZIP loads in steady-state interconnection and contingency studies. These aggregate models are computationally convenient. However, they obscure the electrical relationship between computational workloads, server utilization, and grid-side demand. They ignore the internal power-electronic conversion stages of IT loads and assume homogeneous workload distributions across the compute clusters. This hides operating-point-dependent converter losses and efficiency variations. We propose a steady-state equivalent-circuit model (ECM) for data centers, which explicitly builds circuit models for IT loads, power supply units, cooling, and auxiliary systems. For power supply units, the equivalent circuit model explicitly represents internal power-electronic conversion stages. For IT loads, we develop a utilization-dependent server power model, and we combine it with loss-aware ECMs of power supply units. This approach captures the grid-side impact of heterogeneous workload distributions while preserving compatibility with conventional power-flow analysis. We evaluate this data center ECM in large-scale transmission power flows, using Monte Carlo simulations under heterogeneous and homogeneous cluster utilization. In comparison with the fixed-efficiency constant-PQ model, the ECM predicts that the most stressed line exceeds its thermal limit in about 30% of Monte Carlo samples. The results further show that homogeneous server utilization overstates line-loading variability by 17%-46% relative to heterogeneous server utilization, depending on the intra-cluster workload correlation.

0.47

Unlocking AI Data Center Interconnection Capacity Through Coordinated Grid and Data Center Flexibility

eess.SY ·2026-10-04 ·Rida Fatima, Xingpeng Li
similarity 0.69
Abstract

The rapid growth of AI data centers is creating concentrated electricity demands that can exceed available distribution network headroom and delay interconnection. This paper investigates whether capacity can be used effectively by coordinating flexibility on both sides of the interconnection. A day-ahead mixed integer second order cone programming framework maximizes feasible AI data center IT capacity using utility side conservation voltage reduction and network topology reconfiguration, together with data center workload shifting and reserve constrained uninterruptible power supply storage. Background feeder demand uses voltage dependent ZIP models, while the data center is modeled as constant power demand using Training, Inference, and Mixed workload profiles. A two-stage solution first maximizes interconnection capacity and then minimizes feeder losses for the retained capacity, with numerical relaxation screening. Studies on a 116-bus model derived from the IEEE 123-node feeder show that, at the constrained bus-60 connection point, grid side flexibility, driven almost entirely by network reconfiguration, increases feasible IT capacity by approximately 42.5-45.0%, while data center flexibility alone provides approximately 2.1-5.4% gains. Coordinated operation increases feasible IT capacity from approximately 10.5-10.6 MW under BASE operation to 15.3-16.0 MW, corresponding to gains of approximately 45.9-50.8%; the 16.0 MW Inference result is limited by the adopted UPS reserve requirement. Benefits are strongly location dependent and influenced by workload flexibility, deferral duration, PUE, UPS energy and reserve requirements, and feeder loading. Under a combined adverse operating condition, FULL capacity decreases by only 3.4% relative to the nominal Mixed case while retaining substantial additional capacity over BASE.

0.08

From Grid to Chip: Power Architecture, Stability, and Flexibility of AI Data Centers

cs.ET cs.AReess.SY ·2026-09-10 ·Yubo Song, Rui Kong, Takuro Umihara, Pooya Davari, Frede Blaabjerg +1 more
hot direction similarity 0.67
Abstract · The manuscript has been submitted for review to IEEE Open Journal of Power Electronics

The rapid growth of artificial intelligence (AI) computing is transforming data centers into large, dynamic electrical loads. Their deployment is primarily constrained by energy availability and grid-connection capacity, which is further aggravated by the ability of power-delivery architectures, control systems, and computing workloads to operate reliably during fast grid disturbances. This article presents a technological perspective on AI data centers as grid-interactive computing systems. First, it reviews grid-integration bottlenecks, evolving connection policies, grid-code requirements, which has fostered new technological trends via spatio-temporal flexibility available through workload orchestration, cooling systems, on-site resources, and energy storage. Second, it maps the evolution of power-delivery architectures from medium-voltage grid interfaces to chip-level, discussing higher-voltage DC distribution, solid-state transformers, wide-bandgap devices, advanced chip-level power delivery, and liquid cooling. Third, it establishes a three-level stability framework spanning rack-level DC-bus dynamics, facility-level converter interactions, and system-level grid-coupled behavior. The framework connects dominant instability mechanisms, including constant power load effects, impedance interactions, forced oscillations, and operating-mode transitions, with suitable modeling, assessment, and mitigation approaches. Synthesizing these topics, this article highlights grid-to-chip co-design as a central requirement for scalable AI infrastructure, linking computing workloads, power-delivery systems, energy buffers, and grid operation.

0.27

Modeling and Stability of Power Systems With Coupled Data Center and Grid Dynamics

eess.SY ·2026-11-17 ·Guido Cavraro
similarity 0.66
Abstract

The growing deployment of data centers poses challenges for power-system operation. However, data centers possess flexible resources that can be leveraged to mitigate their impact on the grid and provide grid services. This paper develops a linear-affine dynamic model of a transmission network with multiple data centers, explicitly coupling electromechanical grid dynamics with data center power demand and computational backlog. Grid-aware computing policies are incorporated to represent how data centers adjust their computational power in response to grid frequency deviations and workload backlog. The proposed framework provides a tractable means of investigating the interactions between multiple data centers and the transmission grid and assessing the potential of flexible computing to support power-system stability.

0.25

Comparison of Open-Source PSCAD EMT Models for Large-Scale AI Data Centers in Smart Grids

eess.SY ·2026-11-17 ·Alex Chen, Ahmad Mohammad Saber, Deepa Kundur
similarity 0.66
Abstract · 5 pages, 2 figures, submitted to PESGM 2027

The rapid deployment of artificial intelligence data centers (AIDCs) introduces gigawatt-scale, highly nonlinear, and fast-varying electronic loads that challenge grid voltage regulation, frequency stability, and disturbance ride-through. Capturing their transient behavior during grid faults and rapid computational workload swings requires high-fidelity electromagnetic transient (EMT) simulations rather than root mean square models. However, limited methodologies exist to audit the component-level adequacy of EMT AIDC models. This paper proposes a software-agnostic, 41-point fidelity framework spanning 11 categories that synthesizes 37 criteria from an existing modeling guideline with four novel requirements: frequency ride-through compliance, disaggregated fan and chiller cooling loads, temperature-dependent thermal response, and DC information technology (IT) load representations. Applying this framework to the four publicly available AIDC models in PSCAD/EMTDC reveals varying degrees of completeness: while the models capture IT load transitions, uninterruptible power supplies, and transfer switches for bulk stability studies, critical gaps remain in electro-thermal cooling coupling, internal protective relaying, and site-level controls. Addressing these gaps will enable comprehensive protection coordination and ride-through compliance studies.

0.20