Abstract

Rapid power variations from artificial intelligence (AI) workloads pose frequency-security challenges for islanded data-center microgrids. This paper proposes a generator step- response-based framework to rapidly screen candidate load pro- files and derive frequency-secure operating limits for IT workload scheduling. Identified generator responses are superimposed to assess the cumulative frequency effects of successive load changes without repeated dynamic simulations. The framework identifies potentially unsafe intervals and determines allowable load magni- tudes, ramp rates, and minimum event spacing, while accounting for prediction uncertainty and governor limits. Validation on a 2.5 MVA islanded microgrid with eight generator configurations and 14 synthetic AI workload profiles shows that 94.75% of 40,208 assessment windows receive decisive screening labels, with no frequency-violating windows classified as secure.

Closest papers

Nearest neighbours by meaning across the whole index.

AIDC Microgrid Vulnerability Assessment Under Computing-Power Coordinated Attacks

eess.SY ·2026-08-11 ·Ze Yu, Hongwei Zhen, Chao Shen, Mingyang Sun
similarity 0.67
Abstract

The rapid growth of large language model (LLM) services is expanding AI data centers (AIDCs), increasing electricity demand and associated carbon emissions. Renewable energy integration can mitigate these impacts but also strengthens the coupling between AIDC loads and inverter-interfaced generation, creating cross-domain cyber-physical vulnerabilities. Specifically, adversarial AI requests alter AIDC power demand, whereas inverter control tampering modifies source-side dynamics, and their combined impact on system stability varies with generation forecast and demand response uncertainties. To this end, we propose an uncertainty-aware AIDC microgrid vulnerability assessment framework under computing-power coordinated attacks. First, the framework maps adversarial AI requests to AIDC power variations and represents uncertainties in attack-induced demand responses and photovoltaic (PV) forecasts through confidence-weighted realizations. Then, impedance based stability analysis combines these realizations with bounded inverter parameter tampering to construct attack reachable domains and identify critical attack time windows. Furthermore, a separate criterion identifies fixed coordinated attack vectors that retain destabilizing capability throughout each selected window. Case studies demonstrate that, unlike either attack component applied alone, coordinated attacks within identified critical windows induce sustained inverter frequency oscillations with peak absolute deviations exceeding 20% of nominal frequency, whereas the evaluated out-of-window response remains bounded. The proposed method further identifies critical attack windows and the associated coordinated attack vectors.

0.04

Data Center Load Accommodation under QoS and Checkpoint-Induced Frequency Security Constraints

eess.SY ·2026-10-16 ·Ruolan Cui, Ziang Liu, Chenxi Hu, Francis Yunhe Hou
benchmark similarity 0.64
Abstract · 10 pages

The rapid growth of artificial intelligence workloads is accelerating the expansion and grid interconnection of data centers (DCs). Existing data center load accommodation (DCLA) assessments primarily focus on grid and resource adequacy and often imply that greater workload flexibility always increases accommodable capacity. However, workload flexibility has a dual effect. Workload deferral and temporal shifting can alleviate network congestion, whereas synchronized checkpointing of training workloads can cause large and rapid load reductions, threatening frequency stability. Therefore, DCLA cannot be determined solely by grid adequacy. This paper develops an optimal DCLA method that jointly accounts for workload quality of service (QoS), checkpoint-induced frequency security (FS), and grid adequacy. First, a QoS-aware model characterizes workload-dependent flexibility while ensuring service feasibility. Second, checkpoint-induced FS constraints are developed for periodic and event-triggered power variations, with key frequency-security limits reformulated in algebraic form. Third, a two-stage lexicographic model is developed to maximize DCLA and minimizes the required energy storage (ES) deployment, and then optimizes system operation under the given DC and ES siting and sizing decisions. Case studies show that the proposed method avoids a 40.3% overestimation of DCLA compared with the grid-adequacy benchmark. QoS is the primary limiting factor, while checkpoint-induced frequency-security constraints become more restrictive as training workloads increase. These findings highlight that reliable DCLA should account for both its grid-support value and the associated QoS and FS risks.

0.16

Grid-Aware Assessment of Forced Oscillations from Spatially Distributed Large Loads

eess.SY ·2026-11-17 ·Min-Seung Ko, Hao Zhu
similarity 0.63
Abstract

This paper develops a unified analytical framework for assessing forced oscillations induced by spatially distributed large-load fluctuations to determine their grid-aware fluctuation magnitudes. Emerging computational loads, such as hyperscale datacenters, present cyclic power variations with dynamic impacts depending on the waveform characteristics, forcing frequency, and source location. Our grid-aware framework represents these fluctuations using deterministic harmonic and probabilistic spectral models, and analyzes the resulting bus-wise frequency deviations based on a generic grid frequency-response model. Deterministic, risk-aware, and band-based probabilistic severity measures are further developed to obtain admissible fluctuation limits under different assumptions on frequency and phase uncertainty. We also formulate a security-constrained (SC) optimization of locational fluctuation magnitudes among existing large loads, accounting for their aggregated frequency deviation level. Case studies on the IEEE 39-bus and 14-generator Australian systems validate the proposed severity measures and admissible limit analysis. The SC optimization results further show that distributing a given amount of aggregate fluctuation toward dynamically less sensitive locations can substantially reduce system-wide oscillation severity.

0.35

Privacy-Preserving Coordinated Operation of Power Grids and AI Data Centers: A Checkpoint-Aware Three-Phase Scheme

eess.SY ·2026-09-22 ·Ziang Liu, Ruizhang Yang, Xin Cui, Francis Yunhe Hou
similarity 0.62
Abstract · 10 pages

The rapid growth of large language model training and serving is driving AI data centers (AIDCs) toward gigawatt scale. Unlike conventional commercial loads, AIDCs possess significant operational flexibility through dynamic voltage and frequency scaling (DVFS) of training and inference workloads, while periodic model checkpointing can induce abrupt power drops and rebounds that erode operating reserves and increase transmission congestion risks. Coordinating AIDC operation with grid scheduling under these unique operational characteristics is challenging because grid and AIDC operators are generally unwilling to share proprietary data and decision-making authority. This paper proposes a hierarchical privacy-preserving coordinated operation scheme between the power grid and AIDCs to address this gap. The proposed scheme contains three phases. In Phase I, the grid operator computes a certified inner approximation of the AIDCs security region for subsequent coordination. In Phase II, the AIDC operator coordinates training and inference AIDCs to optimize workload allocation within the certified security region and generate power schedules and checkpoint alerts. In Phase III, the grid operator solves a checkpoint-aware two-stage robust optimal power flow (OPF) considering renewable generation and checkpoint uncertainties. By exchanging only compact interface information, the framework preserves the privacy of both grid and AIDCs, avoids frequent iterative communication, and enables secure coordination with guaranteed feasibility. Numerical studies on a modified IEEE 14-bus system and a modified NYISO system demonstrate the effectiveness, robustness, and security of the proposed framework.

0.19

AI Data Centers Meet Electrical Grids: A Review of Power Challenges and Coordinated Solutions

eess.SY ·2026-10-06 ·Mariam Mughees, Yuzhuo Li, Yize Chen, Yunwei Ryan Li
survey similarity 0.62
Abstract

Artificial intelligence (AI) workloads are creating large, power-electronic loads whose effects on power systems depend on location, temporal variability, controllability, and interactions with other loads and resources. Annual electricity consumption alone cannot capture these effects. This review examines how AI data centers affect power systems stability, renewable-energy integration, and low-carbon planning by tracing the power-delivery chain from accelerators and workloads through rack converters, uninterruptible power supplies (UPS), storage, and microgrids to the transmission point of interconnection. Reported oscillatory events and multi-gigawatt load transfers highlight how facility responses can amplify disturbances, while programmable workloads and controllable power converters offer opportunities for demand flexibility. Challenges and mitigation strategies are organized across device, rack, facility, and power systems levels, spanning millisecond-to-year timescales. A bandwidth-matching framework relates disturbances to the response capabilities of mitigation resources. The review distinguishes computational energy efficiency from power systems and sustainability outcomes: lower energy consumption per token does not necessarily reduce peak demand, electrical disturbances, or carbon emissions. It examines how coordinated workload scheduling, grid-interactive UPS systems, storage, high-voltage DC distribution, and flexible interconnection can support reliability, efficiency, and decarbonization. Key research needs include dynamic load models, high-bandwidth telemetry, carbon-and grid-aware scheduling, and mechanisms for valuing flexible computational demand.

0.08

Grid Demand Flexibility Assessment of AI Data Centers via Batch Workload Temporal Shifting

eess.SY ·2026-09-29 ·Suntao Su, Liang Du, Shengyi Wang
similarity 0.61
Abstract · 5 pages, 5 figures, conference

The rapid growth of artificial intelligence (AI) data centers has introduced new challenges to power system operation. As their power demand becomes larger and more variable, quantitatively characterizing their demand flexibility is increasingly important for effective power system coordination. However, heterogeneous workload characteristics and resource requirements make this flexibility difficult to characterize directly. This paper proposes a framework for assessing the grid-compatible demand flexibility of AI data centers via batch workload temporal shifting. An averaging-based resource usage processing method is developed to map fine-resolution CPU, GPU and memory usage into unified time intervals compatible with power system operation. A workload temporal scheduling model is then formulated to shift batch workloads while preserving execution continuity, delay constraints, and server resource capacities, and is coupled with a utilization-dependent server power model to translate workload scheduling decisions into server power demand. Two complementary flexibility metrics are evaluated: short-term peak demand shaving and the maximum duration of sustained power reduction. Numerical results based on real GPU cluster traces demonstrate that workload temporal shifting can provide quantifiable and grid-compatible demand flexibility for AI data centers with limited disruption to computing workloads.

0.13

Reshaping Checkpoint-Induced Power Variations Through Inference Workload Scheduling

eess.SY ·2026-11-09 ·Yu Ma, Ziheng Sheng, Anna Andriiko, Chau-Wai Wong, Jong Ha Woo +4 more
hot direction similarity 0.61
Abstract

Synchronous checkpoints in large language model training cause rapid power variations that challenge frequency regulation in islanded data-center microgrids. This paper proposes a checkpoint-aware two-layer framework that schedules flexible inference workloads to compensate for checkpoint-induced disturbances. Using measured GPU power profiles and anticipated checkpoint power deficits, the upper layer coordinates heterogeneous task selection and launch times, while the lower layer adjusts the batch sizes of newly launched tasks online to correct power-tracking errors. Early launching (EL) and staged retirement (SR) further smooth power transitions at checkpoint onset and recovery, respectively. PSCAD/EMTDC simulations with reference checkpoint drops of 1-3 MW demonstrate reductions of 41.6-61.6% in maximum absolute frequency deviation and 68.5-89.6% in mean absolute frequency deviation relative to no scheduling. Battery energy storage system (BESS) peak charging power and charging energy decrease by 65.1-100% and 89.7-100%, respectively. These benefits exceed those of greedy scheduling when GPU resources are relatively abundant.

0.23

TuneBench: Benchmarking AI Agents for Power System Dynamic Model Calibration

eess.SY ·2026-11-03 ·Andrea Pomarico, Salvatore Tessitore, Giorgio Giannuzzi, Alberto Berizzi
benchmarkcode/data similarity 0.61
Abstract

Large Language Model (LLM)-based agents can automate complex engineering workflows by interacting with tools, interpreting feedback, and making iterative decisions. This paper introduces TuneBench, a benchmark for evaluating Agentic AI in power system dynamic model calibration, where controller parameters are adjusted to reproduce target dynamic responses. The benchmark reflects a common Transmission System Operator (TSO) practice, in which equivalent models used for Dynamic Security Assessment (DSA) are calibrated against measurements from grid-code compliance tests when proprietary models are unavailable. Two cases of increasing complexity are considered: the governor and Automatic Voltage Regulator (AVR) of a synchronous generator and the control system of a Battery Energy Storage System (BESS), both tuned against active-power and voltage step tests within a budget of 15 simulations. LLM-based agents are compared with random search and Genetic Algorithm (GA) baselines over 10 independent runs. Only the most advanced models, Opus 5.5 and GPT-6, accurately reproduce all target trajectories, with median R2 above 0.995 in every test and tracking errors up to two orders of magnitude lower than the baselines. The agent logs show that these agents autonomously extract dynamic performance indices, such as settling time and damping, and relate them to specific control parameters, decomposing the tuning problem into physically interpretable sub-problems. The benchmark is publicly available at https://github.com/Power-Agent/PowerAgentBench/tree/main/benchmarks/dynamic/level3.