System operators will probably allow virtual power plants (VPPs) to submit their feasible region (FR) for market clearing and dispatch. A VPP needs to determine its FR to submit as a whole based on the individual operation model of its internal distributed energy resources (DERs), which is an FR aggregation problem. Existing FR aggregation approaches rely on analytical methods, which have issues with generality and adaptability. In this paper, we propose a data-driven approach to approximate the energy-regulation FR of VPPs. It adopts the virtual battery model to approximate the aggregate FR of a VPP and determines the model parameters through inverse optimization based on generated multi-scenario operation data using the original operation model. Numerical tests verified the accuracy of the proposed method. We believe that our work helps to better leverage the flexibility of DERs.

Comment
Published in: 2024 IEEE Power & Energy Society General Meeting (PESGM)
DOI
10.1109/PESGM51994.2024.10689111

Closest papers

Nearest neighbours by meaning across the whole index.

Real-Time Operation Strategy of Virtual Power Plants With Optimal Power Disaggregation Among Heterogeneous Resources

eess.SY ·2026-08-27 ·Qixin Chen, Ruike Lyu, Hongye Guo, Xiangbo Su
publishedhot directionhighly cited similarity 0.68
Abstract · Accepted by Applied Energy

The virtual power plant (VPP) can aggregate flexible resources on the demand side to provide frequency regulation for the grid, helping address the supply-demand balance challenges. When deploying regulation, the VPP disaggregates the requested power adjustment in real time among its internal heterogeneous resources. Achieving optimal power disaggregation in this process is challenging due to the temporal coupling characteristics of the resources, the uncertain regulation signals, and the requirement for fast response. Therefore, existing research relies on heuristic methods, such as proportional disaggregation, and fails to leverage the heterogeneity of multiple resources. Here, we propose an optimal operation strategy for VPPs to provide regulation, exploiting the complementary characteristics of heterogeneous resources by prioritizing the use of low-cost resources while considering temporal coupling. To reduce the computational overhead of online deployment, we further propose a fast disaggregation algorithm to eliminate the reliance on optimisation solvers. We conducted case studies on the operation of a VPP composed of resources including thermostatically controlled loads and industrial production processes. The results verified the reduced operation cost and increased profit of the VPP under the proposed strategy, with only milliseconds of online computation time. We believe that our work can help better exploit demand-side flexibility.

0.62

Co-optimizing Bidding and Power Allocation of an EV Aggregator Providing Real-time Frequency Regulation Service

eess.SY ·2026-08-25 ·Ruike Lyu, Hongye Guo, Kedi Zheng, Mingyang Sun, Qixin Chen
top venuehighly cited similarity 0.65
Abstract · Published in: IEEE Transactions on Smart Grid ( Volume: 14, Issue: 6, November 2023)

The rapidly expanding scale of electric vehicle (EV) fleets and continuously decreasing battery costs are making vehicle-to-grid services a reality. In this paper, we study the interaction between the problems of an EV aggregator's bidding in the regulation market and power allocation (i.e., determining the (dis)charging powers of the EVs in regulation deployment). Although the two problems are coupled, they are often regarded as decoupled and optimized separately for complexity issues. However, failing to consider the coupling of bidding and power allocation can lead to a decline in the profit of the EV aggregator (EVA). In this paper, we propose a framework for co-optimizing EVA bidding and power allocation in the regulation market. The bidding model is formulated as a stochastic programming problem with embedded power allocation in discretized regulation signal scenarios. To meet the solution time requirement for regulation deployment, we further propose a power allocation model that can be solved online. It utilizes the Lagrange multipliers from the bidding problem to ensure that the allocation results correspond to the optimal solution of the bidding problem. The effect of the proposed framework on improving EVA profits and reducing degradation costs is verified in the case study.

0.67

Integrating Fast-response Capability into Virtual Power Plant Operation for Ancillary Services

eess.SY ·2026-08-26 ·Qixing Liu, Ruike Lyu, Zhe Zhai, Yan Shen, Xue Liu +1 more
published similarity 0.65
Abstract · Published in: 2025 IEEE Kiel PowerTech

Virtual power plants (VPPs) can aggregate distributed energy resources (DERs) to provide ancillary services for power systems, creating new profit opportunities. Ancillary services such as secondary frequency regulation require providers to have sufficient response capability to follow rapidly changing control commands. If overlooking the response requirement, the VPP will not be able to accurately measure its regulation capability, reducing its earnings in performance-based markets or risking disqualification. This paper integrates the requirement for fast-response capability into the operational framework of VPPs providing ancillary services. We leverage historical control commands to formulate chance constraints in the bidding model, mandating that the VPP's fast-response capability meets the requirement of ancillary services with a specified probability. Case studies verify that considering fast-response capabilities can enhance VPP operation.

0.62

Resource-Aware Rolling-Horizon Controller for Renewable-Based Virtual Power Plants Providing Automatic Frequency Restoration Reserves

eess.SY ·2026-09-25 ·Marco Vinicio Avendaño-Caiza, Juan Diego Rios-Peñaloza, Javier Roldán-Pérez, José Luis Rodríguez-Amenedo, Milan Prodanovic
similarity 0.64
Abstract · Submitted to a scientific journal for possible publication. 10 pages, 11 figures

Virtual power plants (VPPs) are an effective solution for increasing the penetration of renewable energy sources (RES) in power systems. Moreover, VPPs can provide ancillary services if generators and loads are closely connected and properly coordinated. This aspect has been addressed in several studies, yet they mostly focus on the dispatch optimisation level, leaving real-time operation aspects unresolved. To close this gap, a central controller for VPPs based on a rolling-horizon optimisation is proposed in this work. Its main objective is to maximise revenues while delivering frequency restoration services. A day-ahead optimisation firstly defines the power setpoint and the upward and downward reserves of the VPP. Then, the rolling-horizon optimiser, executed every minute, distributes the power and reserve references between the VPP units to achieve their close tracking while taking into account resource availability (wind speed, irradiance, etc.), operational constraints and battery degradation. The effectiveness of the controller is tested using a two-area interconnected power system under different RES generation and demand profiles. The simulations are performed in MATLAB/Simulink and include detailed dynamic models of the VPP elements, demonstrating the applicability of the algorithm to real systems. The day-ahead and the rolling-horizon optimisation problems are modelled using YALMIP and solved using Gurobi. The obtained results demonstrate the VPP supporting grid frequency restoration by optimally allocating its resources, even under the presence of forecast uncertainty.

0.18

Fair Dynamic Operating Envelopes using Distributed Multi-Period Optimal Power Flow and Jain Index for Active Distribution Networks

eess.SY cs.CE ·2026-08-24 ·Pedro Salomão Quessongo, Daniel Gebbran, Clodomiro Unsihuay-Vila
similarity 0.63
Abstract · 10 pages, submitted to CLAGTEE 2026 Conference

Dynamic operating envelopes (DOEs) are increasingly used to publish time-varying export limits that keep distribution networks within operational limits. Purely technical DOE allocation, however, can systematically privilege electrically favorable prosumers, while embedding fairness directly into a single-period optimal power flow (OPF) objective mixes network feasibility, equity and efficiency in a way that obscures the cost of fairness. This paper proposes a two-stage, multi-period framework that addresses both of these. Initially, a technical distributed OPF computes network-feasible export envelopes. The subsequent stage then applies a dynamic aggregate export budget and redistributes capacity through cumulative proportional fairness, limiting the additional curtailment by an admissible efficiency budget. The resulting fair DOEs are treated as first-stage decisions, while battery storage provides scenario-dependent recourse under demand and renewable uncertainty. The operational problem is solved by a calibrated regional alternating direction method of multipliers (ADMM) on a lossless LinDistFlow model and independently validated using AC power flow. We observe a trade-off between increases in curtailment \emph{versus} improvements on fairness, as expected, reaching Jain fairness indices close to unity. Results show that considering both storage (which alleviates curtailment impact) and multi-period fairness (which increases curtailment) is an interesting approach for modern DOE design, which in turn requires a multi-period, co-designed approach.

0.51

Optimal Coordination of Multiple Ancillary Service Provisions in Active Distribution Networks

eess.SY ·2026-11-14 ·Xinbao Jia, Yi Guo, Ognjen Stanojev, Zhen Chen, Yuning Jiang +1 more
similarity 0.63
Abstract · 16 pages

We propose a multi-rate model predictive control (MPC) framework for coordinating primary frequency control (PFC), automatic generation control (AGC), and voltage control (VC) in active distribution networks. The framework allocates distributed energy resource (DER) flexibility among these three ancillary services while retaining their different update rates. To account for the intertemporal flexibility of electric vehicle aggregations and aggregations of buildings with thermostatically controlled loads (TCLs), we incorporate time-varying power-energy envelopes into our multi-rate MPC formulation. These constraints couple the combined PFC and AGC response to the demand-side flexibility available later in the prediction horizon. Furthermore, the input-multirate structure enables coordinated ancillary service provision by DERs with different response dynamics. The controller optimizes the three services together, allowing fast regulation to be coordinated with the developing slow response within the available DER flexibility. We demonstrate the coordinated provision of the three ancillary services through closed-loop simulations on a modified IEEE 33-bus system using a nonlinear differential-algebraic model.

0.25

Computationally Transparent Power Flexibility Aggregation via Directional Support Evaluation

eess.SY ·2026-10-21 ·Mingyu Zhai, Liang Du, Yue Chen
similarity 0.62
Abstract · Preprint. Submitted for journal review

The growing penetration of distributed energy resources (DERs) creates new opportunities for improving resource adequacy, operational flexibility, and power-system reliability. However, efficiently characterizing the aggregate flexibility of heterogeneous DER portfolios remains challenging because of high dimensionality, diverse operating dynamics, and spatio-temporal coupling constraints. This paper proposes a computationally transparent framework that formulates aggregate flexibility characterization as a sequence of linear programming (LP)-based directional support evaluations. The framework accommodates heterogeneous DER technologies and configurable device-, feeder-, and portfolio-level constraints. The convex hull of the resulting boundary trajectories provides a feasible inner approximation of the coupled aggregate power flexibility region. Theoretical analysis establishes feasibility and non-overestimation guarantees and characterizes the computational dependence on portfolio size, scheduling horizon, and direction budget. In the small-scale case, the proposed method produces tighter projected regions than box, zonotope, and Chebyshev inner-ball benchmarks and matches a dense directional reference within numerical tolerance using 16--64 construction directions. Large-scale simulations with up to 2000 DERs demonstrate approximately linear empirical runtime scaling with the portfolio size and direction budget over the tested ranges. The results establish a scalable and theoretically grounded approach for aggregate DER flexibility characterization.

0.27

Zero-Sum Power Factor Games

eess.SY math.OC ·2026-08-20 ·Cameron Khanpour, Samuel Talkington, Mathieu Dahan, Daniel K. Molzahn
similarity 0.62
Abstract

Variable active power injections arising from device behavior or compromised dispatch complicate voltage regulation in electric power networks with distributed energy resources (DERs). An operator can limit the resulting voltage deviations by remotely selecting DER reactive power parameters before observing the active power injections. IEEE Standard 1547-2018 specifies constant power factor as one such control mode, coupling each device's reactive power to its realized active power. Using a linear voltage model, we formulate the operator's decision as a robust minimax problem in which the operator minimizes the largest feasible aggregate voltage deviation. We solve this problem by expressing the power factor decisions through continuous reactive to active power ratios and exactly decomposing the payoff according to the signs of the voltage deviations. When every feasible voltage residual remains on its initial side of nominal, the resulting ratios cancel each injection's contribution and yield a closed form minimax strategy. We identify realistic DER ratings for which this strategy applies and quantify the regulation capacity lost under restricted power factor ranges. Numerical tests check the cancellation computation, solve the complete minimax problem directly at a representative DER rating, and compare the linear voltage predictions with nonlinear AC power flow.

0.23