CS Paper Radar

Resource-Aware Rolling-Horizon Controller for Renewable-Based Virtual Power Plants Providing Automatic Frequency Restoration Reserves

Marco Vinicio Avendaño-Caiza, Juan Diego Rios-Peñaloza, Javier Roldán-Pérez, José Luis Rodríguez-Amenedo, Milan Prodanovic

eess.SY ·submitted 2026-09-25 09:12 UTC · v1

Abstract

Virtual power plants (VPPs) are an effective solution for increasing the penetration of renewable energy sources (RES) in power systems. Moreover, VPPs can provide ancillary services if generators and loads are closely connected and properly coordinated. This aspect has been addressed in several studies, yet they mostly focus on the dispatch optimisation level, leaving real-time operation aspects unresolved. To close this gap, a central controller for VPPs based on a rolling-horizon optimisation is proposed in this work. Its main objective is to maximise revenues while delivering frequency restoration services. A day-ahead optimisation firstly defines the power setpoint and the upward and downward reserves of the VPP. Then, the rolling-horizon optimiser, executed every minute, distributes the power and reserve references between the VPP units to achieve their close tracking while taking into account resource availability (wind speed, irradiance, etc.), operational constraints and battery degradation. The effectiveness of the controller is tested using a two-area interconnected power system under different RES generation and demand profiles. The simulations are performed in MATLAB/Simulink and include detailed dynamic models of the VPP elements, demonstrating the applicability of the algorithm to real systems. The day-ahead and the rolling-horizon optimisation problems are modelled using YALMIP and solved using Gurobi. The obtained results demonstrate the VPP supporting grid frequency restoration by optimally allocating its resources, even under the presence of forecast uncertainty.

Comment
Submitted to a scientific journal for possible publication. 10 pages, 11 figures

Closest papers

Nearest neighbours by meaning across the whole index.

Real-Time Operation Strategy of Virtual Power Plants With Optimal Power Disaggregation Among Heterogeneous Resources

eess.SY ·2026-08-27 ·Qixin Chen, Ruike Lyu, Hongye Guo, Xiangbo Su
publishedhot directionhighly cited similarity 0.67
Abstract · Accepted by Applied Energy

The virtual power plant (VPP) can aggregate flexible resources on the demand side to provide frequency regulation for the grid, helping address the supply-demand balance challenges. When deploying regulation, the VPP disaggregates the requested power adjustment in real time among its internal heterogeneous resources. Achieving optimal power disaggregation in this process is challenging due to the temporal coupling characteristics of the resources, the uncertain regulation signals, and the requirement for fast response. Therefore, existing research relies on heuristic methods, such as proportional disaggregation, and fails to leverage the heterogeneity of multiple resources. Here, we propose an optimal operation strategy for VPPs to provide regulation, exploiting the complementary characteristics of heterogeneous resources by prioritizing the use of low-cost resources while considering temporal coupling. To reduce the computational overhead of online deployment, we further propose a fast disaggregation algorithm to eliminate the reliance on optimisation solvers. We conducted case studies on the operation of a VPP composed of resources including thermostatically controlled loads and industrial production processes. The results verified the reduced operation cost and increased profit of the VPP under the proposed strategy, with only milliseconds of online computation time. We believe that our work can help better exploit demand-side flexibility.

0.62

Approximating Energy-Regulation Feasible Region of Virtual Power Plants: A Data-driven Inverse Optimization Approach

eess.SY math.OC ·2026-08-26 ·Ruike Lyu, Hongye Guo, Qixin Chen
publishedhighly cited similarity 0.64
Abstract · Published in: 2024 IEEE Power & Energy Society General Meeting (PESGM)

System operators will probably allow virtual power plants (VPPs) to submit their feasible region (FR) for market clearing and dispatch. A VPP needs to determine its FR to submit as a whole based on the individual operation model of its internal distributed energy resources (DERs), which is an FR aggregation problem. Existing FR aggregation approaches rely on analytical methods, which have issues with generality and adaptability. In this paper, we propose a data-driven approach to approximate the energy-regulation FR of VPPs. It adopts the virtual battery model to approximate the aggregate FR of a VPP and determines the model parameters through inverse optimization based on generated multi-scenario operation data using the original operation model. Numerical tests verified the accuracy of the proposed method. We believe that our work helps to better leverage the flexibility of DERs.

0.63

Who Gets the Grid Capacity? Allocating Dynamic Access Among Multiple Virtual Power Plants

eess.SY ·2026-11-16 ·Nakul Sreekanth, Jun He, Andrew L. Liu, S. Sivaranjani
similarity 0.63
Abstract

Virtual power plants (VPPs) trade in the same wholesale market and share distribution lines and transformers, and uncoordinated, profit-maximizing VPPs can push a shared transformer past its thermal limit or drive a feeder voltage out of band. The utility, which only observes the front-of-the-meter net injection at each bus, must keep the network safe from that net injection alone. We allocate a 24-hour active and reactive operating envelope to each VPP by a Benders decomposition: the utility sets a trial envelope, each VPP solves its private convex portfolio problem, and the returned value and dual gradient become supporting cuts that rebuild its value function while its schedule, state, and cost stay private. The envelope carries the transformer's thermal state across hours, bounds a joint conditional value-at-risk over forecast uncertainty, and is re-optimized each hour with the current hour committed. On a reduced IEEE-13 feeder with real load and prices, an active-power-only implementation lowers the transformer's peak-temperature CVaR from 254 to 97\,$^\circ$C at a 28\% value give-up and holds the transformer below its limit where nameplate access breaches it.

0.35

Frequency-Security-Aware Real-Time Economic Dispatch with Data Center UPS Flexibility for Inertia and Primary Frequency Response Services

eess.SY ·2026-11-13 ·Shengyi Wang, Liang Du
hot direction similarity 0.62
Abstract

The increasing penetration of renewable energy and the rapid growth of AI data centers are introducing significant challenges to power system frequency security. There is an urgent need to identify grid-compatible resources capable of providing fast frequency support. This paper proposes a frequency-security-aware real-time economic dispatch (RTED) model that enables data center (DC) uninterruptible power supply (UPS) systems to provide steady-state power balancing, inertia response, and primary frequency response (PFR) services. Specifically, tractable analytical frequency-security constraints are derived and incorporated into the RTED framework through second-order cone programming (SOCP) formulation. The proposed model jointly optimizes energy, reserve, and inertia to minimize system operation cost while preventing under-frequency load shedding (UFLS). Numerical validation on a modified IEEE 39-bus system demonstrates that the proposed RTED model with UPS flexibility can economically support system operation and significantly improve frequency security under active-power deficit disturbances.

0.30

Coordinated Conservation Voltage Reduction and Network Topology Reconfiguration in Active Distribution Networks

eess.SY ·2026-10-12 ·Rida Fatima, Hassan Zahid Butt, Xingpeng Li
similarity 0.62
Abstract

Distribution networks rely on conservation voltage reduction (CVR) and network topology reconfiguration (NTR) to manage demand, distributed energy resources (DERs), and tighter operating margins. Yet these strategies are typically deployed independently, despite coupled effects on feeder voltages, losses, and loading. This paper addresses that gap by developing a day-ahead mixed-integer second order cone programming (MISOCP) framework that jointly optimizes feeder head voltage control and network reconfiguration. The formulation incorporates AC branch flow constraints, ZIP load models, DERs, battery energy storage systems, and multi substation radiality. Using modified IEEE 33 bus and 123 bus systems, four configurations isolate the individual and coordinated effects of CVR and NTR. On the 33-bus system under mixed ZIP loading, NTR reduces active energy loss by 2.50%, while coordinated operation reduces it by 2.91% relative to SDN and produces a 2.46% CVR induced active load reduction relative to SDNTR. Under constant impedance loading, coordinated operation reduces active energy loss by 17.65% relative to SDN, while CVR reduces active load by 14.61% relative to SDNTR. DER portfolio scaling shows a nonmonotonic coordinated load reduction response, strongest at 20% penetration and decreasing at higher levels. On the 123 bus system, NTR reduces losses by 19.3%, while CVR reduces voltage dependent load energy by 2.3 to 2.4%. Under loading stress, SDN becomes infeasible at 120% loading, whereas CEDNTR remains feasible. Overall, the results demonstrate complementary, operating condition dependent benefits shaped by load composition, DER portfolio scaling, feeder topology, voltage margins, and source constraints, highlighting the value of joint optimization.

0.29

Integrating Fast-response Capability into Virtual Power Plant Operation for Ancillary Services

eess.SY ·2026-08-26 ·Qixing Liu, Ruike Lyu, Zhe Zhai, Yan Shen, Xue Liu +1 more
published similarity 0.62
Abstract · Published in: 2025 IEEE Kiel PowerTech

Virtual power plants (VPPs) can aggregate distributed energy resources (DERs) to provide ancillary services for power systems, creating new profit opportunities. Ancillary services such as secondary frequency regulation require providers to have sufficient response capability to follow rapidly changing control commands. If overlooking the response requirement, the VPP will not be able to accurately measure its regulation capability, reducing its earnings in performance-based markets or risking disqualification. This paper integrates the requirement for fast-response capability into the operational framework of VPPs providing ancillary services. We leverage historical control commands to formulate chance constraints in the bidding model, mandating that the VPP's fast-response capability meets the requirement of ancillary services with a specified probability. Case studies verify that considering fast-response capabilities can enhance VPP operation.

0.62

Optimal Coordination of Multiple Ancillary Service Provisions in Active Distribution Networks

eess.SY ·2026-11-14 ·Xinbao Jia, Yi Guo, Ognjen Stanojev, Zhen Chen, Yuning Jiang +1 more
similarity 0.60
Abstract · 16 pages

We propose a multi-rate model predictive control (MPC) framework for coordinating primary frequency control (PFC), automatic generation control (AGC), and voltage control (VC) in active distribution networks. The framework allocates distributed energy resource (DER) flexibility among these three ancillary services while retaining their different update rates. To account for the intertemporal flexibility of electric vehicle aggregations and aggregations of buildings with thermostatically controlled loads (TCLs), we incorporate time-varying power-energy envelopes into our multi-rate MPC formulation. These constraints couple the combined PFC and AGC response to the demand-side flexibility available later in the prediction horizon. Furthermore, the input-multirate structure enables coordinated ancillary service provision by DERs with different response dynamics. The controller optimizes the three services together, allowing fast regulation to be coordinated with the developing slow response within the available DER flexibility. We demonstrate the coordinated provision of the three ancillary services through closed-loop simulations on a modified IEEE 33-bus system using a nonlinear differential-algebraic model.

0.25

Minimizing Grid Interconnection Capacity Requirements for AI Data Centers: A Developer-Side Planning Framework with Onsite Resources and Workload Flexibility

eess.SY ·2026-08-29 ·Hassan Zahid Butt, Rida Fatima, Xingpeng Li
similarity 0.59
Abstract

Securing grid interconnection capacity has become a bottleneck for AI data center projects and can take longer than constructing the facilities themselves. This mismatch can delay deployment for years, making early interconnection planning essential. This paper develops ICP-AI, an interconnection capacity planning framework from a data center developer's perspective. The framework minimizes grid import capacity under a prescribed onsite investment budget while jointly sizing photovoltaic (PV) and battery energy storage system (BESS) resources and scheduling deadline constrained workload flexibility. A secondary refinement fixes the minimum grid capacity and selects the minimum-investment PV-BESS portfolio among solutions that achieve that capacity. The framework is evaluated using monthly composite stress profiles across varying temporal assumptions, load shapes, flexible load fractions, and deferral windows. Results show that interconnection capacity reduction depends strongly on the planning environment: at a $100M budget, it is about 6% for the high load factor baseline, exceeds 10% under monthly average solar availability, and reaches 13.3% for a more diurnal load. At a $10M budget, 5% flexible load with a 1 h workload deferral window reduces BESS capacity from 15.30 to 4.87 MWh while increasing capacity reduction from 4.43% to 4.84%. To test sensitivity to temporal compression, the model is also solved over the full 8,760 h chronology, which preserves the main capacity and flexibility trends. Overall, ICP-AI quantifies the interconnection capacity and infrastructure substitution value of workload flexibility, providing an investment-interconnection frontier to support capital allocation and early project planning in constrained grid environments.

0.12