Benefits of Dynamic Thermal Rating for Distribution Transformers Under Accelerated Load Growth

Wenbo Wang, Killian McKenna, Francisco de Leon, Haowei Lu, Xin Fang

eess.SY ·submitted 2026-09-28 20:21 UTC · v1
unusual

Abstract

Dynamic Thermal Rating (DTR) has been widely applied to transmission lines for congestion management, but its potential for distribution transformers is less explored. By adjusting equipment ratings based on real ambient and operating conditions, DTR allows transformers to operate above conservative static nameplate values without compromising asset health. This paper evaluates how DTR can serve as a non-wires alternative to traditional upgrades in distribution systems facing accelerated load growth. Using an example feeder from the SMART-DS dataset, we compare conventional transformer replacement strategies against DTR-enabled operation with ambient-adjusted ratings. The results demonstrate that DTR can defer a significant number of transformer upgrades and reduce annual upgrade costs. More broadly, DTR is most effective in regions with pronounced weather diversity, peak demand occurring during cooler periods, or sustained load growth that would otherwise trigger costly reinforcements. These findings show that DTR is a practical and cost-effective option for utilities, provides both operational flexibility and investment deferral opportunities, and offers a foundation for developing distribution-level DTR programs.

Comment
5 pages, intend for conference

Closest papers

Nearest neighbours by meaning across the whole index.

Dynamic Line Ratings Counteract Transmission Investment Needs Driven by Climate Change

eess.SY ·2026-10-19 ·Megan Jones, Vladimir Dvorkin, Michael Craig
similarity 0.60
Abstract · 16 pages, 7 figures, supplementary information included, under review at Energy & Environmental Science

Rising temperatures due to climate change will reduce power system transmission capacity. This reduction will interact with an ongoing shift from static to time-varying transmission rating standards. Previous research has yet to disentangle the effects of changing rating standards and climates on investment decisions. We quantify transmission investment needs for the Western U.S. power system (WECC) through mid-century under climate change and three rating standards: static ratings (SLR), ambient-adjusted ratings (AAR), and dynamic line ratings (DLR). By embedding alternative rating standards and high-resolution future weather data into a generation and transmission expansion model, PyPSA-USA, we find WECC will lose 1-3% of its transmission capacity across potential future climates under static ratings by mid-century, necessitating a 1-5% increase in transmission investment. Adoption of AAR or DLR eliminates most (81-99%) of the adaptation-driven transmission capacity needs, and further reduces aggregate transmission investments (by up to 31%). Additionally, we demonstrate that planning with time-varying ratings does not increase investment variability for individual lines under climate uncertainty relative to planning with static ratings. Our results emphasize the value and practicality of considering alternative rating standards in climate adaptation planning.

0.26

Who Gets the Grid Capacity? Allocating Dynamic Access Among Multiple Virtual Power Plants

eess.SY ·2026-11-16 ·Nakul Sreekanth, Jun He, Andrew L. Liu, S. Sivaranjani
similarity 0.57
Abstract

Virtual power plants (VPPs) trade in the same wholesale market and share distribution lines and transformers, and uncoordinated, profit-maximizing VPPs can push a shared transformer past its thermal limit or drive a feeder voltage out of band. The utility, which only observes the front-of-the-meter net injection at each bus, must keep the network safe from that net injection alone. We allocate a 24-hour active and reactive operating envelope to each VPP by a Benders decomposition: the utility sets a trial envelope, each VPP solves its private convex portfolio problem, and the returned value and dual gradient become supporting cuts that rebuild its value function while its schedule, state, and cost stay private. The envelope carries the transformer's thermal state across hours, bounds a joint conditional value-at-risk over forecast uncertainty, and is re-optimized each hour with the current hour committed. On a reduced IEEE-13 feeder with real load and prices, an active-power-only implementation lowers the transformer's peak-temperature CVaR from 254 to 97\,$^\circ$C at a 28\% value give-up and holds the transformer below its limit where nameplate access breaches it.

0.35

A Critical Review of Grid Integration Challenges and Flexibility Opportunities for Large-Scale Data Centers

eess.SY ·2026-10-14 ·Bibek Dhakal, Manohar Chamana, Biswambhar Gayen, Jatendar Kumar, S M Shams Rahman +5 more
similarity 0.56
Abstract

The rapid proliferation of cloud computing and artificial intelligence workloads is fundamentally reshaping the magnitude, spatial concentration, and electrical characteristics of data center power demand. Data centers differ from conventional commercial loads because they combine high rack densities, converter-dominated interfaces, thermally coupled cooling, uninterruptible power supplies, programmable workloads, and increasingly complex behind-the-meter generation and storage within a single facility. This review examines their grid integration from utility and sustainable-energy perspectives across resource planning, large-load interconnection, distribution feeders, market operation, real-time dynamics, power quality, and asset management. Particular attention is given to distribution-level issues that receive limited treatment in broader energy reviews: bidirectional operation on renewable-rich feeders, harmonic propagation and resonance, ride-through and reconnection, transformer derating, cable ampacity, neutral-conductor heating, protection, and measurement. Static, composite, physics-based dynamic, calibrated, impedance, electromagnetic transient, and hybrid load models are compared according to study purpose and data requirements, and utility coordination platforms, uninterruptible power supply and battery control, workload flexibility, renewable co-location, cogeneration, fuel cells, thermal storage, and clean firm supply are assessed. The central finding is that requested peak demand and annual energy matching alone cannot establish reliable or sustainable integration. Credible assessment must consider hourly and locational supply, network deliverability, marginal emissions, lifecycle and water impacts, backup obligations, rebound, asset health, and verified operating capability.

0.12

Price-Optimized EV and Heat-Pump Scheduling Can Exceed Uncoordinated Feeder Peaks

eess.SY ·2026-10-05 ·Tatjana Hein, Lukas P. Wagner, Alex Bernhard, Felix Ocker
publishedcode/data similarity 0.55
Abstract · Accepted at 2026 IEEE IES ONCON

Electric vehicles and heat pumps add large, time-flexible loads to low-voltage feeders. When each household independently minimizes its own charging cost against the same electricity price, this flexible demand piles into the cheapest hours, and the resulting synchronization can stress the feeder more than uncoordinated operation does. This work quantifies that effect on a rural low-voltage feeder with photovoltaics (97 buses, 250 kVA transformer) in 913 simulation runs that compare seven strategies across four seasons, device penetrations of up to 90 %, 208 price weeks from 2022-2025, and heterogeneous heat pumps. At 30 % penetration of each device, this decentralized cost minimization drives the transformer to 253 % of rated capacity, more than three times the peak of non-optimized Fixed-random charging with the same mobility and charged energy, and 478 % with electric vehicles alone at 90 % penetration, with undervoltage at the far end of the longest feeder arm. It exceeds Fixed-random and Fixed-times charging in every winter, spring, and autumn price week, and each 30 pp of heat-pump penetration raises its peak by about 110 pp, twelve times as much as without optimization. Centralized peak minimization removes all demand-driven violations. In the heat-pump-free summer case at 60 % photovoltaics, midday reverse power flow sets a transformer floor of 128.9 % that no strategy undercuts, since no commuting electric vehicle is at home at the export peak. With a time-variable grid fee added to the spot price, the weekly peak of decentralized cost minimization falls into the reduced-fee window in 99 of the 104 fee-active price weeks, compared with 53 without the fee, while keeping at least 89.8 % of its height, so the fee relocates rather than removes the synchronization. The simulation and optimization code is available at https://github.com/lukas-wagner/SynchronizationEffectsAnalysis.

0.64

Dynamic and Risk-Aware Procurement of Fast Frequency Response from Electric Vehicles and Heat Pumps

eess.SY ·2026-11-18 ·Savvas Panagi, Fanourios Kourougianni, Andreas Olympios, Chrysovalantis Spanias, Petros Aristidou
similarity 0.54
Abstract

Low-inertia power systems increasingly rely on Fast Frequency Response (FFR) to keep the frequency nadir above under-frequency load-shedding thresholds without oversized Frequency Containment Reserve or synchronous inertia. This paper proposes two complementary methodologies that interface with an existing day-ahead FFR capacity market. On the Transmission System Operator (TSO) side, a dynamic procurement rule maps forecasted kinetic energy and contingency magnitude onto an offline neighborhood-need surface, yielding interval-wise FFR capacity requests rather than constant seasonal or annual volumes. On the aggregator side, a risk-aware, TSO-certifiable bidding strategy quantifies reliable FFR capacity from fleets of electric vehicles (EVs) and heat pumps (HPs) by offering lower conditional quantiles of day-ahead headroom at a prescribed delivery reliability. The resulting requests and offers are cleared through a pay-as-bid capacity auction. A Cyprus 2025 case study shows that dynamic neighborhood-based procurement yields an annual clearing cost of about EUR 476,000, which is 30%-33% lower than the seasonal and annual static rules and also below the UFLS VoLL of EUR 637,500 estimated from the fifteen real 2025 events with fmin <= 49 Hz. EV and HP offers meet their target delivery reliabilities, and RMS validation finds 46 of 50 operating points above 49 Hz at both full and 85% FFR delivery.

0.25

Impact of Data Center Load on Co-Optimized Generation and Transmission Expansion Planning with Embedded Unit Commitment

eess.SY ·2026-10-13 ·Haoxiang Wan, Xingpeng Li, Jonghwan Kwon
published similarity 0.52
Abstract · 6 pages, 2 figures, 3 tables. Accepted to the 2027 IEEE Texas Power and Energy Conference (TPEC)

The rapid growth of hyperscale data centers challenges grid expansion planning, yet existing studies focus largely on operational flexibility rather than long-term investment decisions. This paper examines how large data center loads sited at multiple buses affect co-optimized Transmission Expansion Planning (TEP) and Generation Expansion Planning (GEP). The problem is formulated as a multi-year, Unit Commitment (UC)-embedded mixed-integer linear program on the modified IEEE 24-bus Reliability Test System (RTS-24) with Electric Reliability Council of Texas (ERCOT)-calibrated renewable energy profiles. A 500 MW data center load, about 17.5% of the base-year peak, is allocated across four buses by voltage level, generation headroom, renewable co-location, and network connectivity. Integrating this load raises the 15-year net present value of total system cost by 1,794 million USD (+61.6%) and the system-average locational marginal price (LMP) by 45.2%, with operating cost dominating capital investment (84.2% versus 15.8%). Renewable curtailment remains negligible: existing renewables are already near full utilization, so the added demand is served almost entirely by incremental thermal generation. Most notably, the load shifts the optimal plan from transmission-only to generation-only, replacing the base-case 230 kV reinforcement with a new 400 MW combined-cycle gas turbine and showing that strategically sited generation can substitute for network reinforcement.

0.47

Data-center growth impacts household electricity costs more through wholesale prices than through grid reinforcement

eess.SY econ.GN ·2026-11-11 ·Lingdong Zhou, Wenjia Xia, Jiyu Wang, Fei Ding, Xiangqi Zhu
hot direction similarity 0.52
Abstract · 22 pages, 8 figures, 1 table. Lingdong Zhou and Wenjia Xia contributed equally to this work

Rapid data-center expansion is raising concerns about electricity affordability, yet how the costs of serving these large new loads reach residential customers remains poorly understood. Here, we quantify the potential impact of 371 announced Texas data-center projects, totaling 38.9 GW by 2030, on residential electricity costs by linking power system expansion, wholesale electricity markets, transmission reinforcement, and retail cost allocation. We find that accommodating this demand increases modeled residential electricity costs in one representative case by 1.64 cents/kWh, with 68% arising from higher wholesale electricity prices and 32% from regulated transmission charges. Allowing new gas generation near data centers reduces the 2023 residential cost increase to 0.92 cents/kWh, whereas excluding data centers from the transmission cost-sharing base raises it to 1.87 cents/kWh. These findings reveal that the residential cost burden of data-center growth is driven primarily by wholesale electricity price increases, rather than direct transmission investment costs, and depends critically on generation siting, infrastructure planning, and cost allocation.

0.29

Exploiting the Benefits of V2B Application on Peak Shaving of Data Center Loads

eess.SY ·2026-08-31 ·Arya Joshi, Hamed Haggi, Chinmay Morankar
similarity 0.52
Abstract · Digest submission version for IEEE IAS Annual Meeting 2026

The accelerated growth in data center projects has introduced a demand-driven bottleneck throughout power grids and contributed to a substantial increase in carbon emissions. These concerns are fueling discussions on methods to use existing energy assets to drive operational efficiency. To this end, this paper explores the benefits of Vehicle-to-Building (V2B) applications to support peak shaving of data center cooling loads. Initially, a literature review was conducted considering V2B constraints and optimization methods including SoC limitations, EV participation, tariffs, and building loads. This analysis was then used to develop a conceptual case study of a 10 MW data center in Loudoun County, VA by simulating a temperature-dependent load profile and adjusting the V2B participation of 40 commercial and passenger EVs. Simulation results indicate that, depending on seasonal variations in cooling load demands, strategic deployment of V2B assets between 12-5pm can offset gross cooling loads by 13-36%.

0.17