Dynamic Line Ratings Counteract Transmission Investment Needs Driven by Climate Change

Megan Jones, Vladimir Dvorkin, Michael Craig

eess.SY ·submitted 2026-10-19 18:37 UTC · v1

Abstract

Rising temperatures due to climate change will reduce power system transmission capacity. This reduction will interact with an ongoing shift from static to time-varying transmission rating standards. Previous research has yet to disentangle the effects of changing rating standards and climates on investment decisions. We quantify transmission investment needs for the Western U.S. power system (WECC) through mid-century under climate change and three rating standards: static ratings (SLR), ambient-adjusted ratings (AAR), and dynamic line ratings (DLR). By embedding alternative rating standards and high-resolution future weather data into a generation and transmission expansion model, PyPSA-USA, we find WECC will lose 1-3% of its transmission capacity across potential future climates under static ratings by mid-century, necessitating a 1-5% increase in transmission investment. Adoption of AAR or DLR eliminates most (81-99%) of the adaptation-driven transmission capacity needs, and further reduces aggregate transmission investments (by up to 31%). Additionally, we demonstrate that planning with time-varying ratings does not increase investment variability for individual lines under climate uncertainty relative to planning with static ratings. Our results emphasize the value and practicality of considering alternative rating standards in climate adaptation planning.

Comment
16 pages, 7 figures, supplementary information included, under review at Energy & Environmental Science

Closest papers

Nearest neighbours by meaning across the whole index.

Benefits of Dynamic Thermal Rating for Distribution Transformers Under Accelerated Load Growth

eess.SY ·2026-09-28 ·Wenbo Wang, Killian McKenna, Francisco de Leon, Haowei Lu, Xin Fang
unusual similarity 0.60
Abstract · 5 pages, intend for conference

Dynamic Thermal Rating (DTR) has been widely applied to transmission lines for congestion management, but its potential for distribution transformers is less explored. By adjusting equipment ratings based on real ambient and operating conditions, DTR allows transformers to operate above conservative static nameplate values without compromising asset health. This paper evaluates how DTR can serve as a non-wires alternative to traditional upgrades in distribution systems facing accelerated load growth. Using an example feeder from the SMART-DS dataset, we compare conventional transformer replacement strategies against DTR-enabled operation with ambient-adjusted ratings. The results demonstrate that DTR can defer a significant number of transformer upgrades and reduce annual upgrade costs. More broadly, DTR is most effective in regions with pronounced weather diversity, peak demand occurring during cooler periods, or sustained load growth that would otherwise trigger costly reinforcements. These findings show that DTR is a practical and cost-effective option for utilities, provides both operational flexibility and investment deferral opportunities, and offers a foundation for developing distribution-level DTR programs.

0.27

Which wind and solar modelling choices matter? Effects on capacity factors, energy droughts and European power system configuration

eess.SY ·2026-10-29 ·L. Karkossa, A. Grochowicz, M. J. Koivisto, A. Hahmann, M. VIctoria
similarity 0.60
Abstract

Europe's future power system will rely heavily on wind and solar power and must remain resilient during prolonged periods of low wind and solar generation, known as variable renewable energy (VRE) droughts. To capture such rare events, adequacy assessments increasingly draw on decades of weather data, but the conversion of weather into power is largely treated as fixed. It remains unclear which modelling choices in this conversion matter for representing these droughts, and whether they matter as much as the weather itself. Here we systematically compare these choices side by side (bias correction, wind speed extrapolation, capacity layouts, turbine and photovoltaic configurations, and wake losses) and trace their effects through VRE droughts to the design of a net-zero European power system, using 85 years of reanalysis data. We find that modelling choices barely change how often VRE droughts occur or when the system is stressed. They do, however, determine how much capacity is needed to withstand that stress. By altering the electricity delivered during droughts, they shift required capacity by up to 480 GW, which is comparable to the spread across the most critical weather years. Modelling exercises should therefore use multiple weather years; bias-correct and regionally validate weather inputs; explicitly represent resource heterogeneity, forward-looking technologies, and wake losses; and judge these choices by their effect on the low-generation tail, not only on the mean.

0.24

U.S. Data Center Growth Through 2030: A Critical Review of Grid Adequacy and Transmission Expansion Planning

eess.SY ·2026-11-10 ·Babak Porkar, Mona Ghassemi
hot direction similarity 0.59
Abstract

The growth of large data centers raises questions about both supply adequacy and the suitability of load representations used in connection studies. This paper critically reviews the U.S. demand, generation, and transmission outlook through 2030 and examines the implications for transmission expansion planning (TEP). Comparison of public forecasts highlights distinctions among annual average demand, peak demand, and grid connection capacity. National generating-capacity totals cannot establish a dependable surplus because resource availability, regional adequacy, transmission constraints, and project timing determine supply capability. Recent grid events and published dynamic studies demonstrate that faults can trigger substantial data-center transfers to backup supply, followed by delayed or coordinated demand recovery. These behaviors require appropriate representation within the conventional planning framework, alongside assessment of the requested maximum grid import. The selected literature reveals limited integration of validated data-center dynamic models into the technical screening and economic comparison of expansion alternatives. The review identifies the need to establish whether fault response and recovery change feasible connection capacity, required reinforcement, or the preferred transmission investment.

0.35

Time to AC-t: When AC-transmission changes capacity expansion planning

eess.SY math.OCphysics.soc-ph ·2026-11-02 ·Lara Booth, Shiva Madadkhani, Ruaridh Macdonald, Priya L. Donti
code/data similarity 0.57
Abstract · 35 pages, 5 figures, 3 tables; plus 16 pages of supplemental information (8 figures, 6 tables). Submitted to Joule

Capacity expansion models often dramatically simplify the physics of how power flows through a transmission network in order to preserve computational tractability. However, with the rapid growth of electrification, large loads, renewables, and storage, increased realism in planning future grids is imperative. We extend the open-source capacity expansion model GenX with AC optimal power flow physics, and analyze generation, storage, and transmission investment decisions for 20-zone, hourly models of Germany and Texas. We compare our results against those using two common approximations, the transport model and DC optimal power flow. We find that total costs and emissions largely agree across all formulations. However, we find substantial differences in outputs related to transmission, generation siting, storage, and reactive-power support between the approximate formulations and the true AC physics formulation. We identify where AC physics changes planning decisions and discuss how to potentially capture these effects without the full computational cost.

0.23

Virtual Transmission Lines from Data Center Workload Migration: Coordinated Multi-Year Transmission Expansion Planning

eess.SY ·2026-10-09 ·Mengxin Zhu, Qian Kai, Yadong Liu, Yingjie Yan, Haoyu Zhao
similarity 0.55
Abstract

The rapid growth of electricity demand from AI data centers is creating a dual mismatch in power systems: a temporal mismatch between fast-rising demand and slow transmission expansion, and a spatial mismatch between concentrated data-center loads and geographically dispersed renewable resources. These mismatches can exacerbate transmission congestion, resulting in unserved data-center load and renewable-energy curtailment. This study models geographic workload migration as a virtual transmission line (VTL) that changes nodal data-center demand without transferring physical electricity. A mixed-integer linear programming model is then developed to co-optimize multi-year candidate-line construction and workload migration, subject to construction delays, renewable-energy curtailment, unserved data-center load, workload-balance requirements, communication-bandwidth constraints, and link-latency limits. The model is evaluated over an eight-year planning horizon on a modified IEEE 14-bus system. The results show that coordinating VTL with physical transmission expansion reduces total system cost, unserved data-center load, and renewable-energy curtailment while alleviating transmission congestion. VTL-aware planning also requires one fewer candidate line than build-only planning. However, VTL alone cannot meet system demand and does not eliminate the need for physical transmission reinforcement. Sensitivity analysis indicates that VTL provides the greatest value when transfer capacity is tight, construction costs are high, load growth is rapid, and data-center flexibility is greater. Additional validation on the IEEE 118-bus system over a five-year planning horizon shows that coordinated planning retains its cost and reliability benefits while reducing physical expansion requirements.

0.06

Co-Optimization of Network Topology and Variable Impedance Devices under Dynamic Line Ratings Using Iterative McCormick Relaxation

eess.SY ·2026-10-27 ·Junseon Park, Hyeongon Park, Rahul K. gupta
benchmark similarity 0.55
Abstract

Grid Enhancing Technologies (GETs), such as Network Topology Optimization (NTO), Dynamic Line Rating (DLR), and Variable Impedance Devices (VIDs) are increasingly deployed in power transmission grids to address congestion and improve grid utilization. However, their growing adoption necessitates coordinated operation to fully exploit their benefits. This paper presents a unified co-optimization framework that integrates NTO, DLR, and VID to alleviate congestion and minimize operational costs. NTO is modeled using a node-breaker formulation to provide enhanced switching granularity, while DLR incorporates weather-dependent parameters, including wind speed and ambient temperature, to dynamically adjust transmission limits. The resulting formulation is a mixed-integer nonlinear program due to power flow constraints with bilinear VID terms, and discrete topology decisions. To improve tractability, we propose using a McCormick relaxation approach to linearize bilinear terms. Furthermore, we propose an iterative refinement of the McCormick relaxation scheme to enhance solution accuracy. The proposed framework is validated through detailed analyses on the IEEE 118-bus system, along with additional case studies on other benchmark systems to assess scalability. Results demonstrate that the proposed approach improves solution accuracy compared to standard McCormick relaxation, achieves solution quality close to the nonlinear formulation, and maintains computational efficiency.

0.29

Impact of Wind-Solar-Battery Growth on Electricity Prices: Reserve Scarcity and Transmission Congestion

eess.SY ·2026-11-14 ·Haoxiang Wan, Ivan Castillo, Xingpeng Li
similarity 0.55
Abstract · 7 pages, 3 figures, 2 tables. Submitted to IEEE GECA 2027

This paper asks whether sequential wind, solar, and battery storage additions that eliminate unserved energy also remove modeled reserve scarcity and transmission congestion. Thirty-one cumulative portfolio states are evaluated on a modified IEEE 24-bus system for a constructed stressed day using a 24-hour day-ahead unit commitment model with network constraints, co-optimized energy and upward reserve, chronological battery storage, and an approximation of the Electric Reliability Council of Texas operating reserve demand curve. The thermal baseline has 106 MWh of unserved energy, whereas 450 MW of wind is sufficient to serve all demand. However, with 1,500 MW of wind, the hourly modeled reserve scarcity price still reaches \$5,000/MWh because wind output declines after the system peak. Adding 1,800 MW of solar reduces the load weighted daily average modeled reserve scarcity price from \$1,136.2/MWh to \$101.2/MWh and confines modeled reserve scarcity to three evening hours. Adding 250 MW/1,000 MWh of battery storage further lowers the average to \$4.3/MWh and reduces wind curtailment from 631 MWh to 306 MWh. Transmission congestion nevertheless remains: all residual wind curtailment occurs at bus 21, wind capture prices at buses 21 and 23 differ by \$31.8/MWh, and identical battery storage plants yield normalized net energy market revenues of \$201/(MW$\cdot$day) and \$121/(MW$\cdot$day) at buses 19 and 21, respectively. These results show that unserved energy, modeled reserve scarcity, and locational congestion effects measure distinct operating conditions and should be evaluated separately but interpreted together.

0.35

Impact of Data Center Load on Co-Optimized Generation and Transmission Expansion Planning with Embedded Unit Commitment

eess.SY ·2026-10-13 ·Haoxiang Wan, Xingpeng Li, Jonghwan Kwon
published similarity 0.54
Abstract · 6 pages, 2 figures, 3 tables. Accepted to the 2027 IEEE Texas Power and Energy Conference (TPEC)

The rapid growth of hyperscale data centers challenges grid expansion planning, yet existing studies focus largely on operational flexibility rather than long-term investment decisions. This paper examines how large data center loads sited at multiple buses affect co-optimized Transmission Expansion Planning (TEP) and Generation Expansion Planning (GEP). The problem is formulated as a multi-year, Unit Commitment (UC)-embedded mixed-integer linear program on the modified IEEE 24-bus Reliability Test System (RTS-24) with Electric Reliability Council of Texas (ERCOT)-calibrated renewable energy profiles. A 500 MW data center load, about 17.5% of the base-year peak, is allocated across four buses by voltage level, generation headroom, renewable co-location, and network connectivity. Integrating this load raises the 15-year net present value of total system cost by 1,794 million USD (+61.6%) and the system-average locational marginal price (LMP) by 45.2%, with operating cost dominating capital investment (84.2% versus 15.8%). Renewable curtailment remains negligible: existing renewables are already near full utilization, so the added demand is served almost entirely by incremental thermal generation. Most notably, the load shifts the optimal plan from transmission-only to generation-only, replacing the base-case 230 kV reinforcement with a new 400 MW combined-cycle gas turbine and showing that strategically sited generation can substitute for network reinforcement.

0.47