AC Assessment of DC Power Flow Screening for Data Center Hosting Capacity and Siting

Haoxiang Wan, Jesus Silva-Rodriguez, Jonghwan Kwon, Xingpeng Li

eess.SY ·submitted 2026-11-14 20:15 UTC · v1
hot direction

Abstract

A screening procedure based on direct current (DC) power flow estimates the data center hosting capacity of a candidate bus, termed the DC-screened capacity, and selects the generator commitment that supports it. This paper assesses that estimate under the alternating current (AC) network model. With the selected commitment fixed, an AC optimal power flow reoptimizes dispatch and voltages to find the largest data center load the bus can carry, termed the AC-assessed capacity. On a synthetic Texas system with 123 buses, the DC-screened capacity exceeds the AC-assessed capacity at 113 buses. Across all 123, the ratio of DC-screened to AC-assessed capacity has a median of 143% (a 43% overestimate) and a maximum of 1,070%. At these 113 buses, the DC-screened capacity violates a branch apparent power limit or a generator reactive power limit in the AC model, two limits the DC model omits. The overestimate changes decisions: a 1-GW project passes DC screening at every bus but exceeds the AC-assessed capacity at 37, and the bus ranked first by DC screening has 205.5 MW less AC-assessed capacity than the bus ranked second. Reporting the AC-assessed capacity beside each DC-screened capacity lets planners reject oversized projects or choose better sites.

Comment
5 pages, 5 figures, 1 table. Submitted to the 2027 IEEE PES General Meeting

Closest papers

Nearest neighbours by meaning across the whole index.

Mitigating the Grid Impact of Gigawatt-Scale AI Data Centers via High-Fidelity Model Flexibility

eess.SY math.OC ·2026-11-18 ·Eihab E. E. Ahmed, Saeed Manshadi
hot direction similarity 0.68
Abstract

Gigawatt-scale artificial intelligence data centers (AIDCs) are being connected at a single point of interconnection (POI) faster than transmission can be reinforced, yet studies of their flexibility rely on DC power flow and simplified load envelopes that omit voltage, cooling dynamics, and workload deadlines. This paper addresses this gap by embedding a high-fidelity AIDC model, with separate inference and training pools, hall thermal mass, PV, a battery energy storage system (BESS) with reactive capability, and a STATCOM, in a five-minute multi-period AC optimal power flow. Simulations on the RTS-GMLC test system show that active-power flexibility mitigates local price spikes and relieves congestion, whereas reactive support from the BESS inverter or a STATCOM is needed to keep the POI voltage away from sagging around its 0.95~pu limit. Sensitivity analyses show that cost-driven charging of large batteries can induce new morning congestion and that storage largely substitutes for wider workload deferral.

0.30

Impact of Security Modeling Fidelity on Hyperscale Data Center Hosting Capacity Assessment

eess.SY ·2026-10-13 ·Haoxiang Wan, Linhan Fang, Jonghwan Kwon, Jesus Silva-Rodriguez, Jianyi Yang +3 more
published similarity 0.68
Abstract · 5 pages, 2 figures, 1 table. Accepted to the 2027 IEEE PES Grid Edge Technologies Conference & Exposition

This paper assesses hyperscale data center hosting capacity in transmission grids. Hosting capacity (HC) analysis quantifies the maximum additional load a bus can accommodate without violating operational constraints. This paper defines data center HC as the maximum time-invariant active power demand at a single target bus over a 24-hour peak-day horizon, and evaluates it under four models of increasing fidelity (i.e., the extent to which the model enforces real-world operational security requirements) on the modified IEEE 24-bus system: (i) DC optimal power flow (DC-OPF) without unit commitment (UC), (ii) basic SCUC (security-constrained unit commitment) without reliability constraints, (iii) SCUC with spinning reserve, and (iv) N-SCUC with both reserve and branch-contingency security. Comparing these models quantifies the impact of unit commitment, reserve requirements, and N-1 security on bus-level HC estimates. The N-SCUC yields an average HC of 444 MW; omitting N-1 security raises this to 532 MW, a 19.8% overestimation. The DC-OPF and basic SCUC models further overestimate HC, indicating a trade-off between model complexity and estimation accuracy.

0.60

Impact of Data Center Load on Co-Optimized Generation and Transmission Expansion Planning with Embedded Unit Commitment

eess.SY ·2026-10-13 ·Haoxiang Wan, Xingpeng Li, Jonghwan Kwon
published similarity 0.63
Abstract · 6 pages, 2 figures, 3 tables. Accepted to the 2027 IEEE Texas Power and Energy Conference (TPEC)

The rapid growth of hyperscale data centers challenges grid expansion planning, yet existing studies focus largely on operational flexibility rather than long-term investment decisions. This paper examines how large data center loads sited at multiple buses affect co-optimized Transmission Expansion Planning (TEP) and Generation Expansion Planning (GEP). The problem is formulated as a multi-year, Unit Commitment (UC)-embedded mixed-integer linear program on the modified IEEE 24-bus Reliability Test System (RTS-24) with Electric Reliability Council of Texas (ERCOT)-calibrated renewable energy profiles. A 500 MW data center load, about 17.5% of the base-year peak, is allocated across four buses by voltage level, generation headroom, renewable co-location, and network connectivity. Integrating this load raises the 15-year net present value of total system cost by 1,794 million USD (+61.6%) and the system-average locational marginal price (LMP) by 45.2%, with operating cost dominating capital investment (84.2% versus 15.8%). Renewable curtailment remains negligible: existing renewables are already near full utilization, so the added demand is served almost entirely by incremental thermal generation. Most notably, the load shifts the optimal plan from transmission-only to generation-only, replacing the base-case 230 kV reinforcement with a new 400 MW combined-cycle gas turbine and showing that strategically sited generation can substitute for network reinforcement.

0.47

Unlocking AI Data Center Interconnection Capacity Through Coordinated Grid and Data Center Flexibility

eess.SY ·2026-10-04 ·Rida Fatima, Xingpeng Li
similarity 0.63
Abstract

The rapid growth of AI data centers is creating concentrated electricity demands that can exceed available distribution network headroom and delay interconnection. This paper investigates whether capacity can be used effectively by coordinating flexibility on both sides of the interconnection. A day-ahead mixed integer second order cone programming framework maximizes feasible AI data center IT capacity using utility side conservation voltage reduction and network topology reconfiguration, together with data center workload shifting and reserve constrained uninterruptible power supply storage. Background feeder demand uses voltage dependent ZIP models, while the data center is modeled as constant power demand using Training, Inference, and Mixed workload profiles. A two-stage solution first maximizes interconnection capacity and then minimizes feeder losses for the retained capacity, with numerical relaxation screening. Studies on a 116-bus model derived from the IEEE 123-node feeder show that, at the constrained bus-60 connection point, grid side flexibility, driven almost entirely by network reconfiguration, increases feasible IT capacity by approximately 42.5-45.0%, while data center flexibility alone provides approximately 2.1-5.4% gains. Coordinated operation increases feasible IT capacity from approximately 10.5-10.6 MW under BASE operation to 15.3-16.0 MW, corresponding to gains of approximately 45.9-50.8%; the 16.0 MW Inference result is limited by the adopted UPS reserve requirement. Benefits are strongly location dependent and influenced by workload flexibility, deferral duration, PUE, UPS energy and reserve requirements, and feeder loading. Under a combined adverse operating condition, FULL capacity decreases by only 3.4% relative to the nominal Mixed case while retaining substantial additional capacity over BASE.

0.29

Steady-State Equivalent Circuit Model for Data Center Loads

eess.SY ·2026-08-18 ·Muhammad Hamza Ali, Peng Sang, Hyeon Woo, Hyein Kang, Sungyun Choi +1 more
similarity 0.62
Abstract

Planners currently represent data centers as aggregate constant-PQ or ZIP loads in steady-state interconnection and contingency studies. These aggregate models are computationally convenient. However, they obscure the electrical relationship between computational workloads, server utilization, and grid-side demand. They ignore the internal power-electronic conversion stages of IT loads and assume homogeneous workload distributions across the compute clusters. This hides operating-point-dependent converter losses and efficiency variations. We propose a steady-state equivalent-circuit model (ECM) for data centers, which explicitly builds circuit models for IT loads, power supply units, cooling, and auxiliary systems. For power supply units, the equivalent circuit model explicitly represents internal power-electronic conversion stages. For IT loads, we develop a utilization-dependent server power model, and we combine it with loss-aware ECMs of power supply units. This approach captures the grid-side impact of heterogeneous workload distributions while preserving compatibility with conventional power-flow analysis. We evaluate this data center ECM in large-scale transmission power flows, using Monte Carlo simulations under heterogeneous and homogeneous cluster utilization. In comparison with the fixed-efficiency constant-PQ model, the ECM predicts that the most stressed line exceeds its thermal limit in about 30% of Monte Carlo samples. The results further show that homogeneous server utilization overstates line-loading variability by 17%-46% relative to heterogeneous server utilization, depending on the intra-cluster workload correlation.

0.47

Time to AC-t: When AC-transmission changes capacity expansion planning

eess.SY math.OCphysics.soc-ph ·2026-11-02 ·Lara Booth, Shiva Madadkhani, Ruaridh Macdonald, Priya L. Donti
code/data similarity 0.62
Abstract · 35 pages, 5 figures, 3 tables; plus 16 pages of supplemental information (8 figures, 6 tables). Submitted to Joule

Capacity expansion models often dramatically simplify the physics of how power flows through a transmission network in order to preserve computational tractability. However, with the rapid growth of electrification, large loads, renewables, and storage, increased realism in planning future grids is imperative. We extend the open-source capacity expansion model GenX with AC optimal power flow physics, and analyze generation, storage, and transmission investment decisions for 20-zone, hourly models of Germany and Texas. We compare our results against those using two common approximations, the transport model and DC optimal power flow. We find that total costs and emissions largely agree across all formulations. However, we find substantial differences in outputs related to transmission, generation siting, storage, and reactive-power support between the approximate formulations and the true AC physics formulation. We identify where AC physics changes planning decisions and discuss how to potentially capture these effects without the full computational cost.

0.23

Assessing Data Center Hosting Capacity Considering Electromagnetic Transient Dynamics

eess.SY ·2026-11-11 ·Fan Jiang, Xingpeng Li
hot direction similarity 0.61
Abstract

Hosting capacity is commonly assessed with steady-state optimization, which leaves the dynamic response of the data center and the grid at the resulting operating point untested. This paper assesses candidate data center capacities by coupling a unit commitment (UC) model with electromagnetic transient (EMT) simulation. During the capacity search, the UC model determines the economic dispatch for each tested data center capacity, and the resulting operating points are tested for settling with the generators committed online by the UC model and after a selected synchronous generator outage. Three nested capacities are obtained: the optimization-based steady-state capacity, the dynamic pre-outage capacity, and the post-outage dynamic capacity, each bounded by the previous one. On a test system with a detailed data center model, both dynamic capacities fall well below the optimization capacity, and the ranking of connection locations changes with the assessment stage and with the outage. In the most severe outage case at each candidate bus, the capacity is about 30% below the steady-state capacity. Thus, the dynamic response of the data center and the grid should be part of the hosting capacity assessment, and the comparison of connection locations should be made on the post-outage dynamic capacity.

0.26

Service-Aware Hosting Capacity Assessment of Edge Data Centers with Workload Flexibility

eess.SY ·2026-10-13 ·Linhan Fang, Haoxiang Wan, Anurag Srivastava, Xingpeng Li
similarity 0.61
Abstract

The growing demand for edge computing, content delivery, and AI services is driving the interconnection of edge data centers (DCs) with distribution networks. Before interconnection, utilities evaluate how much DC capacity can be accommodated without violating feeder current and voltage limits. Fixed peak load representations can overlook service dependent demand patterns, cooling related facility demand, and delay tolerant computing tasks. This paper develops a hosting capacity (HC) assessment model for edge DCs with shiftable workload scheduling. Three representative types are considered: mobile edge computing (MEC), content delivery network (CDN), and AI DCs. Facility demand is modeled by combining fixed base demand, service driven demand, prescribed cooling-overhead coefficient, and a shiftable workload component. Workload execution is optimized under arrival causality, maximum delay, daily energy balance constraints, and the resulting active and reactive loads are embedded in a distribution power flow model. Compared with the baseline without load shifting, the maximum bus level HC gain on the IEEE 33-bus system reaches 4.46% for MEC DCs and 9.89% for AI DCs, while CDN case shows negligible gain under the assumed cache management windows.

0.28